AGENDA ITEM SUMMARY
Work Session: Santa Clara Community Park Update
Meeting Date: May 18, 2005 Agenda Item Number: B
Department: Public Works Staff Contact: Andrea G. Riner
www. cl. eugene, or. us Contact Telephone Number: 682-4909
ISSUE STATEMENT
This is an update to City Council on the Santa Clara Community Park land acquisition project. The
update includes findings from the recent telephone survey and the property appraisals requested for the
Santa Clara and Laurel Hill Valley sites.
BACKGROUND
Funding for the acquisition of land to provide a community park for Santa Clara was included in the
1998 Parks and Open Space bond measure. Since that time, a preferred site has been identified and
property negotiations with the site owners, the McDougals, have proceeded. The land acquisition
strategy includes a revision of the City's Urban Growth Boundary to move 197 acres of land in Santa
Clara into the UGB and move 120 acres in the Laurel Hill Valley outside of the UGB. The difference,
77 acres in Santa Clara, would be donated to the City for parkland. In addition, the City would acquire
100 of the 120 acres in Laurel Hill to complete the Ridgeline Trail between Hendricks Park, Laurelwood
Golf Course, and Moon Mountain, for a price of $950,000. An additional 30 acres of Ridgeline open
space would be donated by the property owners to connect the site south to 30th Avenue and other public
open space.
Following City Council approval to initiate the Metro Plan amendment, a series of public workshops
were held in Santa Clara to further communicate the goals of the project, identify concerns and issues,
and develop a conceptual site plan aimed at addressing those concerns. Initial public involvement had
been conducted via a community advisory committee convened for three meetings in the summer of
2003. Due to the level of concern raised by those who attended the more recent workshops, a survey
was conducted to provide a better understanding of the level of public support or concern about the
project and related issues. A summary of the results of this survey, including staff analysis, is included
as Attachment A. The full survey report will be made available in the Council Office, and will be
placed on the Parks and Open Space web site on or before May 18.
In addition to the telephone survey, the council identified the need for additional information about
current property values and requested that appraisals of both the Santa Clara property and the Laurel Hill
Property be conducted. The appraisals for the Santa Clara site include an evaluation of the 77-acre
donation site as well as a discreet 40-acre piece that would not be acquired as part of an associated
development or land swap. A summary of the results of the appraisals are included in Attachment B.
L:\CMO\2005 Council Agendas\M050518\S050518B.doc
The land swap proposal was presented to the council at a November 24, 2003, work session, following a
preliminary executive session. In July 2004, the council approved a joint request from the City of
Eugene Parks and Open Space Division and the property owners to initiate a Metro Plan amendment.
The council requested appraisals of the two subject properties at a February 9, 2005, work session.
Also, following a question from Councilor Kelly, Parks and Open Space staff provided a response
outlining an initial evaluation of the alternative proposals presented by the Santa Clara Community
Organization. This council assignment was provided to the council in its May 5 council packet.
Financial/Resource Considerations
Financial resources for the Santa Clara Community Park include the 1998 Parks and Open Space bond
measure for land acquisition and Parks System Development Charge funding for park development.
Council Goals/Priorities
Acquisition of parkland can be related to a number of City Council goals, including sustainable
community development, healthy natural and built environment, and providing accessible and thriving
cultural and recreational opportunities.
Timing Issues
The current agreement between the City and the McDougals expires on July 1, 2005. Staff has received
a letter from the McDougals' representative Mike Evans indicating that while they support the project,
they recognize that the level of concern raised by area residents presents a challenge and that they intend
to let the agreement lapse unless substantial progress can be made in the near future. A copy of this
letter is provided as Attachment C.
RELATED CITY POLICIES
Related City policy documents include the 1998 Parks and Open Space bond measure, the 1989 Eugene
Parks and Recreation Plan, the 2004 Draft Parks, Recreation and Open Space Comprehensive Plan and
the 1998 Growth Management Study.
COUNCIL OPTIONS
The council may wish to consider the following options:
1. Proceeding with the development of findings for the Metro Plan Amendment land use process, as
needed to acquire land for a community park in Santa Clara and to obtain Ridgeline open space in
the Laurel Hill Valley.
2. Table the land swap/UGB expansion question. Continue discussions with the community to identify
priorities for community parkland in Santa Clara as identified within the Draft Parks, Recreation and
Open Space Comprehensive Plan.
3. Abandon the land swap proposal.
CITY MANAGER'S RECOMMENDATION
The City Manager recommends proceeding with the development of findings for the Metro Plan
amendment, which will allow the planning and analysis to prepare findings and will include addressing
the concerns raised by the public to date. This level of analysis is required as part of a Metro Plan
amendment process.
L:\CMO\2005 Council Agendas\M050518\S050518B.doc
SUGGESTED MOTION
No motion is required; this is a work session only.
ATTACHMENTS
A. Santa Clara Community Park Survey Results
B. Property Appraisal Information
C. Letter from Land Planning Consultants dated 4/19/2005
FOR MORE INFORMATION
Staff Contact: Andrea G. Riner
Telephone: 682-4909
Staff E-Mail: andrea.g.riner~ci.eugene.or.us
L:\CMO\2005 Council Agendas\M050518\S050518B.doc
ATTACHMENT A
Santa Clara Community Park Survey Results
The staff analysis of key survey findings and a copy of the Executive Summary of the consultant's
report are attached. The full report will be provided in the Council office and on the parks website.
Overview
The findings from the telephone survey are typical of the project to date - conflicting and complex.
While they do not give a resounding go-ahead for the proposed land swap, neither do they clearly say
the project should discontinue. While more people support the proposal than oppose it throughout
Eugene (combining all responses), there is a significant level of opposition, especially in 97404, and
general confusion. Table 1 provides a breakdown of support and opposition for the project according to
the location of the respondent (city-wide versus 97404 residents) and initial versus final opinions.
Table 1. Support of Support Opposition Undecided
:::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::: ::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::
Project Data (08 & Initial Ei~l Initial Eiffel Initial ~i~[
030) Support Opposition Undecided
"~ Eugene 36% ~% 19% 45%
'o o
~, o, Santa Clara
rY (Zip 97404) 38% S~0/° 26% ~% 36%
Project Awareness
Survey results show that there is a high level of awareness of the proposal. Generally speaking, when
compared to city-wide respondents, Santa Clara residents are more aware of the proposal and more
opposed (although not at the same rates). Of the respondents from Santa Clara, 66% were previously
aware of the proposal, with a city-wide awareness level of 50%. Survey results also show that the
sources of information differ between Santa Clara and city-wide respondents. Roughly 39% of Santa
Clara residents reported hearing of the proposal through either "neighbors, friends or family," or
"neighborhood meetings," compared with 18% of Eugene residents. These finding suggests that the
Santa Clara Committee for Sensible Parks and Open Space's (SCCSPOS) public outreach efforts had a
significant effect on the Santa Clara resident's awareness and understanding of the proposal.
Survey results also reveal that a core constituent of community parks - families with children - is
relatively unfamiliar with the project. Specifically, an analysis of results to Q5 of the survey states,
"Those with no children, those over 45, 97494 residents, and Santa Clara residents are more likely than
others to be aware of the proposed project."
Reasons for Opposition
The biggest concern for all respondents is the impacts of the added housing development that would
result from the land swap proposal, according to an analysis of open ended responses (Q40). The
arguments against the project seem to be based primarily on two fundamental issues: the desire to
preserve agricultural land and a general disapproval of development and developers. While traffic and
school impacts were also a concern, these were not sited as the major reasons for opposing the project.
Understandably, Santa Clara residents are much more concerned about the impacts of added traffic than
city-wide respondents.
L:\CMO\2005 Council Agendas\M050518\S050518B.doc
Reasons for Support
Survey results identified a variety of factors as compelling reasons to support the proposed project. The
factors most likely to make Eugene residents support the proposal include protection of forest and
stream headwaters, not net change of the Urban Growth Boundary, community involvement in project
development, and the knowledge that city services are already in place.
Ultimately, arguments in favor of the project are not as clear, again stemming from the complexity of
the project and the difficulty in identifying the multiple benefits of the project. For example, protecting
forest and headwater streams was one of the highest rated goals by Eugene residents. However, a
similar question about acquiring ridgeline open space was the lowest rated factor in question #30.
Obviously, these two goals were not seen as one and the same.
Potential Misunderstanding of Project
An important finding from the report is that certain questions in the survey may have been
misinterpreted. Results for all respondents show a dramatic increase from initial opposition to final
opposition (from 23% to 41%) to the proposal, as compared to the slight increase from initial support to
final support (from 37% to 38%). While this implies that additional information sways many of the
undecided respondents towards opposition of the project, other results suggest that confusion and
misunderstanding of the proposal heavily affected responses to Q39: "Now, after what you have heard,
would you support or oppose the proposed land trade, community park, and development of property in
Santa Clara?" The questions that may have been misinterpreted include Q 15, Q 16, and Q 18, which ask
respondents to determine how development scenarios, likely to occur without (instead of) the proposal,
affect their support for the proposal. The high rates of opposition in response to these questions
contradict responses to Q30 as well as Q40, which cite the impacts of additional housing development as
the primary reason for opposition.
The report notes that "regarding condemnation of land, it appears that people were rating the idea of
condemnation, rather than the idea that without the project, condemnation could occur. The same is true
for 'without the land trade proposal, the developer wants to develop the entire parcel with housing.' In
other words, a majority of participants stated that they would move towards opposing the land swap
proposal if they knew that without it government condemnation was involved. Clearly, participants
were actually expressing their strong opposition to condemnation as a land acquisition approach.
A likely cause of the confusion and an issue that has challenged staff from the beginning is that this
proposal does not translate well into easily understood "sound-bites". Hot button issues, such as
annexation, condemnation, agriculture, traffic, development and developers, trigger responses that are
disproportionate with other responses.
Important Actions
Survey results from Q30 determined the importance of various actions the City could take with regard to
the proposal. Community involvement in decision-making was rated as the most important factor. This
suggests that both opponents and proponents of the project want more opportunities in determining how
the development will look. Whether it has been made clear that the land swap approach provides the
most public involvement opportunities is not known. The next most important actions the City could
take are "minimizing traffic impacts to neighbors," and "preserving prime agricultural land." These
results provide useful direction to staff for refinement of the project approach.
L:\CMO\2005 Council Agendas\M050518\S050518B.doc
SANTA CLARA COMMUNITY PARK SURVEY
CONDUCTED FOR
THE CITY OF EUGENE
PARKS AND OPEN SPACE DIVISION
March, 2005
ADVANCED ~TING
RESEARCH INC.
P.O. Box 5244 · Eugene, OR 97405 · Phone/Fax 541-345-6600 · www.advancedmarketingresearch.com
2
TABLE OF CONTENTS
EXECUTIVE SUMMARY ................................................. 3
Purpose of the Study .......................................................... 8
Methodology ................................................................... 8
Quotas Observed .......................................................... 8
Response Rate .......................................................... 9
Tests for Differences Between Proportions ............................... 9
Notes on Chi Square .......................................................... 9
Bound on Error - Weighted Data ........................................ 10
Bound on Error - Unweighted Data ........................................ 11
Differences Between Percentage Points ............................... 12
ANALYSIS OF DATA ................................................. 13
Awareness of the Proposed Project ........................................ 14
Sources of Information ................................................. 15
Initial Support of the Proposal ........................................ 16
Effect of Various Factors ................................................. 17
UGB Would be Expanded ................................................. 18
Ridgeline Trail Would Move Outside UGB ............................... 19
Forest and Stream Headwaters Would be Protected ...................... 20
No Net Change ................................................................. 21
207 Acres for $1 Million ................................................. 22
City Budget is $1 Million ................................................. 23
Condemnation of Property ................................................. 24
Condemnation Would Cost More ........................................ 25
Development on Agricultural Land ........................................ 26
Developer Wants to Develop Entire Parcel ............................... 27
Only Developed Land Would Be Annexed ............................... 28
900 Homes and 10 Acres Commercial ............................... 29
Community Involvemem ................................................. 30
Progressive Design Methods ................................................. 31
City Services are in Place ................................................. 32
Traffic Would Increase ................................................. 33
Street System Could Handle Traffic ........................................ 34
Class Size Would Increase ................................................. 35
Least Parks Per Person in Santa Clara ............................... 36
No Other Parcels Available ................................................. 37
Support Changing the UGB? ................................................. 38
Importance of Factors .......................................................... 39
Final Support of Project ................................................. 40
Reasons for Opposition ................................................. 41
DATA TABLES .......................................................... 23
QUESTIONNAIRE INSTRUMENT
Advanced Marketing Research, Inc.
3
EXECUTIVE SUMMARY
Awareness of the Proposed Project (Q5)
50% of Eugene residents are aware of the proposed community park and neighborhood
development project in Santa Clara, near Prairie and Irvington Roads, while 66% of 97404
residents are aware of the proposed project.
Sources of Information (Q6)
73% of Eugene residents, and 65% of 97404 residents had heard about the proposal through news
media. 29% of 97404 residents (compared with 15% of Eugene residents) had heard about the
proposal from neighbors, friends, or family. (Note: "Eugene Residents" means 400 Eugene
residents, including 66 97404 residents.)
lnitial Support of the Proposal (Q8)
36% of Eugene residents would support or lean towards supporting a project where the City
would acquire land for a large park in Santa Clara, based on a land trade proposal with a
developer. 19% would oppose or lean towards opposing such a project (compared with 26% from
97404). 45% of Eugene residents are undecided, compared with 36% of 97404 residents.
Effect of Various Factors (Q9-Q28)
The most compelling reason to support the proposed project is that "purchasing the Ridgeline
Trail property would protect forest land and stream headwaters." Other factors that would cause
people to lean toward supporting the project are: "community members could be involved in how
the development would look," "the proposed development would incorporate design methods for
ease of living and functioning," ''there would be no change in the total amount of land available
for development inside the Urban Growth Boundary," "with the land trade proposal, the City
would obtain 207 acres of parks and open space for under $1 million," "the City bas a budget of
$1, million to buy park land in Santa Clara," and "city services such as water, power, sewer and
streets are already in place adjacent to the proposed development."
The most compelling reason to oppose the proposed project is that ''the project would allow a
housing development on prime agricultural land." Other factors that would cause people to lean
toward opposing the project are: "added housing would increase the size of classes in some
Bethel schools," ''the proposed development would include over 900 new homes and 10 acres of
commercial development in Santa Clara," and ''traffic would increase near the new park and
neighborhood."
Regarding condemnation of land, it appears that people were rating the idea of condemnation,
rather than the idea that without the project, condemnation could occur. The same is true for
"without the land trade proposal, the developer wants to develop the entire parcel with housing."
UGB Would Be Expanded (Q9)
36% of Eugene residents said knowing that ''the Urban Growth Boundary would be expanded to
include the park and a new housing development" would make them more likely to support, or
lean toward supporting the project, while 38% said this information would make them more likely
to oppose, or lean toward opposing the project.
Advanced Marketing Research, Inc.
4
Ridgeline Trail Would Move Outside UGB (Q10)
36% of Eugene residents said knowing that "Ridgeline Trail land in the south hills would be
moved outside the Urban Growth Boundary and purchased for parks as part of the proposal"
would make them more likely to support, or lean toward supporting the project, while 38% said
this information would make them more likely to oppose, or lean toward opposing the project.
Forest and Stream Headwaters Would Be Protected (Qll)
65% of Eugene residents (compared with 50% of 97404 residents) said knowing that "purchasing
the Ridgeline Trail property would protect forest land and stream headwaters" would make them
more likely to support, or lean toward supporting the project, while 16% (compared with 25% of
97404 residents) said this information would make them more likely to oppose, or lean toward
opposing the project.
No Net Change (Q12)
49% of Eugene residents said knowing that "there would be no change in the total amount of land
available for development inside the Urban Growth Boundary" would make them more likely to
support, or lean toward supporting the project, while 18% (compared with 26% of 97404
residents) said this information would make them more likely to oppose, or lean toward opposing
the project.
207 Acres for $1 Million (Q13)
50% of Eugene residents (compared with 43% of 97404 residents) said knowing that "with the
land trade proposal, the city would obtain 207 acres of parks and open space for under $1
million" would make them more likely to support, or lean toward supporting the project, while
24% (compared with 34% of 97404 residents) said this information would make them more likely
to oppose, or lean toward opposing the project.
City Budget is $1 Million (Q14)
52% of Eugene residents said knowing that ''the City has a budget of $1 million to buy park land
in Santa Clara" would make them more likely to support, or lean toward supporting the project,
while 26% (compared with 33% of 97404 residents) said this information would make them more
likely to oppose, or lean toward opposing the project.
Condemnation of Property (Q15)
16% of Eugene residents said knowing that ''without the housing development, acquiring the
targeted park site and ridgeline would involve government condemnation of property" would
make them more likely to support, or lean toward supporting the project, while 52% said this
information would make them more likely to oppose, or lean toward opposing the project.
Regarding condemnation of land, it appears that people were rating the idea of condemnation,
rather than the idea that without the project, condemnation could occur.
Condemnation Would Cost More (Q16)
18% of Eugene residents said knowing that "condemning the targeted park site and ridgeline
would cost more than the package proposed" would make them more likely to support, or lean
toward supporting the project, while 50% said this information would make them more likely to
oppose, or lean toward opposing the project.
Advanced Marketing Research, Inc.
5
Regarding condemnation of land, it appears that people were rating the idea of condemnation,
rather than the idea that without the project, condemnation could occur.
Development on Agrieultur~! Land (Q17)
17% of Eugene residents said knowing that "the project would allow a housing development on
prime agricultural land" would make them more likely to support, or lean toward supporting the
project, while 65% said this information would make them more likely to oppose, or lean toward
opposing the project.
Developer Wants to Develop Entire Parcel (Q18)
25% of Eugene residents said knowing that "without the land trade proposal the developer wants
to develop the entire parcel with housing" would make them more likely to support, or lean
toward supporting the project, while 51% (compared with 59% of 97404 residents) said this
information would make them more likely to oppose, or lean toward opposing the project.
Regarding the developer's intent, it appears that people were rating the idea of developing the
entire parcel of land, rather than the idea that without the project, the developer wants to develop
the entire parcel.
Only Developed Land Would Be Annexed (Q19)
38% of Eugene residents said knowing that "only the land sited for development would be
annexed as part of this project" would make them more likely to support, or lean toward
supporting the project, while 31% (compared with 38% of 97404 residents) said this information
would make them more likely to oppose, or lean toward opposing the project.
900 Homes and 10 Acres Commercial (Q20)
30% of Eugene residents said knowing that ''the proposed development would include over 900
new homes and ten acres of commercial development in Santa Clara" would make them more
likely to support, or lean toward supporting the project, while 50% (compared with 59% of 97404
residents) said this information would make them more likely to oppose, or lean toward opposing
the project.
Community Involvement (Q21)
55% of Eugene residents said knowing that "community members could be involved in how the
development would look" would make them more likely to support, or lean toward supporting the
project, while 21% (compared with 31% of 97404 residents) said this information would make
them more likely to oppose, or lean toward opposing the project.
Progressive Design Methods (Q22)
51% of Eugene residents said knowing that ''the proposed development would incorporate design
methods for ease of living and functioning" would make them more likely to support, or lean
toward supporting the project, while 21% (compared with 29% of 97404 residents) said this
information would make them more likely to oppose, or lean toward opposing the project.
City Services are in Place (Q23)
52% of Eugene residents said knowing that "city services such as water, power, sewer and streets
are already in place adjacent to the proposed development" would make them more likely to
support, or lean toward supporting the project, while 23% (compared with 34% of 97404
Advanced Marketing Research, Inc.
6
residents) said this information would make them more likely to oppose, or lean toward opposing
the project.
Traffic Would Increase (Q24)
27% of Eugene residents said knowing that "traffic would increase near the new park and
neighborhood" would make them more likely to support, or lean toward supporting the project,
while 42% (compared with 55% of 97404 residents) said this information would make them more
likely to oppose, or lean toward opposing the project.
Street System Could Handle Traffic (Q25)
41% of Eugene residents said knowing that "the street system in the area can accommodate traffic
increases resulting from the proposal" would make them more likely to support, or lean toward
supporting the project, while 27% (compared with 34% on 97404 residents) said this information
would make them more likely to oppose, or lean toward opposing the project. 9% of 97404
residents do not believe that the street system could handle the increased traffic.
Class Size Would Increase (Q26)
25% of Eugene residents said knowing that "added housing would increase the size of classes in
some Bethel schools" would make them more likely to support, or lean toward supporting the
project, while 53% said this information would make them more likely to oppose, or lean toward
opposing the project.
Least Parks Per Person in Santa Clara (Q27)
45% of Eugene residents said knowing that "Santa Clara has the least amount of park land per
person in Eugene" would make them more likely to support, or lean toward supporting the
project, while 24% (compared with 32% of 97404 residents) said this information would make
them more likely to oppose, or lean toward opposing the project.
No Other Parcels Available (Q28)
45% of Eugene residents said knowing that '`there are no other undeveloped parcels of land
available for a large community park in the Santa Clara area" would make them more likely to
support, or lean toward supporting the project, while 24% (compared with 33% of 97404
residents) said this information would make them more likely to oppose, or lean toward opposing
the project.
Support Changing the UGB? (Q29)
38% of Eugene residents support, or lean toward supporting changing the Urban Growth
Boundary in order to build a park and housing development in Santa Clam. 40% (compared with
47% of 97404 residents) oppose, or lean toward opposing such a change.
Importance of Factors (Q30)
Respondents were asked to rate the importance of various actions the City could take. The most
important action is providing opportunities for community involvement in decision-making,
followed by minimizing traffic impacts to neighbors, and preserving prime agricultural land.
Slightly less important are preserving wetlands, improving citizen access to parks and open space,
and providing recreation services to an area currently underserved. Of moderate importance are
maintaining the current Urban Growth Boundary, and acquiring ridgeline open space in the south
hills.
Advanced Marketing Research, Inc.
Final Support of Project (Q39)
After hearing all of the previous statements, the level of support of the proposal by Eugene
residents went t~om 36% to 40%, while the level of support by 97404 residents remained virtually
flat. The real shift was away from "undecided" toward "oppose." After the information, the level
of opposition by Eugene residents went from 19% to 37%, and by 97404 residents from 26% to
44%.
Reasons for Opposition (Q40)
The most widely-stated reason Eugene residents give for opposing the proposed project is the
development/developer/growth issue, followed by traffic. For 97404 residems, these two reasons
carry equal weight, followed by a lack of trust for the City.
Advanced Marketing Research, Inc.
SANTA CLARA COMMUNITY PARK SURVEY
FOR THE CITY OF EUGENE PARKS DEPARTMENT
March, 2005
PURPOSE OF THE STUDY
The purpose of this study is to assist the City of Eugene in measuring awareness of, and opinions
on, the proposed land trade, housing development, and community park project in Santa Clara.
METHODOLOGY
Advanced Marketing Research was hired to conduct the research project in order to obtain
unbiased and statistically valid results.
Using questions developed in partnership with City of Eugene Parks Department staff and
reviewed by key stakeholders, Advanced Marketing Research designed a questionnaire
instrument to be administered by telephone. Using a random list of residents living in Eugene as a
sampling frame, 400 interviews of 97404 residents, and 400 interviews with "Other Eugene"
residents, were completed. 97404 residents living both inside and outside city limits were
interviewed. "Other Eugene" residents living outside city limits were not included in the sample.
Telephone interviews were conducted between February 24 and March 16, 2005.
Proper data analysis techniques were employed by Advanced Marketing Research to avoid
introducing unnecessary error and bias into the study.
QUOTAS OBSERVED
The gender and age quotas below were targeted in the data collection process.
Males 48% to 52%
Females 48% to 52%
Age 65+ 12% to 20%
For the data tables with the banner containing "gender," "children, .... age," and "zip codes," the
97404 data was weighted to reflect the population of that zip code relative to the other Eugene zip
codes.
Advanced Marketing Research, Inc.
9
RESPONSE RATE
Of the 1,296 qualified respondents reached by telephone, 800 interviews were completed, for a
response rate of 62%. The overall breakdown of numbers dialed is as follows:
Refusals 496
Disconnects 178
Wrong Numbers 4
Language Barrier 3
Spanish Language Barrier 3
Business Numbers 31
Fax 11
No Answer 731
Answering Machine 581
Busy Signal 55
Call Backs 15
No Qualified Respondent 26
Quota Filled 55
Completed Interviews 800
Total Numbers Dialed 2,989
TESTS FOR DIFFERENCES BETWEEN PROPORTIONS
When looking at the data tables, differences between percentage amounts can be misleading, and
statistical tests must be conducted to determine if the differences are statistically significant. The
computer makes these calculations for us, and the results are occasional plus or minus signs at the
bottom of certain cells. These indicate that those answers are more different fi.om everybody
else's answers than could be expected due to chance, given the sample sizes involved. Plus signs
are used if the group picks that answer more often than everyone else; minus signs if it is less than
everyone else. The number of plus or minus signs indicates the level of statistical significance.
One means the 90% level, two the 95% level, and three the 99% level. For example, two plus
signs would mean that you can be 95% sure that the people represented by that group really
would pick that answer more often than the people represented by the rest of the sample. It should
be noted that this test can only be done for banner columns that contain at least 30 people.
Because of this requirement, it is possible that the test will be done for some banner columns on a
table and not for others.
NOTES ON CHI SQUARE
Thc chi square value and its associated probability arc printed beneath thc first column in each
banner heading. Thc probability (p=.xxx) indicates thc probability that the heading and row
variables arc not related is .xxx. For example, a .05 probability of not being related means a 95
percent chance of being related.
Advanced Marketing Research, Inc.
10
BOUND ON ERROR - WEIGHTED DATA, REPRESENTING ALL OF
EUGENE
SAMPLE SIZE Bound on Error at
SEX Frequency Percent 95% Confidence Level
Male 192 48% 6.5%
Female 208 52% 6.2%
AGE
18-24 18 5% --
25-34 53 13% 12.3%
35-44 77 19% 10.2%
45-54 85 21% 9.7%
55-64 81 20% 10.0%
65+ 84 21% 9.8%
CHILDREN?
Yes 135 34% 7.7%
No 264 66% 5.5%
ZIP CODE
97401 85 21% 9.7%
97402 103 26% 8.9%
97403 24 6% --
97404 66 17% 11.1%
97405 100 25% 8.9%
97408 22 5% --
TOTAL 400 100% 4.5%*
* What this means is that we are 95% certain that the mean response of the entire population of
Eugene lies within (plus or minus) 4.5% of the survey response.
Advanced Marketing Research, Inc.
11
BOUND ON ERROR - UNWEIGHTED DATA, REPRESENTING 97404
AND "OTHER" EUGENE
SAMPLE SIZE Bound on Error at
97404 Frequency Percent 95% Confidence Level
City, North of Beltline 143 36% 7.5%
City, South of Beltline 53 13% 12.3%
County, North of Beltline 101 25% 8.9%
County, South of Beltline 103 26% 8.9%
97404
Santa Clara 244 61% 5.8%
River Road 156 39% 7.2%
EUGENE
97404 400 50% 4.5%*
Other Eugene 400 50% 4.5%*
* What this means is that we are 95% certain that the mean response of the entire population of
97404 lies within (plus or minus) 4.5% of the survey response, and we are 95% certain that
the mean response of the entire population of"Other Eugene" lies within (plus or minus)
4.5%.
Advanced Marketing Research, Inc.
12
MINIMUM DIFFERENCE IN PERCENTAGE POINTS REQUIRED FOR
STATISTICAL SIGNIFICANCE IN COMPARISON OF REPORTED
PERCENTAGES FOR SUBGROUPS WITH 95% CONFIDENCE
Subsample 50 100 150 200 250 300 350 400 450 500 600
50 20% 17% 16% 15% 15% 15% 15% 15% 15% 15% 15%
100 14% 13% 12% 12% 11% 11% 11% 11% 11% 11%
150 11% 11% 10% 10% 10% 9% 9% 9% 9%
200 10% 9% 9% 9% 8% 8% 8% 8%
250 9% 8% 8% 8% 8% 8% 7%
300 8% 8% 7% 7% 7% 7%
350 7% 7% 7% 7% 6%
400 7% 7% 7% 6%
450 7% 6% 6%
500 6% 6%
600 6%
Minimums are for reported percentages near 50%. When much smaller or much larger
percentages are reported, a slightly smaller minimum is required.
Advanced Marketing Research, Inc.
ATTACHMENT B
Property Appraisal Information
The attached documents provide summary information of property appraisals relating to the acquisition
of land for a Santa Clara community park, including both the Santa Clara site and the Laurel Hill Valley
properties. This information is provided in response to a request from Council in February of this year.
Santa Clara/lrvington Property
This appraisal was completed by Charles P. Thompson & Associates on April 1, 2005 with a March 24,
2005 date of value. A value of $462,000 was determined for a 77-acre parcel in the northwest corner of
the subject parcel, or that area proposed for parkland within the current concept plan for the 197 acres.
The property was appraised based on the present Exclusive Farm Use (EFU) zoning and the site
remaining outside of the Urban Growth Boundary (UGB).
A value of $280,000 was determined as part of the evaluation of a 40-acre parcel located in the southern
portion of the 197-acre subject property adjacent to Irvington Road. This appraisal was also based on
the present EFU zoning and the site remaining outside of the UGB.
Additional information is attached in the excerpts from the Complete Appraisal Summary Report dated
April 1, 2005, and a letter from Charles P. Thompson & Assoc., Inc. dated April 12, 2005.
Laurel Hill Property
Appraisals had been conducted on this site previous to the recent Council request. One was done
through a request of the City as part of preliminary-property negotiations. The appraisal, also conducted
by Charles P. Thompson & Associates, determined a value of $950,000 for the approximately 100 acres
to be sold in fee title to the City. In addition the appraiser was asked to provide an estimate for the value
of the approximately 30 acre exclusive use trail and open space easement that was proposed to be
donated to the City. The appraised value of the 30 acre easement was concluded to be $1,667 per acre or
$50,000 for the total easement area. These values are based on the UGB boundary exchange scenario
and the site being located outside of the urban growth boundary. Additional information is attached in a
letter from Charles P. Thompson & Assoc., Inc., dated April 15, 2004 and the Complete Appraisal
Summary Report excerpts dated April 6, 2004.
For comparison purposes an appraisal of this site based on its value inside of the UGB is also
referenced. This appraisal was previously completed for the McDougals in March of 2000 by Charles
Thompson. The value derived based on that condition was $2,150,000. Additional information is
attached in the Charles P. Thompson & Assoc., Inc., letter of March 22, 2000.
L:\CMO\2005 Council Agendas\M050518\S050518B.doc
Charles E Thompson & Assoc., Inc.
Real Estate Appraisers & Counselors
April 12, 2005
Mr. Russ Royer
Senior Real Property Officer
City of Eugene Public Works
Engineering Division
858 Pearl Street
Eugene, OR 97401
RE: Complete Appraisal - Summary Report of two undeveloped land parcels located north
oflrvington Road, south of Beacon Drive, east of Prairie Road, and west of River Road,
Lane County, Oregon (Property owned by LeeLynn, Inc., and Wiley Mtn., Inc.)
Dear Mr. Royer:
During our telephone conversation on Friday, April 8, 2005, you indicated a concern involving the
analysis of Sale Nos. 2 and 4. Your opinion was that these two sales seemed to support a higher
value for the subject then the values reported of $6,000 per acre for Subject Parcel 2, and $7,000 per
acre for Subject Parcel 1.
Sale No. 2, after subtracting $50,000 for the improvements, reflected a per acre value of$5.195 per
acre. My analysis was that this sale indicated a value for the two subject properties of well above
this figure, i submit that $6,000 and $7,000 per acre are well above this figure.
Likewise, Sale No. 4 reflected a per acre price of $5,633 per acre. Again, my values of $6,000 and
$7,000 per acre are above this figure.
Perhaps, based solely on these two sales, I could have gone somewhat higher, perhaps $7,000 and
$8,000 per acre; however, I based the value conclusions on all of the sales, rather thanjust those two.
Our discussion regarding the lack of sales of properties adjacent to the Urban Growth Boundary,
prompted me to search back in time to find a 2000 sale, which involved a 77.03 acre (useable) land
parcel located on the west side of Greenhill Road, adjacent to Barger Drive, and approximately 1,326
feet south of its intersection with Bodenhamer Road in Lane County, Oregon. This property sold
in February of 2000 for a price $250,000, or $3,245 (useable) per acre. Adjusting this for time at 4%
per annum, results in a time adjusted price per acre of $3,948 per acre.
While this property is similar to the subject in that it is zoned Exclusive Farm Use and involves
several drainage-ways, it is considered inferior in that it is also bisected in a diagonal fashion with
a BPA power line near the eastern one-third of the property. Moreover, the soils are inferior to those
1~0. BOX 10233 · EUGENE, OREGON · 97't40-2233 · TELEPftONE (54l) 343-8895 · E4X (.541) 343-5190
Russ Royer
April 12, 2005
Page 2
of the subject. However, this is a two-edged sword. This property because of its less than ideal
soils, might be chosen to go inside the Urban Growth Boundary before the subject, which involves
Class I and II soils.
If you judge the subject to be 30% superior to this sale property, which is a stretch, it would only
indicate a value for the subject of $5,132 per acre.
This sale property was purchased based on speculation that it might be brought into the Urban
Growth Boundary in the future. As such, the purchase price was significantly higher than the typical
farm property transaction.
We appraised the sale property in late-1999 welt below $3,245 per acre. And then in 2000, we
revised the appraisal upward to $254,000 or $3,297 per acre overall, based on the useable acres of
77.03. The sale then closed at $250,000 or $3,245 per useable acre.
Based on the foregoing, ! believe that my value estimates are accurate and supportable. However.
in a courtroom situation, a jury might well come in at a much higher figure.
As we discussed, the solution might be to value the subject property based on an "extraordinary
assumption" regarding annexation. _
If you have further questions, please feel free to call at your convenience.
Very truly yours,
CHARLES P. THOMPSON &~ A,~C., INC.
COMPLETE APPRAISAL-
SUMMARY REPORT
of
TWO UNDEVELOPED LAND PARCELS
located
North of Irvington Road, South of Beacon Drive,
Il East of Prairie Road, and West of River Road
Eugene, Oregon
Date of Report: April 1, 2005 Submitted to: Russ Royer
Senior Real Property Officer
City.of Eugene Public Works
Engineering Division
858 Pearl Street
Eugene, OR 97401
Date of Value: March 24, 2005 Submitted by: Charles P. Thompson, MAI, SRA
Charles P. Thompson & Assoc., I~.
1234 High Street, Suite A
Eugene, OR 97401
~-' Real Estate Valuations Northwest
Charles P. Thompson & Assoc., Inc.
Real Estate Appraisers & Counselo~-s
Commercial Division
Charles E Thompson & Assoc., Inc.
Real Estate Appraisers & Counselors
I April 1, 2005
I Mr. Russ Royer
City of Eugene Public Works
Engineering Division
I 858 Pearl St.
Eugene, OR 97401
I RE: Complete Appraisal- Summary Report of two undeveloped land parcels, located
north of Irvington Road, South of Beacon Drive, East of Prairie Road, and West
of River Road, Lane County, Oregon. The two land parcels, one containing
I approximately 40 and the other parcel containing approximately 77
acres,
acres,
are part of Tax Lot 200, on Lane County Assessor's Map 17-04-03.
I Dear Mr. Royer:
Pursuant to your request, I have personally inspected the above referenced properties for the
I purpose of estimating the market values thereof effective March 24, 2005.
The subject properties were appraised subject to the assumptions and limiting conditions
I outlined in this report. The market values of the fee simple interests in the subject properties,
effective March 24, 2005, were concluded to be as follows:
i Parcel I (40-acre parcel) $280,000 ($7,000 per acre)
I Parcel II (77-acre parcel) $462,000 ($6,000 per acre)
The two subject land parcels are part of a larger parcel, Tax Lot 200 on Lane County
I Assessor's Map 17-04-03, which contains a total of approximately 197.16 acres, adjacent to
the Urban Growth Boundary. The current zoning is Exclusive Farm Use with a 30-acre
minimum division size.
I
This appraisal was completed in conformity with the Code of Ethics and Standards of
Professional Practice of the Appraisal Institute. Also, the appraisal was done in accordance
I with the 2005 edition of the Uniform Standards of Professional Appraisal Practice (USPAP),
adopted by the Appraisal Foundation.
I
I P.O. BOX 10233 · EUGENE, OREGON · 97440-2233 · TELEPHONE (541) 343-8895 · FAX (541) 343-5190
This summary appraisal report is respectfully submitted and your attention drawn to the
"Assumptions and Limiting Conditions" as set forth'beginning on page 24. If I can be of
further assistance, please call at your convenience.
Very truly yours,
CHARLES P. THOMPSON & ASSOC., INC.
CharleYs .
State Certified General App~mi~r #C000007
PLAT MAP
FOR ASSESSMENT s~o.
ANDONLyTAXATION ~ L~E,.,.~o.COUNTY ~ ~ IN'EX
~9-29
SEE ~P
,~.m ~.* 004-87
? ~OT ~.14 004-17
~ ~ ~~ 052-29
~ [ I Parcel II
Parcel I
I
M~ ~2-17 ~-~
3 ~ 1704~34
I
] ~ ~o ~ k ~ _
I Charles P. Thompson & Assoc., Inc. 1 ]
C-CityEugeneSantaClara.305
Charles P. Thompson & Assoc., Inc.
Real Estate Appraisers & Counselors
April 15, 2004
Russ Royer VIA FACSIMILE: 682-503'2,
Senior Real Property Officer
City of Eugene - Public Works
Engineering Division
858 Pearl St.
Eugene, OR 97401
RE: Appraisal of the McDougal Foundation properW containing approximately 98.68 acres,
located on the north side of 30th Avenue, near its intersection with Spring Boulevard,
Eugene, Oregon.
Assessor's Map & Tax Lot No.: 18-03-10, TL 701
Dated: April 6, 2004
Dear Mr. Royer:
Pursuant to your request, I have reviewed my file on the above captioned appraisal for the purpose
of rendering opinions regarding the value of the land under the BPA Easement. I have included
values for that portion inside this Urban Growth Boundary (Tax Lot 701) and that portion outside
the Urban Growth Boundary, which was not included in the appraisal (Tax Lot 702). Tax Lot 701.
the subject of the appraisal, contained approximately 98.68 acres, while Tax Lot 702 contains
approximately 137.77 acres.
The property which is the subject of the appraisal, Tax Lot 701 was valued in the appraisal at
$950,000 or $9,627 per acre. The portion of that property under the Powerline Easement is believed
to suffer a reduction in value of about two-thirds, which results in the value tbr the encumbered
portion of $3,209 per acre. This portion of the subject property cannot be built-on, but has some
value in that it can be used for density calculations.
Tax Lot 702, the 137.77 acre parcel outside the UGB, is valued based on Sale 2 which involved a
property that was divided into two 50+ acre parcels which sold in 1998 and 1999 at between $3,868
and $4,062 per acre. Using a figure of $4,000 per acre updated for time at 3% per annum, results
in a time adjusted price of $5,000 per acre. This figure is utilized for the land parcel outside the
Urban Growth Boundary. Reducing the $5,000 per acre by two-thirds results in a per acre value for
this parcel of $1,667.
P.O. BOX10233 · EUGENE, OREGON · 97+¢0-2233 · TELEPHONE (5Ztl) 343-,0,895 · [AX (541)343-5190
In imposing a second easement on both parcels, which will be utilized as a hiking trail, will not in
my opinion reduce the fee value further.
If you have any questions regarding this matter, please contact me at your convenience.
Very truly yours,
CHARLES P. THOMPSON &.ASSOC.
Charles P. Thompson, MAI,:SR/A
COMPLETE APPRAISAL-
SUMMARY REPORT
of
PROPERTY OWNED BY THE
MCDOUGAL FOUNDATION
located on
THE NORTH SIDE' OF 30TIt AVENUE NEAR ITS
INTERSECTION WITH SPRING BOULEVARD IN
EUGENE, OREGON
Date of Report: April 6, 2004 Submitted to: Russ Royer
Senior Real Property officer
City of Eugene Public Works
Engineering Division
858 Pearl Street
Eugene, OR 97401
Date of Value: March 17, 2004 Submitted by: Charles P. Thompson, MAI, SRA
Charles P. Thompson & Assoc., Inc.
1234 High Street, Suite A
Eugene, OR 97401
Real Estate Valuations Northwest
CMrles P. Thompson & Assoc., Inc.
Real Estate,Appraisers & Counselors
Commercial Division
Charles P. Thompson & Assoc., Inc.
Real Estate Appraisers & Counselors
April 6, 2004
Russ Royer
City of Eugene Public Works
Engineering Division
City of Eugene
858 Pearl St.
Eugene, OR 97401
RE: Complete Appraisal- Summary Report of a 98.68 acre land parcel, located on the
north side of 30th Avenue near its intersection with Spring Boulevard, Eugene,
Oregon.
Dear Mr. Royer:
Pursuant to your request, I have personally inspected the above referenced property for the
purpose of estimating the market value thereof effective March 17, 2004.
The subject property was appraised subject to the assumptions and limiting conditions
outlined in this report. The market value of the fee simple interest in the subject property,
effective March 17, 2004, was concluded to be $950,000, based on the hypothetical condition
that the property is going to be outside the Urban Growth Boundary within a one year period.
The subject property is currently inside the Urban Growth Boundary of the City of Eugene.
However, the City plans to move the property outside the UGB after acquiring ownership.
Because the subject property is currently inside the UGB, the current owners could most
likely develop the property into five 20-acre homesites without annexation and the extension
of utilities. Assuming this was done, and then the City acquired the property, even though
it was zoned F-2, the City would have to acquire the property with the potential for five, 20-
acre homesites.
In order to value the subject property on an equitable basis, recognizing the now existing
development potential, the subject property is appraised based on the assumption that such
a division is possible, which based on information from the Lane County Planning
Commission, is a reasonable assumption.
P.O. BOX 10233 · EUGENE, OREGON · 97440-2233 · TELEPHONE (541)343-8895 · FAX (541)343-5190
This appraisal was completed in conformity with the Code of Ethics and Standards of
Professional Practice of the Appraisal Institute. Also, the appraisal was done in accordance
with the 2004 edition of the Uniform Standards of Professional Appraisal Practice (USPAP),
adopted by the Appraisal Foundation.
This summary appraisal report is respectfully submitted and your attention drawn to the
"Assumptions and Limiting Conditions" as set forth beginning on page 30. If I can be of
further assistance, please call at your convenience.
Very truly yours,
CHARLES P. THOMPSON & ASSOC., INC.
State Certified GePi~l~;raise~0007/~/
PLAT MAP
Charles P. Thompson & Assoc., Inc.
C-CityEugMcDougal.404 i ]
CORRELATION AND FINAL VALUE CONCLUSION:
The Direct Sales Comparison Approach resulted in a value range for the subject property on
an "as is" basis effective March 17, 2004, of $6,730 to $9,307 per acre. The value was
judged to be near the high end of the r.ange, and was concluded to be $9,000 per acre times
98.68 acres or $888,000, rounded.
The anticipated use or development procedure is considered to be the most valid in this case,
even though many of the calculations are quite subjective. This is because developer's think
along these lines, rather than along the lines of the Direct Sales Comparison Approach even
when good data is available, which in this case good data was not available.
In conclusion, the "as is" value of the subject property, in fee simple time, effective March
17, 2004, is concluded to be $950,000.
Charles P. Thompson & Assoc., Inc.
C-CityEugMcDougal.404 2 9
,Real, Estate Valuations Northwest
Charles P. Thompson & Assoc., Inc.
Real Estate Appraisers & Counselors
March 22, 2000
McDougal Foundation Inc.
c/o Mr. James A. Youel, CPA
925 Country Club Road
Eugene, OR 97401
Dear Mr. Youel:
Pursuant to your request, I have personally inspected the following described property for the
purpose of estimating the market value thereof effective March 15, 2000.
Re: A 100 acre undeveloped land parcel on the northerly side of 30th Avenue ,~d at the
southerly terminus of Riverview Street. Lane County Assessor's Map #18-03-10 part
of Tax Lot 700 (that portion inside the Urban Growth Boundary of the City of
Eug'~ne).
This is a Summary Appraisal Report ~vhich is intended to comply with the reporting
requirements set forth under Standards Rule 2-2(b) of the Uniform Standards of
Professional Appraisal Practice for a Summary Appraisal Report. As such, it presents
only summary discussions of the data, reasoning, and analyses that were used in the
appraisal process to develop the appraiser's opinion of value. Supporting
documentation concerning the data, reasoning, and analyses is retained in the
appraiser's file. The depth of discussion contained in this report is specific to the needs
of the client.
The subject property was appraised subject to the Assumptions and Limiting Conditions
outlined in this report. The market value of the fee simple interest in the subject property
effective March 20, 2000 was concluded to be $2,150,000.
This appraisal was completed in conformity with the Code of Ethics and Standards of
Professional Practice of the Appraisal Institute. Also, the appraisal was done in accordance
with the 1999, edition of the Uniform Standards of Professional Appraisal Practice (USPAP),
adopted by the Appraisal Foundation.
P.O. BOX 10233 · EUGENE, OREGON · 97440-2233 . TELEPttONE (54 I) 343-8895 · FAX (541) 343-5190
This summary appraisal report is respectfully submitted and your attention drawn to the
"Assumptions and Limiting Conditions" as set forth beginning on page 22. If I can be of
further assistance, please call at your convenience.
Very truly yours,
CHARLES P. THOMPSON & ASSOC., INC.
sCt~a~;lecSeP.rt.i~eh~ePSn~rn~,~000007
Location
1 11/93 RA-PD 90 $11,722.7 18-04-03, TL 8400 SW Hills between
Warren St. & Bailey Hill
Road
2 ': 3/93 is? 1°o Easts deB .tonRoad
west of Sundial
3 2/97 ~-PD 91.71 $22,300 18-04-11, TL 302 ~W Hills- Timberline &
Wa~en
4 7/97 ~;;:;~ ~ ~ $~;3~8 ::: ~8~03}16~30~ SEHilh. Di0ardRoad
5 11/95 RA-PD 65.31 $19,905 18-03-03, TL 106 SE Hills - S. terminus of
Henderson Avenue
6 : 5/98 : $18,571'! :18~03¢03 *L 106 SE Hills- S: te~inus of
~ :::: :' Henderson Avenue
7 6/97 ~-PD 43 $17,857 18-03-20-2 I, Extends southerly ~om
TL 101 Matin Street
Subj: 3/00 AGT 100 : 2: 18-03~10, TL 700 Northerly side of3ffh
:: .: : : .(Pad) Ave., eastofSpring Blvd.
* 1 The price per acre orS11,722 was for the land inside the ciW limits.
'2 The price per acre included 12.30 acres ouBide the UGB. The price per acre for the 22.70 acres inside the
UGB was $25,925.
General Discussion of Comparables '
Sales 1 t~ough 7 involve a wide range of sizes and unit prices, which is Wpical for south
hills subdivision land. There have been relatively few recent sales of large, residentially
zoned l~d parcels in the south hills, particularly in the southeast hills, that offer reasonable
comparability to the subject. The above sales r~ge in size from 19.69 acres to 91.71 acres.
By comparison, the subject land parcel contains approximately I00 acres. The time frame
of the sales is 3/93 to 5/98. Two of the sales took place in 1993, one in 1995, t~ee in 1997,
and one in 1998. The per acre price range for the sales is from $11,722 to $25,925.
Analysis of Sales -
Sale 1 involved 90 acres inside the City of Eugene and 122 acres outside the city and outside
the UGB. It is similar to the subject with regard to topography and access. The major
differences between this sale and the subject are size and the time factor. With regard to size,
a comparison of Sales 1 and 2 indicates a 56% difference in price per acre between Sale 1,
a 90 acre land parcel and Sale 2 a 27.44 acre lm~d parcel. Other factors likely entered into
the unit price difference, however, most of the difference is believed attributable to the size
difference. With regard to the factor of time, Sales 1 and 3 are nearly the same size. Sale
1 took place in late 1993 and Sale 3 took place in early 1997, a time difference of
approximately 3.25 years. The two sale properties are quite similar, therefore, most of the
Chades P. Thompson & Assoc., Inc.
C-McDougalLand 300 19
price differential is due to the difference in time. Sale 1 sold for $11,722 per acre in 11/93
and Sale 3 sold in 2/97 for $22,300 per acre, a compound rate of increase of almost 22% per
annum. However, while this rate of increase may be applicable between late 1993 and early
1997, it is not considered applicable between 1993 and 2000. The rate of increase over this
longer period is significantly smaller. Even so, it is apparent from these two sales and other
data that land values in the south hills have increased significantly between late 1993 and
early 1997. Based on this reasoning, Sale 1 suggests a value for the subject land parcel of
more than $20,000 per acre.
Sale 2 is similar to the subject with regard to size and general location, but it has better
access. However, the sale took place in early 1993 and values have increased significantly
since that time. Based on the reasoning recited above, Sale 2 suggests a value for the subject
of significantly more than $18,244 per acre.
Sale 3 involved a 91.71 acre land parcel which sold in early 1997 on the basis of $22,300 per
acre. This sale is similar in size to the subject, but is better located and has better access.
Overall, taking into consideration the time factor, this sale suggests a value for the subject
of less than $22,300 per acre.
Sale 4 took place in mid-1997 and involved a 19.69 acre parcel of land in the south hills,
which sold for $24,378 per acre. It is significantly smaller than the subject, but otherwise
similar. However, it is considered superior with regard to access (long frontage on Dillard
Road). On balance with time, this sale suggests a value for the subject of less than $24,378
per acre~
Sale 5 involved a failed sale of a land parcel near the subject, which sold in late 1995 for
$19,905 per acre. This property contained approximately 65.31 acres. The price and terms
had been agreed to, however reportedly, the purchasers did not follow through and the sale
did not close. This transaction indicates a value for the subject of mot than $19,905 per acre.
Sale 6 - In mid-1998, the City of Eugene purchased 35 acres of the 65.31 acres for a park.
The price was equivalent to $18,571 per acre overall. However, 12.30 acres were outside the
UGB. The price per acre for the 22.70 acres inside the UGB was $25,925 per acre. This sale
suggests a value for the subject of more than $18,571 per acre and less than $25,925 per acre.
Sale 7 involved a 43 acre land parcel which was assembled in two parts in mid- 1997. The
total purchase price for both parcels was $430,000 or $10,000 per acre. The parcel had steep
portions, significant wetlands, and relatively poor access. A plat was submitted and denied
by the City. Then, in 1999 the City purchased 16 acres of the steep portion for a price of
$180,000 or $11,250 per acre. The remaining 27 acres was subdivided into 59 lots, which
is only 2.19 lots per acre. The lots were situated on a 14 acre portion and a 13 acre portion
was left as open space to accommodate the wetlands. A simplified analysis of the seller's
effective price per acre is as follows:
Charles P. Thompson & Assoc., Inc.
C-McDougalLand.300 20
-Mid-1997 purchase price for 43 acres $430,000
Less price received from City for 16 acres $180,000
Balance of $250,000 for 14 acres of useable land is equivalent to $17, 857 per acre
effectively.
This sale is considered inferior to the subject on an overall basis, although significantly
smaller. On balance with size and time, this sale indicates a value foi the subject of'
significantly more than $17,857 per acre.
Based on the foregoing sales, the value of the subject land parcel is reasonably concluded to
be $21,500 per acre or $2,150,000.
Special Note: When a land parcel such as the subject has gone through various stages of
approval and has reached the status of a master plan approval, the value increases
significantly. However, such approval would likely take several years and large outlays of
money for professionals. Moreover, there are many risks along the way.
Charles P. Thompson & Assoc., Inc.
C-McDougalLand.300 2 1
ATTACHMENT C
LAND PLANNING CONSULTANTS
1071 HARLOW ROAD
SPRINGFIELD OR 97477
Phone 541-726-8523
April 19, 2005
Russ Royer
Eugene Public Works Department
858 Pearl Street
Eugene, OR 97401
Dear Russ,
This letter responds to your inquiry concerning the McDougals possible interest in selling a
portion of their Irvington Road property to the City. The McDougals are not and never have been
interested in selling any portion of the property. Neither are they interested in selling their Laurel
Hill property except under the current agreement involving a "swap" of lands within the UGB.
The McDougals agreed to donate land to the parks department that was in excess of the 120 acres
involved in relocating land within the Urban Growth Boundary from South Eugene (the Laurel
Hill site) to the Irvington site. This proposal was believed to be mutually beneficial because the
City would receive land at no cost for a regional park at Irvington and land at a rural value cost
for the ridgeline park area in South Eugene. In return the McDougal's would be able to develop
their more site-ready Irvington property with a design integrated with a park. In additional to an
area for active use, natural areas would weave through the residential development.
The Irvington property is not typical rural land but is what is considered as "opportunity"
property. All public facilities necessary to support urban development either abut or exist on the
site; the property is located within the urban reserve; and, it is projected for urban development in
2 of 3 scenarios within the 50750 Plan. It is well understood in the development community that
there is a short supply of developable land within the Eugene Urban Growth Boundary. It is only
a question of when the Irvington site will be included into the UGB. In addition, the sale of a
portion of the site would obstruct its future logical and efficient development, especially if the
propea-t3,~s street frontage is impacted.
The proposal under agreement between the McDougals and the parks department terminates July
1, 2005. The McDougals do not intend to extend the agreement and will retain ownership of bo~h
of the properties involved.
Hopefully this letter responds adequately to your inquiry.
Sincerely,
Mike Evans