Laserfiche WebLink
<br />a. The corridors for underground utility lines shall be 20 feet wide for excavations or <br />pipes up to 10 feet below ground surface (bgs), 30 feet wide for excavations or <br />pipes from 10 to 15 feet bgs, and 40 feet wide for excavations or pipes deeper <br />than 15 feet bgs. Where two utility lines are cl~se to each other, the corridors for <br />the lines may overlap, but impacts for work on one line are allowed only within <br />the corridor width for that line, not the combined width of both lines. <br /> <br />b. The corridors for above ground utility lines shall be 10 feet wide for single pole <br />structures and 20 feet wide for double pole ("H-style") structures. <br /> <br />c. The utility corridors shall be centered on an existing utility line, extending an <br />equal distance (half the allowed width) on both sides, except for corridors for new <br />utility lines, which shall be located as specified in subsection d below. <br /> <br />d. Construction of new utility lines and new connections to existing utility lines <br />within wetlands designated for protection shall require an amendment of this plan <br />to change the designation from "protect" to "utility line corridor." Such <br />amendments will only be allowed where it is demonstrated that: <br /> <br />1) an alternatives analysis has concluded that locating the new utility line <br />within a protected wetland is the best alternative. The alternatives analysis <br />shall compare alternatives that are completely outside of protected <br />wetlands and compare them to any alternatives that impact protected <br />wetlands. The alternatives shall be evaluated by weighing engineering <br />requirements and total environmental impacts including impacts to <br />threatened and endangered species and their habitat, and to wetlands <br />designated in the Plan for restoration or protection. <br /> <br />2) the new construction cannot reasonably be constructed completely outside <br />of wetlands designated for protection as demonstrated in the above- <br />referenced altemati~es analysis; <br /> <br />3) the utility lines are located so as to reduce the impact to wetlands <br />designated for protection as much as possible, and in no case shall a <br />cumulative area greater than 1 acre be re-designated from "protection" to <br />"utility corridor" for a new utility line; <br /> <br />4) unavoidable impacts will be mitigated through restoration of the project's <br />entire impact area; <br /> <br />5) there are no impacts to wetlands from new utility lines installed within the <br />Willow Creek Natural Area; and <br /> <br />6) impacts to plant and animal species on lists 1 and 2 of the Oregon Natural <br />Heritage Program will not occur. <br />