Laserfiche WebLink
7. RECOMMENDED PLAN <br /> <br />7.6 Identification of Project Phasing <br /> <br />The recommended improvements identified in Table 7.5-1 form the basis for the <br />development of a 20-year project list. To develop the project list, the timing of individual <br />facility improvements had to be identified so that the overall regional wastewater needs <br />could be met without a deficit in capacity. For some of the recommended improvements, a <br />phased approach would provide flexibility in the level of improvements made. For example, <br />modifications to both the north and south aeration basins to convert them to a step-feed, <br />plug-flow air-activated sludge system with anoxic selectors do not have to be complete in <br />both basins to meet the initial capacity needs. These modifications could be phased so that <br />the south basin is modified initially, and the north basin is modified when future flow and <br />loads demand additional capacity, although from an operational standpoint, having both <br />basins configured the same would be simpler. A phased approach to constructing facilities <br />provides a more stable funding process, delays unnecessary capital investments until they <br />are needed, and allows for potential re-evaluation to implement appropriate future <br />technologies. Using this approach, the recommended improvements were broken down into <br />individual projects according to the facility needs over the planning period. For each project <br />component, a fact sheet was prepared that outlines the project name, project description, <br />project justification, project driver, and project trigger. The fact sheets are provided at the <br />end of this chapter. <br /> <br />7.7 Implementation Schedule <br /> <br />Using the project fact sheets, individual improvement projects were consolidated into <br />phases based on the project trigger, which defines when the project must come on line to <br />address capacity, regulatory, or other facility needs. Adjustments to the timing of some <br />projects were made so that large variations in annual capital improvement costs were <br />avoided. This was done without compromising facility needs and the approach resulted in a <br />relatively level cash flow requirement. The estimated cost of each phase is presented in <br />Table 7.7-1. The estimated total cost for the recommended improvements in all phases is <br />approximately $144,000,000. The anticipated projects and estimated project costs that are <br />packaged in each phase are summarized in Table 7.7-2. <br /> <br />The project costs estimated for each of the phases are order-of-magnitude estimates for <br />construction and non-construction in 2004 dollars. The accuracy of this type of cost estimate <br />typically ranges from -30 percent to +50 percent. Costs are based on 10 percent for <br />mobilization/demobilization, bonds, and insurance; construction contingency of 25 percent; <br />and engineering, legal, and administrative (ELA) of 25 percent. Construction costs are based <br />on previous cost estimates or bid tabulations from similar projects. Costs for individual <br />processes include site work, piping, electrical, I&C, and contractor markups. The 25 percent <br />construction contingency is intended to cover unidentified and/or unknown items such as <br />construction dewatering and subsurface structural support of buildings or structures. <br /> <br />The project phasing is shown in Figure 7.7-1, and represents the twelve initial project <br />phases. Figure 7.7-1 does not show offsite projects, such as the improvements to conveyance <br />pump stations, the SIWF, the Biocycle Farm, and the BMF facilities. Figure 7.7-2 shows the <br />project phasing required if the High-Rate Clarification alternative is required by DEQ. This <br /> <br />MWMC_7.0_REV4.DOC 7-13 <br /> <br /> <br />