I. RIVER ROAD SEWER PROJECT
e
Terry Smith, Public Works Department, provided the council with an update on
the status of the River Road sewer project. Because this is expected to be a
highly controversial issue, staff recommends that the Hearings Official
process be skipped and that the contract come directly before the council at
a May 29 public hearing. Contract bids are expected to be opened the first
of May and following this process would allow contractors an additional 7-10
days to prepare bids which would likely be reflected in bid estimates. The
contract should be signed by the City Manager by June 15; construction should
begin in late June.
Mr. Smith advised the council that staff is aware of some actions within the
community to stop this project. It is possible for citizens to submit a
Remonstrance Petition to the council at its public hearing stating that 50
percent of the property owners in this area object to this project. This
petition could be overridden by a two-thirds vote of the council. Another
legal challenge which is being investigated involves concerns of
constitutional equal protection.
Mr. Smith reviewed the method being used by the City to assess sewer costs in
this area. The City plans to assess sewer costs proportional to the area of
the lot. This calculation method is used most commonly for sewer assessment
in Oregon and is the best reflection of the benefit provided to a property by
a sewer improvement.
e
Mr. Smith indicated that concerns surrounding the groundwater problem in
River Road has been a source of tension within our community. Since 1971,
numerous tests of groundwater conditions have been conducted and have proven
conclusively that River Road septic tanks have contributed to a significant
bacterial contamination problem.
Mr. Smith said that sewer affordability has been one heavily debated issue
against this project; the City has conducted an affordability analysis of
MINUTES--Eugene City Council
Dinner/Work Session
April 9, 1990
Page 1
-
e
e
sewer provlslon in that area. A project should be considered too expensive
if sewer costs exceed 3 percent of the median annual family income. Using
this criterion, staff has determined that at a 3-percent rate, homeowners
would be able to meet their financial obligations with either a 10- or
IS-year financing program. The River Road Citizens Advisory team (CAT)
recommended against 20-year financing because it encourages property owners
to enter into long-term debt without substantially impacting monthly sewer
costs; CAT did not consider IS-year financing. Mr. Smith said that interest
costs increase with IS-year financing, and there is a possible negative
impact on the City's bond rating. The choice between 10 and 15 years is up
to the council.
Mr. Smith noted that four low-income deferral programs are available to
assist residents with sewer costs in the River Road area. In addition, it
might be possible for Eugene to receive several million dollars at a
3-percent interest rate from the Oregon State Revolving Loan Fund to aid in
long-term financing. It might also be possible to seek County assistance by
means of the County Road Fund. The road fund could help reduce the average
homeowner's cost by approximately 20 percent.
Mr. Smith said that staff is particularly concerned with those
moderate-income property owners who do not qualify for low-income deferral
programs, but who have large sewer assessment costs. In order to address
this concern, staff is considering a delayed-assessment mechanism in which
the City would assess only a portion of the area of this lot. The remaining
assessment cost would be carried by the City. Mr. Smith noted that the City
may not assess vacant properties until they are annexed to the City and can
be developed. This carrying cost, to the Sewer Utility Fund, is
approximately $1.5 million. The City already has $4 million invested in
interceptor sewers which will gradually be recovered as sewer bills are paid.
Responding to a question from Mr. Boles, Mr. Smith clarified that in the case
of delayed sewer assessment, the property owner would be required to pay the
entire assessment cost at the end of the specified time period. This would
allow property owners to decide when to sell and subdivide their property
within the assessment period. If a property owner chooses to annex,
subdivide the property, and develop, he or she would pay the assessment at
that time.
Responding to a question from Mr. Boles, Mr. Smith said that there is no data
on the average income of those individuals who own large property lots.
Mr. Miller inquired about the possibility of dividing assessed sewer costs
equally among landowners regardless of calculated property area. Mr. Smith
responded that this type of common assessment is less equitable than the
proposed assessment method; large property owners would receive a
substantially greater benefit.
Mr. Boles asked about the equity of proposed cost-cutting programs to those
River Road residents who might not want to subdivide their property; i.e.,
those landowners who desire to maintain the rural character of their land.
For these people, the opportunity to develop is not a benefit. He suggested
the possibility of establishing a contractual agreement with these owners in
which they would demonstrate their intention not to subdivide their property
MINUTES--Eugene City Council
Dinner/Work Session
April 9, 1990
Page 2
-
e
e
and would be penalized if the covenant is violated. Mr. Smith said that this
type of agreement has not been considered. Mr. Holmer added that in the
interest of compact urban growth, the City would not want to encourage this.
Mr. Rutan commended City staff for its excellent work on this project.
Pat Decker, Planning and Development Department, summarized information
regarding the joint hearing between the Lane County Commissioners, the
Springfield City Council, and the Eugene City Council on the Metro Plan
amendment. This hearing will provide the council with an opportunity to hear
from River Road property owners on separating the issues of annexation and
property development. Ms. Decker said that staff is uncertain about what
type of testimony to expect.
Mr. Boles emphasized the importance in the community of hearing the County
present testimony in favor of this project. Mr. Gleason indicated that the
County is currently divided on this issue and, thus, would be difficult for
the County to present a single, unified position.
The meeting adjourned at 6:35 p.m.