Work Session: Finance Plan for Property Acquisition
Meeting Date: February 27, 2008 Agenda Item Number: B
Department: Central Services Staff Contact: Sue Cutsogeorge
www.eugene-or.gov Contact Telephone Number: 682-5589
ISSUE STATEMENT
The Urban Renewal Agency (URA) has directed the purchase of three properties within the West
Broadway redevelopment area. The URA Board is asked to consider the finance plan for acquisition of
the properties.
BACKGROUND
Agency Action History
The URA secured purchase options on properties within the West Broadway redevelopment area
between Willamette Street and Charnelton Street. The option terms and purchase prices associated with
each of the purchase options were negotiated independently based on each property owner’s individual
circumstances.
On December 10, 2007, the URA provided direction to pursue a development agreement for the Beam
Development project and to proceed with acquisition or assignment of the options on the Washburne
building, Centre Court building and adjacent hole, within the financial constraints of the current $33
million urban renewal district spending limit. Also on December 10, 2007, the URA provided direction
to proceed with acquisition of the Diamond property, also within the existing financial constraints of the
urban renewal district spending limit.
On February 11, 2008, the URA directed the Agency Director to … “bring back to the URA as soon as
possible a methodology for soliciting offers from parties interested in assignment of the purchase
options not being exercised by the URA with the first right to acquire the option to the tenant for the
value that the URA paid for the option, and if the tenant was not interested, to solicit offers from others
with some kind of provision that provides for a reasonable time frame for redevelopment after any
demolition, with serious consequences if that redevelopment does not occur. In addition, the City
th
Council directed the City Manager to convey ownership of the City-owned parking lot at 12 & Oak to
th
Diamond Parking as partial compensation for the URA’s acquisition of the Diamond property on 10 &
Olive Street.
On March 10, 2008, the council will consider the supplemental budget action necessary to move forward
with the purchase of the Centre Court building and adjacent hole ($2.8 million), the Washburne building
($1.9 million), and the Diamond property ($290,360).
F:\CMO\2008 Council Agendas\M080227\S080227B.doc
Financial Plan for Property Acquisition
The financial plan for the acquisition of the three properties is set out in the chart below. The Centre
Court and Washburne buildings would be purchased using a combination of a HUD Section 108 Loan,
BEDI grant and urban renewal tax increment funds. The Diamond property would be purchased using
tax increment funds.
Finance Plan for Property Acquisition
Sources of Funds Uses of Funds
HUD Section 108 Loan $ 2,731,000 Acquire CC & Washburne $ 4,700,000
BEDI Grant 691,000 Acquire Diamond 291,000
Urban Renewal Cash 2,295,000 Costs of Acquisition 126,000
Debt Service Reserve* 600,000
Total Sources $ 5,717,000 Total Uses $ 5,717,000
*Only if needed.
The URA is proposing to sell the Centre Court and Washburne properties to Beam and to finance
Beam’s acquisition of the property. Repayment of the HUD Section 108 Loan is proposed to come from
proceeds of a note associated with Beam’s purchase of the properties. Under this approach, HUD’s
security from the City for the Section 108 loan would be provided primarily from a lien on the real
estate, payments from Beam and additional guarantees from Beam. If necessary for HUD approval, the
Agency could also provide a debt service reserve account from tax increment funds as security for the
loan. (The chart above includes a placeholder for a $600,000 debt service reserve.) In the worst case,
HUD may require even more security for the loan. At that point, it might be necessary to pledge tax
increment funds to repay the loan. Until HUD receives the application and considers the finance plan,
the Agency will not know what is needed to secure HUD approval. This finance plan allows for the
Agency to use tax increment funds, if needed, to secure HUD approval.
The finance plan includes additional costs of acquiring the properties and negotiating a development
agreement with Beam. Costs of acquisition include a HUD fee for the Section 108 Loan, bank fees for
the Section 108 Loan, real estate closing costs and City Attorney fees.
Agreement with Beam
Prior to purchasing the properties, the Agency expects to enter into a purchase and sale agreement with
Beam. The agreement will set out the terms and conditions for redevelopment of the Centre Court and
Washburne properties.
Simultaneously with, or shortly after the Agency purchases the property, the Agency will sell the
property on a note to Beam. Beam’s payments will cover repayment of the City’s HUD Section 108
Loan and possibly the BEDI grant. Because the terms of the agreement with Beam have not yet been
determined, any estimates of the financial impact of the agreement are preliminary. Additionally,
preliminary negotiations with Beam indicate a need for construction financing that could come from the
remaining HUD Section 108 and BEDI funds.
HUD 108/BEDI Grant Requirements
The proposed use of HUD Section 108 and BEDI grant funds will qualify for compliance with HUD’s
national objective to address slums and blight on an area basis. In accordance with HUD regulations, no
more than $3,422,000 (30%) of the combined annual CDBG expenditures and HUD Section 108/BEDI
funds may be spent on activities which aid in the elimination of slums or blight. The 30% limitation
F:\CMO\2008 Council Agendas\M080227\S080227B.doc
currently inhibits the City’s ability to purchase the Centre Court and Washburn properties solely with
HUD Section 108 and BEDI funds. The City is in the process of exploring with HUD and the property
owners scenarios that would allow for the use of a greater amount of Section 108 and BEDI funds for
the purchases.
The BEDI grant money must be used in conjunction with a HUD Section 108 loan. The City may
access $1 of BEDI grant funds for every $3.95 drawn down in HUD 108 loan proceeds.
Other Requirements
The Urban Renewal Plan for the Downtown District requires that any project over $250,000 receive
approval from the URA Board. The URA Board gave approval for acquisition of the Diamond property
on December 10, 2007. The URA Board will give approval for the Beam project when the development
agreement parameters are presented in April. In addition to these approvals, the URA Board will need
to approve the budget for these acquisitions on March 10.
URA Financial Capacity for Other Projects
At the council meeting on December 10, staff presented rough estimates of the potential financial
capacity remaining for downtown development projects. The funding sources available for the projects
were urban renewal tax increment funds, the HUD Section 108 Loan, the BEDI grant and the Urban
Renewal Downtown Loan Program.
The remaining amount of urban renewal tax increment funds was based on an estimate of the remaining
amount available under the “maximum indebtedness” cap (the spending limit).
The Section HUD 108 Loan is only an additional amount of funding to the extent that urban renewal tax
increment funds are NOT used as a source of security or repayment for the loan. If urban renewal tax
increment funds are used in connection with the HUD Section 108 loan, then that amount would be
subtracted from the total available for downtown projects.
Since the December update, one additional potential source of funding has been identified. If the sale of
purchase options on the West Broadway properties net any proceeds, then those proceeds would be
available for additional financial participation in any downtown redevelopment projects.
The proposed property acquisitions (Centre Court and hole, Washburne and Diamond) would have the
following effect on the amount available for downtown redevelopment:
Downtown Redevelopment Financial Capacity
Approximate Property Amount
Funding Source Amount Available Acquisitions Remaining
Urban Renewal Tax Increment Funds $4,000,000 $(2,295,000) $1,705,000
HUD 108 Loan 7,895,000 (2,731,000) 5,164,000
BEDI Grant 2,000,000 (691,000) 1,309,000
Urban Renewal Loan Program 2,000,000 ?2,000,000
Proceeds from Sale of Purchase Options 230,000 ?230,000
Total Sources $16,125,0000 $(5,717,000) $10,408,000
F:\CMO\2008 Council Agendas\M080227\S080227B.doc
Preliminary negotiations with Beam Development indicate a need for URA financial participation. The
th
undefined project for the10 and Charnelton site may also entail URA financial participation. Any costs
for these projects would have to come out of the remaining amount shown in this chart, or the City
would have to find additional funds from other sources.
Timeline
As set out at the February 11 meeting, there are several steps to go through prior to closing on any
property acquisition, which is expected to occur by June 24. The timeline from the February 11
presentation is included as Attachment A.
RELATED CITY POLICIES
Future redevelopment of the West Broadway Redevelopment Area is consistent with the policies and
implementation strategies included in the Downtown Plan, including:
?
Downtown development shall support the urban qualities of density, vitality, livability and diversity
to create a downtown, urban environment.
?
Actively pursue public/private development opportunities to achieve the vision for an active, vital,
growing downtown.
?
Use downtown development tools and incentives to encourage development that provides character
and density downtown.
?
Promote multi-story, mixed-use structures downtown through financial incentives or code
amendments.
?
Stimulate multi-unit housing in the downtown core and on the edges of downtown for a variety of
income levels and ownership opportunities.
?
Provide and promote development and community events that reinforce downtown’s role as the
cultural center for the city and region.
?
Reinforce the creative, distinctive culture of downtown as the arts and entertainment center of the
city.
In addition, the future development of the West Broadway Redevelopment Area is responsive to the
following Growth Management policies:
Policy 1: Support the existing Eugene Urban Growth Boundary by taking actions to
increase density and use existing vacant and under-used land within the boundary
more efficiently.
Policy 2: Encourage in-fill, mixed-use, redevelopment, and higher density
development.
Policy 3: Encourage a mix of business and residential uses downtown using incentives and
zoning.
Policy 10: Encourage the creation of transportation-efficient land use patterns and
implementation of nodal development concepts.
Policy 14: Development shall be required to pay the full cost of extending infrastructure and
services, except that the City will examine ways to subsidize the costs of
providing infrastructure or offer other incentives that support higher-density infill,
mixed use, and redevelopment.
F:\CMO\2008 Council Agendas\M080227\S080227B.doc
–
This item is also related to one of the 2007-2008 Council Goals: Downtown InitiativeFacilitate
significant revitalization of downtown core.
URA OPTIONS
The URA Board can accept the finance plan as presented in this material, or propose an alternate finance
plan.
AGENCY DIRECTOR’S RECOMMENDATION
The Agency Director recommends including the necessary budget transactions to accomplish the
property acquisitions on Supplemental Budget #2 to be considered on March 10, 2008.
SUGGESTED MOTION
Move to direct the Agency Director to include the budget transactions necessary to accomplish the
property acquisitions in the Supplemental Budget to be considered on March 10, 2008.
ATTACHMENTS
A.Timeline from 2/11/08 work session
FOR MORE INFORMATION
Staff Contact: Sue Cutsogeorge
Telephone: 682-5589
Staff E-Mail: sue.l.cutsogeorge@ci.eugene.or.us
Staff Contact: Denny Braud
Telephone: 682-5536
Staff E-Mail: denny.braud@ci.eugene.or.us
F:\CMO\2008 Council Agendas\M080227\S080227B.doc