<br />New Police Building and City Hall Remodel for Seismic Bracing & Third Courtroom
<br />City of Eugene - Central Services - Facility Management
<br />3/31/2009
<br />Predesign cost and Budget Estimate3
<br />Feasibilty analysis and construction cost estimating provided by Berry Architects PC, KPFF Consulting Engineers and Construction Focus, Inc.
<br />City Hall Upgrades
<br />2
<br />Total Project
<br />Construction
<br />1
<br />Install seismic bracing
<br />$4,452,119$6,010,361
<br />Remodel to add third Courtroom$730,738$986,496
<br />City Hall Upgrades Total$6,996,857
<br />$5,182,857
<br />Police Building in 2 phases
<br />South of City Hall SiteFormer Agripac Cannery Site
<br />22
<br />Total ProjectTotal Project
<br />ConstructionConstruction
<br />Phase 1 - Patrol Facility$12,627,913$17,047,683$11,667,848$15,751,595
<br />Phase 2 - EPD Admin, Investigations, Records etc.$12,800,069$17,280,093$13,854,743$18,703,903
<br />Police Building Total
<br />$34,327,776$34,455,498
<br /> - including Ph 1 & 2
<br />$25,427,982$25,522,591
<br />City Hall Remodel Sub-Total
<br />$5,182,857$6,996,857$5,182,857$6,996,857
<br />(from above)
<br />Total for Police Building & City Hall Projects
<br />$41,324,633$41,452,355
<br />$30,610,839$30,705,448
<br />notes:
<br />1) Seismic bracing to be conventional occupancy standard.
<br />2) Soft Costs are estimated at 26% of total project costs.
<br />3) Estimates are in 2009 dollars.