<br /> '. 43~
<br /> .
<br /> 9/11/67
<br /> I Council Chamber
<br /> Eugene, Oregon
<br /> September 11, 1967
<br /> Regular meeting of the Common Council of the city of Eugene, Oregon was called to order at 7:30 p.m.
<br /> PDT on September 11, 1967 in the Council Chamber by His Honor Mayor Edwin E. Cone with the following
<br /> councilmen present: Dr. Purdy, Mrs. Lauris, Mr. McNutt, Mr. Anderson, Mrs. Hayward, Messrs. Lassen
<br /> and McDonald. Councilman Wingard was absent.
<br /> NEW BUSINESS
<br /> 1 Councilman McDonald said he has received many complaints concerning 18th between City Vmew and
<br /> -' Oak Patch Road, and asked about the status of the sewer and paving project. The Public Works Director
<br /> said problems have arisen because of extensive sewer construction, but with the traffic detour put into
<br /> today it is hoped work can be expedited. He said the project is about six weeks from completion and
<br /> the weather will determine its progress.
<br /> e 2 The City Manager said Councilmen Anderson, Purdy, and Lassen, selection committee, will meet
<br /> this week to choose the architect for the parking structure at 10th and Oak.
<br /> 3 The Council was notified a joint Council/Planning Commission meeting is scheduled for Monday noon
<br /> September 18, 1967, to (1) review some of the more controversial points of the new zoning ordinance,
<br /> and (2) review of those portions of the Community Goals report underlined as needing implementation.
<br /> 01 4 Bids, Danebo Fire Station, Opened September 8, 1967 were submitted as follows:
<br /> Tot al-1( A 1 t ern ate s
<br /> Bidder Bid ---1- 2 3 -1t --2 6
<br /> A & G $ 85,110 $ 900 $ 1,270 $ 4,600 $ 800 $ 625 $ 615
<br /> Chambers 85,217 600 1,446 4,528 800 483 650
<br /> B.Nelson 87,581 390 2,025 4,690 914 482 1,642
<br /> Ree 89,354 600 1,850 4,065 730 770 850
<br /> E. Shields 90,402 1,200 1,259 3,703 700 545 765
<br /> Moody 90,697 2,170 1,150 3,664 745 553 465
<br /> Lee-Built 90,766 1,054 1,923 4,709 822 676 832
<br /> Youel 91,058 715 1,798 4,798 808 698 498
<br /> *Total bid includes all alternates: 1 - Remove existing station 4 - Air conditioning
<br /> 2 - Deck and pool 5 - Fence
<br /> 3 - Hose tower 6 - Topsoil
<br /> Base Bid Only Base Bid Including Alternate 3 Only
<br /> A&G $ 76,300 A&G $ 80,900
<br /> Chambers 76,710 Chambers 81,238
<br /> B. Nelson 77 , 438 B. Nelson 82,128
<br /> Ree 80,489 Ree 84,554
<br /> Lee-Built 80,750 Lee-Built 85,459
<br /> I Youel 81,743 Moody 85,614
<br /> Moody 81,950 E. Shields 85,933
<br /> E. Shields 82,230 Youel 86,541
<br /> The City Manager explained $75,000 was budgeted for this building; the original cost estimated
<br /> was $71,000 before details of the hose tower were known. He recommended award of contract to
<br /> A&G Construction on their base bid of $76,300 plus Alternate 3, making a total cost for the
<br /> building of $80,900. With inclusion of architect's fees, construction insurance, and soil tests,
<br /> e the overall cost will be $87,314. He said in order to be able to proceed, $10,000 will have to
<br /> be transferred from the fire department automotive equipment fund and equipment now being used
<br /> in the old station could be used for another budget year releasing $2500 in the present budget.
<br /> Mayor Cone questioned the need for the hose tower requiring the additional $4600. It was ex-
<br /> plained the tower provides better air circulation than an inclined ramp and generally does a
<br /> better job than the electric cabinets so far as amount of hose which can be dried at a time
<br /> and in extending the life expectancy of the hose. William Wilson, architect, explained also
<br /> that the $4600 figure mainly represents appurtenances in the tower such as hose brackets,
<br /> ladder, framing, hoist, and catwalk. He said it would be very difficult for firemen on off
<br /> 'hours to construct a separate hose tower, as suggested by the Mayor. Mr. Wilson answered
<br /> several other questions concerning other alternates, and explained the per-square-foot cost
<br /> of $13.80 would be reduced to $12.30 if the site work amounting to $8520 is taken into con-
<br /> sideration. He said duct work will be installed in the entire building for air conditioning,
<br /> but at present the coil unit and controls would be provided for only the living side, with the
<br /> sleeping and study quarters to be air conditioned at some future time. Completion of the proj-
<br /> I ect would be expected in 90 to 120 days from the date of award of contract. Some discussion
<br /> took place with regard to possibility of reducing the size of the apparatus room, but Mr. Wilson
<br /> said the designed size is the minimum. The City Manager explained the building's potential
<br /> is to house four pieces of equipment.
<br /> Dr. Purdy moved seconded by Mr. Anderson to award the contract to A&G Construction on their base bid
<br /> of $76,300 plus Alternate 3 for the hose tower at $4600; to transfer $10,000 from the Fire Equipment
<br /> Fund and use $2500 budgeted this year for equipment; and ask Councilman Lassen to review the plans
<br /> and specifications before the contract is signed. Rollcall vote. All councilmen present voting aye,
<br /> e motion carried.
<br /> II 9/11/67 - 1 L.4
<br />
|