I. WORK SESSION: CAMPGROUND PROPOSAL
City Manager Mike Gleason provided a brief staff report. On August 8, 1990,
the City Council heard a request to establish a campground to serve the
homeless. The request was developed following the protests which took place
when the Opportunity Shelter closed. The Social Goals Committee reviewed the
campground proposal and is providing a progress report to the full council.
e Mr. Gleason pointed out the enormous amount of staff work that has gone into
this campground proposal, which is an indication of the City's interest and
dedication to finding a solution to the homeless problem. He noted, however,
that the proposal has many unresolved problems, particularly regarding the
City's ability to manage a campground effectively. Because of these prob-
lems, Mr. Gleason advised the City Council not to institute this proposal.
Jan Childs, Planning and Development Department, reported on behalf of the
Social Goals Committee. She noted that the Social Goals Committee has had an
opportunity to review the campground proposal and has identified a variety of
concerns and issues. She summarized that the Social Goals Committee believes
that a campground should be a last-resort solution to homelessness in the
community and finds the "night shelter" proposal a preferable alternative.
Further, the committee agreed that City efforts should be concentrated on
providing permanent, affordable housing within the community.
Ms. Childs stated that the Westside Neighborhood Quality Project considered
this proposal last night and voted 25:13 in favor of the proposal. In addi-
tion, a separate vote of the Jefferson Area Neighbors was 13:12 in favor of
the proposal.
Mr. Boles remarked that the Social Goals Committee received minimal community
response to requests for assistance with the proposed "night shelter" pro-
gram. He voiced his support of the Westside Neighborhood Quality Project's
e MINUTES--Eugene City Council September 12, 1990 Page 1
e vote on this issue, but noted that there appears to be a lack of support on
the council for the campground proposal. He suggested that the council
immediately begin discussing the "night shelter" proposal so that it would be
available to serve homeless families this fall.
Mr. Bennett said that the Social Goals Committee recognizes the extreme
seriousness of the homelessness problem in our community. He spoke about the
conflict which exists in housing provision between the needs for emergency
shelter versus permanent housing. Because of the City's costs and liabili-
ties associated with a campground, Mr. Bennett said that he could not support
the campground as a solution to the problem.
Ms. Schue concurred with Mr. Bennett on the seriousness of the housing prob-
lem and agreed that a temporary campground is not the best solution. She
offered her support for the "night shelter" program, recognizing that it,
too, has problems. She noted that several churches have volunteered their
parishes for night shelter and pointed out that homeless families will also
need a minimum level of services during the day.
Speaking as the council's representative on the Housing Policy Board, Ms.
Bascom said that the City has a number of housing projects for low-income
families which are nearing completion, evidence that the City is making some
headway toward long-term housing solutions. She agreed with Mr. Bennett that
funding for emergency housing should not be taken from the City's financial
resources for providing permanent housing.
e Mayor Miller pointed out that the campground proposal has sparked a great
deal of interest and education in the housing problem in the community. He
emphasized the importance of finding a solution to this problem quickly and
asked about the City's ability to find temporary shelter for homeless fami-
lies this winter at a level higher in quality than a campground. In re-
sponse, Mr. Gleason said that the City hopes to have the "night shelter"
available by Thanksgiving.
Mr. Holmer stated that the homelessness issue is an immediate problem that
needs an immediate solution. He advised the council that the issues of day-
and night-time shelter should be addressed concurrently.
Mayor Miller summarized the council's position on this issue. The council
directed that the City Manager report back to the council in mid-October on
the progress being made to address this problem, with the possibility of a
shelter opening in late November. Mr. Miller asked that the proposed solu-
tion meet the housing goals identified by the homeless mothers in their
report at a higher level of quality than the campground proposal.
Mr Gleason indicated that intergovernmental work on this issue has already
begun.
Mr. Boles moved, seconded by Ms. Schue, to instruct the City
Manager to work with the Homeless Mothers Task Force and
other interested parties in the community to generate a
e MINUTES--Eugene City Council September 12, 1990 Page 2
e proposal for temporary shelter in the community. The con-
tents of this proposal, which shall be brought back to the
council by Mid-October, shall include a detailed list of both
day- and night-time services, an analysis of the potential
facility costs, and recommendations on how the City might pay
these costs. The motion carried unanimously, 8:0.
II. ITEMS FROM THE CITY COUNCIL, MAYOR, AND CITY MANAGER
A. Workshop on Drug and Alcohol Abuse
Mr. Green announced that the State of Oregon, in conjunction with the Commu-
nity Substance Abuse Consortium (COSAC), is planning to sponsor a day- long
workshop on drug and alcohol abuse on September 13, from 9 a.m. to 5 p.m.
B. Concentration of Social Services
Mr. Boles noted that a perception exists within the community that social
service responsibilities are over-concentrated in west Eugene. He asked
staff to provide the council with a map detailing where social services are
located in the community.
C. League of Oregon Cities
Ms. Schue announced that she recently spoke before the Domestic Policy Coun-
e cil Task Force on Wetlands at the League of Oregon Cities conference in
Olympia, Washington. She attempted to educate the committee about the re-
gional impact of wetland legislation.
D. Chambers Communications Land Use
Mr. Bennett reminded the council that several weeks ago it instructed staff
to create a plan to deal with the Chambers Communications land-use problem.
He noted that staff is looking at new approaches to finding a solution and
will be reporting to the council soon.
E. Change-of-Date Request for the Goal-Setting Session
Mr. Rutan indicated that his schedule conflicts with the council's Goal-Set-
ting Session previously scheduled for October 26-27 and asked the council if
it would be willing to reschedule. The council directed staff to consider
other possible meeting dates and agreed that if a suitable alternate could
not be found, the meeting date would remained as scheduled.
F. Change in Services to Community Service Organizations
Mr. Rutan applauded the University of Oregon on its decision to turn its
delivery of services at home football games to community service organiza-
tions. He pointed out the tremendous financial benefits that this decision
provides to nonprofit organizations in the community and asked the Mayor to
e MINUTES--Eugene City Council September 12, 1990 Page 3
e write a letter on behalf of the council commending the University on its
decision. The Mayor agreed to draft the letter.
G. Flag Prohibition
Mr. Holmer spoke about the recently adopted Sign Code provision which prohib-
its flag-flying within the city. He noted that the City recently issued a
temporary flag-flying permit to the University of Oregon to allow flag-flying
at the home football games but suggested that the council consider a more
permanent solution. He asked the council to consider an amendment to the
Sign Code which would be crafted narrowly enough to address the University
only.
Mayor Miller voiced concern that such an action might be seen as unfair
within the community and might create the perception that local government is
not operating consistently.
H. Ballot Measure 4
Mr. Holmer said that in order to protect the State's energy supply for the
future, the City should urge citizens to vote no on Ballot Measure Four,
regarding the continued operation of the Trojan Nuclear Plant. He urged that
the Intergovernmental Relations Committee discuss this issue in the near
future.
Mr. Boles also suggested that the Council Committee on Infrastructure discuss
e this issue.
I. Literacy Coalition's Request For Funding
Ms. Ehrman moved, seconded by Ms. Bascom, to direct the City
Manager to proceed with the Literacy Coalition's request for
funding.
Mr. Holmer noted that the council received little information on the budget
of the Literacy Coalition. He requested that more effort be made in the
future to provide the council with all information necessary for decision-
making.
The motion carried unanimously, 8:0.
III. LIBRARY CONCEPTUAL DESIGN
City Manager Mike Gleason introduced the topic. He noted that on June 27,
1990, the council voted to prepare a site/financing/design proposal for a new
Eugene Public Library to be located on the site of the former Sears Building
at Charnel ton Street and lOth Avenue. The council also adopted a project
time line which called for presenting a conceptual design to the community
during September and October. The purpose of this meeting is to provide the
council with information and proposed design variations for the library.
e MINUTES--Eugene City Council September 12, 1990 Page 4
e Mr. Gleason introduced the members of the Library Board and project archi-
tects: Robertson/Sherwood, SERA Architects, and Brockmeyer and McDonald.
Jim Robertson, representing Robertson/Sherwood, presented the council with
two versions of the library conceptual design. He summarized that the prima-
ry goals behind the library expansion project were threefold: generate
awareness within the community of the need for a larger library, present the
library as a key community asset for education and recreation, and provide
information and gather community input regarding possible Sears expansion.
Mr. Robertson reminded the council that it had been determined previously
that to meet current library needs, the newly expanded library would require
a minimum of 100,000 square feet additional working space.
Mr. Robertson emphasized the importance the council placed on public involve-
ment and input into the library expansion project. He noted that the inter-
active design process which has been followed encourages a great deal of
outside input. Although little input has been received thus far, it is the
hope of City staff that the public information sessions will address this.
Mr. Robertson presented the two designs and explained that they vary primari-
ly in their use of space and layout. He emphasized that the library designs
being presented are concepts of what a library on this site could be--not
necessarily what it will be. As further input is received, the design will
change.
e Mr. Robertson said that Concept A anticipates a three-story building with
reinforced ceilings and a two-story, 37,000 square-foot addition to the east
adjoining a 10th Avenue public plaza. Some unused space would exist in the
lower level of this building, which would create the possibility of some
limited expansion in the future.
Mr. Robertson commented that because public functions are planned for all
three levels of the building, an additional service desk would be required
which increases the overhead and maintenance costs of this design.
Mr. Robertson said that the total cost of Concept A would be $14,230,000.
This figure includes $250,000 in land-acquisition costs and $80,000 in moving
costs.
Mr. Robertson said that Concept B is similar to Concept A in many respects,
but utilizes a three-story addition to the east. Public library functions
for Concept B would be limited to two levels, the third level being used for
library operational needs only. He painted out that because of ceiling
limitations, the basement of the renovated building would not be used by the
public at this point.
Mr. Robertson explained that the cost of concept B reflects the need for more
new construction and would total approximately $14,900,000. Because of its
flexibility in function, however, overhead and maintenance costs would be
e MINUTES--Eugene City Council September 12, 1990 Page 5
e less for Concept B than for Concept A. Mr. Robertson stated that in Concept
B, it might be possible to use the basement space for additional underground
parking. The cost of this, which is not calculated into the total, would be
approximately $1,273,000.
Mr. Robertson noted that from a staffing standpoint, Concept B allows for a
more efficient library operation and is the preferred design of the Library
Board.
Responding to a question from Mr. Boles, Mr. Robertson said that both con-
cepts provide elevators for accessibility needs.
Mr. Robertson said that the outside of the building is primarily glazed brick
with colored ceramic tile and a precast concrete base. Mr. Miller pOinted
out the importance of wood products in our community and asked why wood was
not chosen for the exterior of the building. In response, Mr. Robertson said
that brick and ceramic tile were chosen because they are low-maintenance
materials and would rarely need replacing. He noted, however, that wood can
playa major role in the interior library design.
Mr. Boles observed that the main entrance of the proposed library building is
on 10th Avenue, away from the downtown mall. He asked whether consideration
was given to deepening the plaza on the other side. Mr. Robertson said that
the opportunity exists to extend plaza design to the north and create a
larger plaza.
e Responding to a question from Mr. Miller, Mr. Robertson said that no consid-
eration was given to dividing library construction into phases. Although
there might be some additional costs, phased library construction would be a
poss i bil ity.
Mr. Holmer asked what the costs of constructing an equivalent building on
another location might be. In response, Mr. Robertson agreed to provide the
council with these figures. He noted that, although they are not as signifi-
cant as he would like, there are cost savings associated with renovating
rather than destroying the existing building.
Responding to a question from Mr. Green concerning library parking, Mr.
Robertson said that the architects envision a parking lot renovation to
include planting strips, pedestrian walkways, and increased parking widths.
The cost of parking redevelopment, which is not included in overall cost
figures, would approach $200,000. In light of the current fuel situation,
Mr. Boles expressed concern with increasing the size of parking spaces to
accommodate less fuel-efficient cars.
Ms. Bascom asked whether technological advancements in library operation such
as the replacement of books by compact disks have been considered in library
design needs. Mr. Robertson said that consideration has been given for the
"cutting edge" of library services in the future.
e MINUTES--Eugene City Council September 12, 1990 Page 6
e Ms. Ehrman asked whether it would be possible, if growth necessitated, to add
an additional floor to the Sears Building in the future. Mr. Robertson said
that column-stacking limitations would not allow the addition of another
floor.
Ms. Bascom noted that both design concepts plan for having the bookmobile on
the library premises and asked whether it might be possible to move this
facility elsewhere. In response, Assistant Public Librarian Carole
Hildebrand said that it is important for bookmobile function to be located on
the premises. Additionally, Mr. Robertson pointed out the need to have
access to service vehicles on the library premises. Such an area might also
provide service to future branch libraries or provide space for volunteer
functions.
Mr. Rutan felt that the council should present only one library design option
to the public. He noted that people would not recognize a substantial dif-
ference between Concepts A and B and voiced concern that presenting both
designs would only confuse the public. He asked the council whether it might
not want to present only one option to the public. Further, he pointed out
that the council should be prepared to respond to questions about what a much
less expensive option might be.
Mr. Robertson said that reducing the amount of new construction is one means
of reducing library costs and that a smaller building would result.
Ms. Schue pointed out the importance of listening to public feedback before
e selecting the most preferred library option. Ms. Bascom concurred.
Mr. Bennett said that Concept A is an unsatisfactory option because of its
ceiling limitations and felt that it should be eliminated from further con-
sideration. He proposed that Concept B should be placed before the public
with the possible inclusion of a phased-construction approach.
Ms. Ehrman noted that the Sears Building was initially attractive to the
council because it already provided sufficient surface parking. With this in
mind, the parking option available in Concept B might generate a lot of
community controversy.
Mr. Miller emphasized the need for public participation in the library design
process. He advised the council not to eliminate either concept without
first obtaining public feedback. He also stated that library design cost
will be a major concern within the community.
Mr. Green agreed with Mr. Miller on the need for public feedback.
Ms. Schue advised the council to present one concept, Concept B, to the
community. She noted further that whatever the decision, the council needs
to be genuinely responsive to public input.
(At 1:25 p.m., Mayor Miller left the meeting and Councilor Schue became
Chair.)
e MINUTES--Eugene City Council September 12, 1990 Page 7
e IV. WORK SESSION; DEVELOPMENT SERVICES FINANCING STUDY
The council postponed the agenda item due to insufficient time for discus-
sion. The council requested that it be placed on the next possible agenda.
V. ORDINANCE (REVISION) GRANTING AN EXCEPTION FOR OUTDOOR BURNING IN
WILLOW CREEK NATURAL AREA
City Manager Mike Gleason introduced the topic.
CB 4245--An ordinance granting an exception to the application
of Eugene Code, 1971, Section 6.200; and declaring an
emergency.
Mr. Bennett moved, seconded by Ms. Ehrman, that the bill, with
unanimous consent of the council, be read the second time by
council bill number only, and that enactment be considered at
this time. Roll call vote; the motion carried unanimously,
6:0.
Council Bill 4245 was read the second time by bill number only.
Mr. Bennett moved, seconded by Ms. Ehrman, that the bill be
e approved and given final passage. Roll call vote; with all
councilors present voting aye, the bill was declared passed
(and became Ordinance 19715).
At 1:45 p.m., the meeting of the Eugene City Council adjourned.
~~