Laserfiche WebLink
<br /> <br /> <br /> <br /> <br /> <br /> <br />ATTACHMENT D <br />LCC Project Timeline <br /> <br />Lane Community College Downtown Campus building <br />January 15, 2010 <br /> <br />PROJECT SCHEDULE <br /> <br />PHASE 1. FEASIBILITY REPORT <br />2009 – Nov. Issue RFP for Project Manager <br /> Dec. Select Project Manager <br /> Begin 90 day Feasibility Report <br /> Issue RFP for Architect <br />2010 – Jan. Select Architect <br /> Mar. Presentation of Feasibility report to board of Education <br /> Apr. Enter into agreement with URA on land transaction <br /> <br />PHASE 2. DESIGN AND CONSTRUCTION DOCUMENTS PHASE <br />2010 May Issue RFP for Project Manager & Architect <br /> Issue RFP for Commissioning Agent <br /> June Select Project Manager, Architect and Commissioning Agent <br /> Finalize financing plan <br /> Issue RFP for CMGC firm (if CMGC delivery method is adopted) <br /> July Select CMGC firm <br />2011 April Complete Design & Construction documents phase work <br /> <br />PHASE 3. CONSTRUCTION AND MOVE-IN PHASE <br />2011 May Obtain building permit and start construction (if CMGC method is to be <br /> used) <br /> Put Contract documents out to bid (if Design-Bid-Build method is used) <br />2013 June Building reaches substantial completion <br /> July Install College purchased Furniture, Fixtures & Equipment <br /> Aug. Move people, supplies, etc. from existing Downtown Center to new <br /> building <br /> Sept. Start classes in new building <br /> <br /> <br /> <br /> <br /> <br /> <br /> <br /> <br /> Z:\CMO\2010 Council Agendas\M100125\S100125B-and att's A-D.doc <br />