Regular meeting of the City Council of the City of Eugene, Oregon, was called to
order by His Honor Mayor Gus Keller at 7:30 p.m., Council Chambers, May 14, 1979,
with the following Councilors present: Jack Delay, D. W. Hamel, Eric Haws, Scott
Lieuallen, Brian Obie, Gretchen Miller, and Emily Schue. Betty Smith was absent.
I. Agenda Addition--SB 472
(Memorandum Distributed)
Manager asked for a motion to consider the City's strategies in dealing
with SB 472. He explained that the grass seed growers and the Legisla-
ture, in enacting SB 472, have refused to take responsibility for air
quality in the Willamette Valley and the City sees no alternative but to
seek legal remedies.
-
Mr. Delay moved, seconded by Mr. Haws, to amend the agenda to
consider SB 472 and its consequences. Motion carried unanimously.
Mr. Long explained that 5B 472 applies not to this year's burning, but
to next year's burn, and sets the acreage limit at 250,000. The City
opposed this bill and they were almost successful. The alternatives open
to the City now are several: First would be involvement in the admini-
strative process of the Environmental Protection Agency wherein there
is a request by the State of Oregon to go from the present limitation
of 50,000 acres to 180,000 acres. The City would, if the motion passed,
intervene directly in that matter and attempt to defeat the amendment to
the State Implementation Plan. That would make the limitation 50,000
acres. Second would be, with the Council's authority, to develop some
possible issues to present to Federal Court in the form of a declaratory
judgment or some similar proceeding. Finally, the City could assist the
State and Federal governments in enforcing the limitation ultimately
established for this and for next year.
Mayor expressed his frustration at the Legislative hearing. People
who testified seemed to feel that Eugene had done nothing about air
pollution. He asked the Council to take a strong position. He said
that Eugene will suffer economically because of the impact on growing
businesses and industries. The grass seed growers refused to compro-
mise. He lauded the fine work of the legislators who supported the
City.
Mr. Delay moved, seconded by Mr. Hamel, that the Council instruct
staff to pursue whatever remedies are or may be available to the
City in this matter. Motion carried unanimously.
e
ZS6
5/14/79--1
II. Public Hearings
A. Consideration of Jetboats on Willamette River Issue (Materials Dis-
tributed)--Manager noted the City had received a petition and a
large amount of correspondence asking the City Council take an
active role in this matter. The Planning staff has done preliminary
research on how to go about this. It will require a lot of legal
research and staff time. Who has control over the river and its
banks seems to be something that needs clarifying.
e
Public hearing was opened.
Speaking in favor of the jetboats on the Willamette River was:
Roger Eugene Lefler, PO Box 389, Rogue River, owner of the jetboat
operation; he said he would answer any questions.
Those speaking against the jetboats on the Willamette River were:
Ka, Robinhold, 4450 Hilyard; Fred Mohr, 2662 Alder; Louis Osternig,
79 Fair Oaks; Terry McCabe, 1717 Carmel; John McCaffrey, 414 East
15th Avenue; Peter M. Patricelli, MD, 2385 Madrona; Michael Piper,
2682 Potter; Steve Gilbert, 1260 Fairview; Richard Bappe, 1172 West
5th Avenue; Ron McMullan, 1420 East Briarcliff Lane; and George Gary,
1970 Grant.
Those who testified against the jetboats on the Willamette River did
not like the noise of the 40-passenger vehicle. They were concerned ~
about safety for canoeists, fishermen, and waders. Fishermen asked ~
why an environmental impact statement had not been required. Citing a
New Zealand study of 40-percent mortality to salmon eggs when jetboats
stir the spawning beds, they asked why the Oregon Fish & Wildlife
Commission was not concerned. One suggestion was to declare a "quiet
zone" from the Ferry Street Bridge to Beltline Bridge. They noted
that this was a beautiful, safe stretch of river unique for being a
safe place for people to canoe and raft. They asked why an impact
statement was not asked for by the Army Corp of Engineers before the
dock was built. Two studies were cited: One concerned the phasing
out of motorized traffic on the Colorado River in the Grand Canyon.
The other concerned the monitoring by the BLM of conflicts between
motorized and non-motorized vehicles on the Rogue River. The cost
of regulation of motorized boats on the Willamette River was another
concern of those who testified.
Public hearing was closed, there being no further testimony
presented.
Mr. Delay moved, seconded by Mr. Hamel, to defer action to a less
crowded agenda in order to provide the Council more time to
consider the matter.
5/14/79--2
e
251
-
Ms. Schue asked for more information. She wondered how much authority
the City had in this matter. Mr. Lieuallen asked the staff to research
the question of jurisdiction. He said the "quiet zone" had a great
appeal to him, and asked if that would be legally possible.
Mr. Long said that the question of jurisdiction was a tangle and would
take a long time to unravel. Did the Council want to pursue it?
Ms. Miller noted that this is an issue of the City, County (the
boat dock is on an easement owned by the County), the State Marine
Board, the State Department of Environmental Quality, and the Corp
of Engineers. It was hoped that action could be taken in a few weeks
as they get more information.
Manager noted that the intent of the motion was that, in perhaps a
month, staff would come back with preliminary answers, an estimate of
what might be involved, and the best way to pursue the matter.
Vote was taken on the motion which carried unanimously.
B.
Rezoning From RA to R-2 propertf Located West of Oak Patch Road On
North Side of West 15th Avenue Polioudakis) (Z 79-3) (Map Distri-
buted)--Unanimously recommended by the Planning Commission on April 3,
1979.
-
Mr. Saul said that this rezoning involves 9,780 square feet presently
developed as a single-family residence. The property could be devel-
oped to a maximum of three units under the proposed zone change.
Almost all the property surrounding this one is already zoned R-2.
Since 1967, there have been ten zone changes to R-2 along Oak Patch
Road between 18th and 11th. The findings of the Planning Commission
recommend this zone change on the grounds of consistency with the
General Plan, the issue of public need, and the other applicable
standards.
No ex parte contacts or conflicts of interest were declared by the
Councilors.
Staff notes and minutes were entered into the record.
Public hearing was held, with no testimony presented.
CB 1885--Authorizing rezoning from RA to R-2 property located west
of Oak Patch Road on the north side of West 15th Avenue
was read by council bill number and title only, there being
no Councilor present requesting it be read in full.
Mr. Delay moved, seconded by Mr. Hamel, that the findings sup-
porting the rezoning, as set forth in Planning Commission staff
notes and minutes of April 3, 1979, be adopted by reference
-
2~
5/14/79--3
thereto; that the bill be read the second time by council bill
number only, with unanimous consent of the Council; and that ....
enactment be considered at this time. Motion carried unani- ~
mously and the bill was read the second time by council bill
number only.
Mr. Delay moved, seconded by Mr. Hamel, that the bill be approved
and given final passage. Roll call vote. All Councilors present
voting aye, the bill was declared passed and numbered 18392.
c. Rezoning From RA to R-2 Property Located at the Southeast Corner of
9th Avenue and Hayes Street (Booth) (Z 79-4) (Map Distributed)--Unani-
mously recommended by the Planning Commission on April 13, 1979.
Mr. Saul said that this involves 8,750 square feet and is vacant at
this time. Under the existing zoning, the property could be developed
as a duplex; under the proposed zoning, it could be developed as a
tri-plex. This is a small area of the city where the Planning Commis-
sion and the City Council have been attempting to encourage residential
development over the past several years. The commitment of funds for
improvement of the park located just south of this area, as well as
the denial of several zone changes that would have resulted in conver-
sion of residential property to non-residential use, are indications
of this encouragement. One of the denials was for this property for
a conversion to C-1.
No exparte contacts or conflicts of interest were declared by
Councilors.
Staff notes and minutes were entered into the record.
e
Public hearing was held, with no testimony presented.
CB 18B6--Authorizing rezoning from RA to R-2 property located at the
southeast corner of 9th Avenue and Hayes Street was read by
council bill number and title only, there being no Councilor
present requesting it be read in full.
Mr. Delay moved, seconded by Mr. Hamel, that findings supporting
the rezoning as set forth in Planning Commission staff notes and
minutes of April 3, 1979, be adopted by reference thereto; that
the bill be read the second time by council bill number only, with
unanimous consent of the Council; and that enactment be considered
at this time. Motion carried unanimously, and the bill was read
the second time by council bill number only.
Mr. Delay moved, seconded by Mr. Hamel, that the bill be approved
and given final passage. Roll call vote. All Councilors present
voting aye, the bill was declared passed and numbered 18393.
5/14/79--4
e
~5~
-
e
e
-'-------~,.;-
-~,
D. Garbage Rate Increase Request (Materials Distributedl--Manager said
this matter had been discussed at previous Council meetings. The
matter had been reviewed and studied by the Garbage Board. The
recommended increase amounts to 6.9 percent. The last increase was
March 1, 1978. This increase would become effective June 1, 1979.
In the agreement, there was a provision that the haulers would abide
by financial accounting procedures worked out by the Finance Department.
Public hearing was held, with no testimony presented.
Res. No. 3140--Concerning customer rates for garbage collection and
authorizing an increase was read by number and title.
Mr. Delay moved, seconded by Mr. Hamel, to adopt the resolution.
Mr. Hamel asked if there could be consideration given to having the
garbage haulers act independently so that, if they increase their
fees, citizens would have the option of changing garbage haulers.
Manager said that it had been considered and rate cutting was a
concern. The idea that one or two garbage haulers might emerge
on top was undesirable; however, it could be considered.
Motion carried, all Councilors present voting aye except Mr. Haws
voting no.
E.
for Somerset
Mr. Saul said that this appeal is a challenge to the preliminary
approval of Phases 5, 6, and 7 of Somerset Hills PUD, granted April 6,
1979. The appeal challenges only one aspect of the approval; that is,
the location of a driveway into a parking lot that is part of the
development. The appeal alleges that cars exiting from the driveway
at night onto Timberline shine their lights into the appellant's home
and that the problem could be eliminated by moving the driveway
further to the north.
No exparte contacts or conflicts of interest were declared by
Council ors.
Staff notes and minutes were entered into the record.
Public hearing was opened.
Michael Dooley, 2641 Woodstone Place, landscape architect, noted that
he had submitted materials to the Council that explained his position.
He said the driveway was a 14-percent grade and lights on high beam
from cars would shine in his house. He explained his desire to have
the driveway moved further to the north.
5/14/79--5
260
,""""""- "
Dick Unruh, Moreland, Unruh & Smith, Architects, noted that the
Council had before them answers to Mr. Dooley's appeal. He referred ....
to the untimeliness of the appeal, saying that Mr. Dooley could have ~
appealed the PUD at the diagrammatic phase of the PUD. He noted that
entering traffic was not a problem, nor was daytime traffic. He felt
that Mr. Dooley's planned road was unworkable. He differed with Mr.
Dooley.s findings concerning headlights, saying that low beam lights
do not reach Mr. Dooley's home.
Mr. Dooley felt that he was asking for a minor change. He disagreed
with the unworkable aspect of the suggested road change. He, again,
disagreed that lights would not reach his home.
Public hearing was closed, there being no further testimony.
Mr. Obie asked about putting a sign asking that lights be lowered.
Mr. Saul replied that it was not in the Council's interest to set
that kind of condition which would be very difficult to enforce
through the years as it would be on private property.
Mr. Delay moved, seconded by Mr. Hamel, to deny the appeal.
Motion carried, all Council members voting aye, except Mr. Haws
voting no.
F. Appeal of Planning Commission Action Re: Code Violation Regarding
Austin B. Petersen, dba Austin 1-Sto Plumbin Located at 2228 Olive
Street CV 79-1 Map Distributed --Manager noted this Zoning Code
violation related to the storage of commercial materials and parking
of commercial vehicles at a residence. The matter was brought before ~
the Planning Commissfon on two occasions: One when the Petersens were ..
unable to attend; the second on March 6, 1979, when the Planning
Commission ruled that there was a violation after testimony from the
neighborhood. The Planning Commission ordered the storage terminated
at this location. The violator could then appeal, followed up by a
statement of appeal, stating the reasons. This statement of reasons
for appeal has not been received by the City. It is within the
authority of the Council to dismiss the appeal.
Mr. Saul asked that the Council, as a preliminary matter, decide if
it wished to dismiss the appeal on the grounds that the requirements
of the City Code for conduct of an appeal had not been met.
Mr. Long stated that, in the past, the position of the Council has
been that it will not hear an appeal when the requirements of the
Code have not been complied with, and the omissions are serious. The
applicant was twice told, once by letter and once in person, that they
must file a statement setting forth their reasons for the appeal. The
Council may dismiss this appeal.
Mr. Haws moved, seconded by Mr. Delay, to dismiss the appeal. The
motion carried unanimously.
5/14/79--6~
2&1
e
G. New Liquor License Outlets
1. La Nouba, 380 West 13th Avenue (RMB/PS) (Richard Fulwiler,
Donald Marsh)
Manager noted that there had been objectors in the neighborhood.
The lack of parking is a problem. Public Works has noted that
on-site parking has not been provided and would be required at a
ratio of one space per 60 square feet of building area. There is
controversy concerning this application, and there is a parking
problem.
e
Public hearing was opened.
Those speaking against the proposed liquor license were:
John C. Furney, 347 West 13th Avenue, submitted a petition of 15
names. He was also representing John & Jill's Market. He and the
petitioners objected because of inadequate parking, live entertain-
ment, intoxicated drivers, and the possibility of danger to the
area stores and homes. He did not object to having a deli in the
neighborhood.
Dale Berg, 397 West 13th Avenue, said that he looked forward to
the deli, but did not like this approval because there was not
adequate parking. His establishment did not want to provide that
parki ng.
Chester Pietka, 372 West 12th Avenue, also objected to approval
because of inadequate parking. He liked the idea of having a
deli; he was concerned about noise at the house next door.
Those speaking in favor of the proposed liquor license were:
Don Marsh, 380 West 13th Avenue, partner in this establishment,
admitted parking was a problem. There was parking at Berg's Ski
Shop and at Pietka's. They would have parking at the Wagon Wheel.
The nature of the clientele would be in and out.
Public hearing was closed, there being no further testimony.
Manager said that Mr. Allen advised that if they do not have
parking on the site, they are allowed to have parking within 400
feet of the site. His department would not issue a permit unless
there was sufficient parking space (one per 60 square feet). Mr..
Marsh said that he understood it was related to the seating spacE~.
Manager thought nine spaces; Mr. Marsh thought three to four
spaces were necessary.
-
Mr. Obie said the issue was selling beer and wine on the premises.
Mr. Haws asked the criteria for issuing a liquor license and
wondered if parking was one of them.
2'2
5/14/79--7
Mr. Delay moved, seconded by Mr. Hamel, to forward the recommen-
dation for approval, subject to conditions. The motion carried
unanimously.
-
2. Valley River Union, 1125 Valley River Drive, (PS) (William
Larson)
Manager said this request was from a gas station that said that
they would be selling other foods, too. The application was in
order.
Public hearing was opened, there being no testimony.
Mr. Delay moved, seconded by Mr. Hamel, to forward recommendation
for approval, subject to conditions. Motion carried, all Councilors
voting aye, except. Mr. Obie voting no.
H. Public Works Bid Awards (Attached; Opened May 8, 1979, 10 a.m.)--Manager
noted that there were 11 different bid awards.
Mr. Allen suggested the approval of the low bids on each item, except
6 and 10. Number 6 was initially approved by 54 percent of the
property owners. Since that date, one of the property owners withdrew,
reducing the petition to 35 percent. The developer adjacent to the
street indicated that there is a contractual agreement that makes one
property go along with approving the street. That would put the
percentage to 50. The City does not become the banker on this project.
On the paving of Broadmoor, Item 10, $37.60 per front foot is the
price of this project. The project was proposed in 1969, and cost ~
$10.00 per front foot at that time. It was rejected by the property
owners.
Public hearing was opened on the paving in Project 6.
Those speaking in favor of the project were:
Floyd Wilkes, 2310 Tabor Street, the original developer of property,
said that 50 percent of the property owners are obligated to participate
according to an agreement which covers all property in Wilkes Plat and an
adjoining piece of property on the same side of the street, Which had
an agreement with the then owner of the property.
Larry Jackson, 1373 Bond Lane, said that his name had been removed
from the petition. Public Works told him that he could remove his
name. He asked that the contract not be awarded. He said that he was
not against the development, but against the way it was handled.
5/14/79--8
e
U3
e
Mrs. Robert Self, 1395 Bond Lane, did not like the way this was
handled. She understood that the City required 50 percent of the
property owners to request the street improvement. She did not
understand why they should pay for a road that was necessary for
the developer to develop his land.
Public hearing was opened on the paving for Project 10.
Speaking in favor of the project was:
Peter Ogan, 2096 Broadview, representing three families on Broadview,
objected to the dust and dirt in the summer, and mud in the winter.
He felt that, as a taxpayer, it was not unreasonable to ask for an
improved street.
Speaking against the project were:
Kathleen Springate, 2095 Broadview, who objected to the street improve-
ment on the grounds that the street was adequate and that they would
be assessed $7,500. She said they would have to close off one of
their driveways because the street height would make the driveway
unusable. She said that 52 percent of the land along the street was
owned by people who did not want the improvement.
-
Paul Hobo, 2090 Broadview, stated that his street is paved and he is
happy with it. He did not want to pay $2,700 to repave the stree~.
The height and width of the street design were not to his liking, and
did not fit in with what is now there. He urged the City to start at
the Springate's driveway and to make a short street.
Public hearing was closed on Items 6 and 10, there being no further
testimony.
Mr. Allen, commenting on the Bradley Street project, said that the
City Council respects the right of an individual to withdraw their
name. That has nothing to do with the process. The contract would
mean that the City was within their rights to assess the property
owners. We would still recommend that project on the condition that
the developer is responsible for the deferred assessments.
Mr. Allen, commenting on Item 10, Broadview, said that the comments
were similar to the ones in 1969. One curb would be higher than
the other for drainage, no storm sewer being added.
Mr. Delay moved, seconded by Mr. Hamel, to award low bids as
recommended, with the conditions set forth by Mr. Allen on Item 6
concerning street dedication, and the deferred assessments.
Motion carried, all Councilors present voting aye, except Ms.
Miller voting no.
-
5/14/79--9
2~
III. Ordinance for Second Reading
CB 1878--Regarding land development; amending Section 7.279 of the Eugene ~
Code, 1971, and declaring an emergency was read by council bill
number and title only, there being no Councilor present requesting
it be read in full.
Mr. Delay moved, seconded by Mr. Hamel, that the bill be approved
and given final passage. Roll call vote. Motion carried, all
Councilors present voting aye, except Mr. Haws and Ms. Miller
voting no, and Mr. Obie abstaining.
IV. Ordinances for First Reading
CB 1887--Levying assessments for paving, sanitary sewer, and storm sewer
within Plum Tree Subdivision; and paving, sanitary sewer, and
storm sewer within Janisse Subdivision and storm sewer within 160
feet of the east boundary of Janisse Subdivision extended north
to the Amazon Channel (1453, 1457) (78-10, 78-11) was read by
council bill number and title only, there being no Council member
present requesting it be read in full.
Mr. Delay moved, seconded by Mr. Hamel, that the bill be read the
first time and be referred to Hearings Panel for hearing May 21,
1979, with Panel recommendations to be brought back for Council
consideration and final reading May 29, 1979. The motion carried
unanimously.
CB 1888--Levying assessments for the sanitary sewer to serve Essex Heights
Subdivision (1462) (78-30) was read by council bill number and
title only, there being no Council member present requesting it
be read in full.
-
Mr. Delay moved, seconded by Mr. Hamel, that the bill be read the
first time and be referred to Hearings Panel for hearing May 21,
1979, with Panel recommendations to be brought back for Council
consideration and final reading May 29, 1979. The motion carried
unanimously.
CB 1889--Levying assessments for paving on Hawkins Lane from Highland
Oaks Boulevard to 250 feet south of 25th Avenue; and on 25th
Avenue from 500 feet west of Hawkins Lane to Hawkins Lane (1487)
(78-34) was read by council bill number and title only, there
being no Council member present requesting it be read in full.
Mr. Delay moved, seconded by Mr. Hamel, that the bill be read the
first time and be referred to Hearings Panel for hearing May 21,
1979, with Panel recommendations to be brought back for Council
consideration and final reading May 29, 1979. The motion carried
unanimously.
5/14/79--10 ~
U5
-
CB 1890--Levying assessments for paving, sanitary sewer, and storm sewer
within Commerce West Business Park; and sanitary sewer within 160
feet of the west boundary of Commerce West Business Park (1444)
(78-44) was read by council bill number and title only, there
being no Council member present requesting it be read in full.
Mr. Delay moved, seconded by Mr. Hamel, that the bill be read the
first time and be referred to Hearings Panel for hearing May 21,
1979, with Panel recommendations to be brought back for Council
consideration and final reading May 29, 1979. The motion carried
unanimously.
CB 1891--Levying assessments for storm sewer between Echo Hollow and
Ellsworth Street from the Marshall Ditch to Royal Avenue (1155)
(78-63) was read by council bill number and title only, there
being no Council member present requesting it be read in full.
Mr. Delay moved, seconded by Mr. Hamel, that the bill be read the
first time and be referred to Hearings Panel for hearing May 21,
1979, with Panel recommendations to be brought back for Council
consideration and final reading May 29, 1979. The motion carried
unanimously.
-
CB 1892--Levying assessments for paving, sanitary sewer, storm ~ewer,
and pedestrian way within and adjacent to Skywood Subdivision
(1458) (78-16) was read by council bill number and title only,
there being no Council member present requesting it be read in
full.
Mr. Delay moved, seconded by Mr. Hamel, that the bill be read the
first time and be referred to Hearings Panel for hearing May 21,
1979, with Panel recommendations to be brought back for Council
consideration and final reading May 29, 1979. The motion carried
unanimously.
CB 1893--Levying assessments for paving, sanitary sewer, and storm sewer
to serve Lincoln Crest Subdivision and paving on Lincoln Street
from 31st Avenue to Crest Drive (1421) (78-21) was read by
council bill number and title only, there being no Council
member present requesting it be read in full.
Mr. Delay moved, seconded by Mr. Hamel, that the bill be read the
first time and be referred to Hearings Panel for hearing May 21,
1979, with Panel recommendations to be brought back for Council
consideration and final reading May 29, 1979. The motion carried
unanimously.
CB 1894--Levying assessments for paving, sanitary sewer, and storm sewer
within and adjacent to Leo & Betty Davis Subdivision; sanitary
sewer within 160 feet of the north, south, and east boundaries of
e
2~b
5/14/79---11
Leo & Betty Davis Subdivision; and paving, sanitary sewer, and
storm sewer within Linmar Subdivision and sanitary sewer within ~
160 feet of the east margin of Linmar Subdivision (1396, 1464) ~
(78-24) was read by council bill number and title only, there
being no Council member present requesting it be read in full.
Mr. Delay moved, seconded by Mr. Hamel, that the bill be read the
first time and be referred to Hearings Panel for hearing May 21,
1979, with Panel recommendations to be brought back for Council
consideration and final reading May 29, 1979. The motion carried
unanimously.
CB 1895--Levying assessments for paving, sanitary sewer, and storm sewer
within South Vista Subdivision; and to serve Anne Plat; and
sanitary sewer to serve within 160 feet of the north and south
boundary of Anne Plat (1423, 1440) (78-33) was read by council
bill number and title only, there being no Council member
present requesting it b~ read in full.
Mr. Delay moved, seconded by Mr. Hamel, that the bill be read the
first time and be referred to Hearings Panel for hearing May 21,
1979, with Panel recommendations to be brought back for Council
consideration and final reading May 29, 1979. The motion carried
unanimously.
CB 1896--Levying assessments for paving, sanitary sewer, and storm sewer
to serve Weiger Park Subdivision (1517) (78-38) was read by
council bill number and title only, there being no Council member
present requesting it be read in full.
Mr. Delay moved, seconded by Mr. Hamel, that the bill be read the
first time and be referred to Hearings Panel for hearing May 21,
1979, with Panel recommendations to be brought back for Council
consideration and final reading May 29, 1979. The motion carried
unanimously.
e
CB 1897--Levying assessments for a storm sewer in Dillard Road from
43rd Avenue to 300 feet southeast of 43rd Avenue; and 100 feet to
300 feet south of 43rd from Dillard Road to 800 feet east (1618)
(78-57) was read by council bill number and title only, there
being no Council member present requesting it be read in full.
Mr. Delay moved, seconded by Mr. Hamel, that the bill be read the
first time and be referred to Hearings Panel for hearing May 21,
1979, with Panel recommendations to be brought back for Council
consideration and final reading May 29, 1979. The motion carried
unanimously. .
5/14/79--12 ~
Z~7
e
CB 1898--Levying assessments for sanitary sewer to serve Tax Lots
18-03-17-10-4801 and 4805 adjacent to East 43rd Avenue (1589)
(78-61) was read by council bill number and title only, there
being no Council member present requesting it be read in full.
Mr. Delay moved, seconded by Mr. Hamel, that the bill be read the
first time and be referred to Hearings Panel for hearing May 21,
1979, with Panel recommendations to be brought back for Council
consideration and final reading May 29, 1979. The motion carried
unanimously.
CB 1899--Levying assessments for a sanitary sewer in Gilham Road from
Kidder Subdivision south to existing sanitary sewer (1534)
(78-66) was read by council bill number and title only, there
being no Council member present requesting it be read in full.
Mr. Delay moved, seconded by Mr. Hamel, that the bill be read the
first time and be referred to Hearings Panel for hearing May 21,
1979, with Panel recommendations to be brought back for Council
consideration and final reading May 29, 1979. The motion carried
unanimousl y.
v.
Resolutions
,-
Res. No. 3141--Authorizing payment of bills, claims, and progress payments
for period April 23 through May 14, 1979, was read by number
and ti tl e.
Mr. Delay moved, seconded by Mr. Hamel, to adopt the resolution.
Roll call vote. Motion carried unanimously.
VI. Approval of Minutes
Mr. Delay moved, seconded by Mr. Hamel, to approve Council minutes
of April 9, 1979, and April 23, 1979. Motion carried unanimously.
VII. Request for Future Agenda Item
Mr. Delay asked if the Hearings Panel process for the assessments could be
considered on a future agenda. He questioned the time they had spent on
thi s i tern, sayi ng that it was simi 1 ar to the time they spend on other
hearings panels. Mayor asked the Manager to put the public bids process
on an agenda.
-
UP~ made, seconded,
Charles T. HenrY~~
City Manager
(Recorded by Beth Conant)
BC:so/CM8a1
and passed, the meeting adjourned to May 16, 1979.
2t;8
5/14/79--13
e
AWARD
-
DEPARTMENT OF PUBLIC WORKS
Engineering Division
1. PAVING. SANITARY SEWER AND STORM SEWER
within and adjacent to Canyon View Estates
Subdivision. (Job $1569)
Bid No. 3
Opened: May 8. 1979
Contract Cost
Bidders:
1~ Morse Bros..Inc.---------------------$
2. H & J Construction-------------------$
3. Eugene Sand & Grave1.Inc.------------$
4. Shur-Way Contractors,Inc.------------$
5. Dan D. Allsup Contractor,Inc.--------$
6. Wildish Construction Co.-------------$
Basic
98,763.84
92.427.15
-0-
97,367.40
99,531. 75
-0-
Alternate
$ 89,498.62
$ -0-
$ 96.503.70
$ -0-
$ 111,492.25
$ 104,864.70
Amount Budgeted
None
'y:.
-----------------------------------------------------------------_._-------------------------------
e 2.
AWARD
Cost to Abutting Property
Cost to City
None
Contract Cost
Bidders: Basic Alternate
1. Shur-Way Contractors, Inc.------------$J43.988.85 $ -0-
2. Eugene Sand & Gravel, Inc.------------$ -0- $ 246,526.95
3. Wi1dish Construction Co.--------------$ -0- $ 250,176.75
4. Dan.D. Allsup Contractor,Inc.---------$ 278,035.30 $ 255,189.95
5. Morse Bros., Inc.---------------------$ -0- $ 256,446.10
6. H & J Construction--------------------$ 275,876.75 $ -0-
26'1
Amount Budgeted
$ 17,500.00
e
-------------------------------------------------------------------------------------------------
281 Paving,
San.Lateral
San.Service
Storm Sewer
5" Concrete
$ 33.20/FF
$ 1.140/Lot
$ 640/Lot
$ 1,420/Lot
$ 2.10/Lot
COMPLETION DATE: August 1, 1979
PAVING, SANITARY SEWER AND STORM SEWER within
Kiska Subdivision; sanitary sewer within 160 feet
of the east margin of Kiska Subdivision; paving,
sanitary sewer and storm sewer within Kukui Hill
Subdivision; and sanitary sewer within 160 feet of
the east and south margins of Kukui Hill Subdivision
(Job Nos. 1547 & 1549)
Cost to Abutting Property
281 PaVing $ 33.00/FF
361 Paving $ 40.60/FF
San.latera1 $ 0.17/SF
San.Service $ 500/Each
StormSewer $ 1,130/Lot
COMPLETION DATE: September 1. 1979
Cost to City
$ 19,500.00
3. PAVING, SANITARY SEWER AND STORM SEWER
within and adjacent to Nolan Industrial
Park (Job #1611)
Page 2
e
Bidders:
Contract Cost
Basic Alternate
AWARD
1. Wildish Construction Co.----------$ -0-
2. Morse Bros., Inc.-----------------$ 186,183.60
3. Eugene Sand & Gravel, Inc.--------$ -0-
4. Dan D. Allsup Contractor, Inc.----$ -0-
5. H & J Construction----------------$ 178,438.10
Cost to Abutting Property:
Cost to City
$ 4,700.00
441 Paving
San.Lat.
San.Service
$ 37.30/FF
$ 0.06/SF
$ 430/Each
COMPLETION DATE: August 1, 1979
$ 165.885.65
$ 1"68,483.67
$ 169,347.51
$ 177,645.05
$ -0-
Amount Budgeted
$ 6,800.00
--------------------------------------------------------------------------------------------------
. ''t~
4. PAVING, SANITARY SEWER AND STORM SEWER
within and adjacent to Maracott Manor;
and storm sewer construction from east
pl~t boundary to 270 feet east (Job #1585)
Bidders:
Contract Cost
Basic Alternate
e
AWARD
1. H & J Construction------------------$ 27,188.00
2. Shur-Way Contractors,Inc.-----------$ 27,635.50
3. Morse Bros., Inc.-------------------$ 29,443.25
4. Eugene Sand & Gravel, Inc.----------$ -0-
5. Dan D. Allsup Contractor, Inc.------$ 35,084.90
Cost to Abutting Property
281 Paving $ 1,450/Lot
San.Serv. $ 1,100/Lot
StormSwr. $ 1,820/Lot
Cost to City
None
COMPLETION DATE: August 1, 1979
$ -0-
$ -0-
$ -0-
$ 31,375.65
$ 35,845.40
Amount Budgeted
None
-------------------------------------------------------------------------------------------------
2..10
e
e 5.
AWARD
e 6.
AWARD
PAVING, SANITARY SEWER AND STORM SEWER to
serve White Oak Heights Subdivision; and
sanitary sewer within 160 feet of the west
boundary of White Oak Heights (JOb #1608)
Bidders:
Contract Cost
Basic Alternate
1. Morse Bros., Inc.--------------------$ 98~928.25
2. H & J Construction-------------------$ 102,613.31
3. Shur-Way Contractors, Inc.-----------$ 105,013.97
4. Dan D. Allsup Contractor, Inc.-------$ -0-
5. Eugene Sand & Gravel, Inc.-----------$ -0-
6. Wildish Construction Co.-------------$ -0-
Cost to Abutting Property
$ 99,481.00
$ -0-
$ -0-
$ 108,373.91
$ 117,990.10
$ 121,076.85
28' Paving
San. Lat.
San.Serv.
Storm Swr.
None
Cost to City Amount Budgeted
None
$ 2,470/Lot
$ 1,770/Lot
$: 210/Lot
$ 700/lot
COMPLETION DATE: August 1, 1979
PAVING, SANITARY SEWER AND STORM SEWER in
Bradley Drive adjacent to Wilkes Plat from 450 feet
north of Bond lane to Bond lane; and storm sewer
construction within Wilkes Plat. (JOb #1472)
. 'v-
Bidders
Contract Cost
Basic Alternate
1. Eugene Sand & Gravel, Inc.-----------$ 27~460.40
2. Shur-Way Contractors, Inc. -----------$ -"27,781. 05
3. Dan D. Allsup Contractor, Inc.-------$ -0-
4. Wildish Construction Co.-------------$ 29,333.35
5. H & J Construction-------------------$ 31,567.90
6. Egge Sand & Gravel Co.---------------$ 32,120.00
7. Morse Bros., Inc.--------------------$ 34,264.50
Cost to Abutting Property
$ 27,858.90
$ -0-
$ 28,680.20
$ -0-
$ -0-
$ -0-
$ -0-
28' Paving
San.Swr.lat.
San.Swr.Serv.
$ 30.20/FF
$ 0.15/SF
$ 410/lot
None
Cost to City Amount Budgeted
None
COMPLETION DATE: August 17, 1979
Page 3
--------------------------------------------------------------------------------------------------
~
21/
Page 4
7. PAVING, SANITARY SEWER, STORM SEWER AND PEDESTRIAN
WAY to serve Anton Subdivision and Amber Subdivision
and sanitary sewer construction within 160 feet of
the east boundary of Anton Subdivision; and paving,
sanitary sewer and storm sewer construction within
Kerrick Subdivision and sanitary sewer within 160
feet of the north boundary of Kerrick Subdivision.
(Job Nos. 1335, 1654, 1601)
Contract Cost
Bidders: Basic Alternate
e
AWARD
1. Morse Bros., Inc.-------------------$ 182,948.50
2. Dan D. Allsup Contractor, Inc.------$ -0-
3. Eugene Sand & Gravel, Inc.----------$ -0-
4. H & J Construction------------------$ 199,604.65
5. Wildish Construction Co.------------$, -0-
$ .176,433~60
$ 180,903.60
$ 186,005.55
$ -0-
$ 219,446.63
Cost to Abutting Property
Cost to City Amount Budgeted
281 Paving
San.Swr.Lat.
San.Swr.Serv.
Storm Sewer
Ped.Way.
$ 22.30/FF
$ O.ll/SF
$ 255/lot
$ 310/Lot
$ 40/Lot
None
None
,.
COMPLETION DATE: September 1,1979
-
--------------------------------------------------------------------------------------------------
8. SANITARY SEWER to serve Banyan Subdivision
and sanitary sewer construction 350 feet
south of Ca1 Young Road from Hammock Street
to 240 feet east. (Job #1581)
Bi dders:
Contract Cost
AWARD 1. Eugene Sand & Gravel, Inc.-----------$ 9,089.00
2. Shur-Way Contractors, Inc.-----------$ 10,603.50
3. H & J Construction-------------------$ 12,053.00
4. Wildish Construction Co.-------------$ 13,003.00
5. Dan D. Allsup Contractor, Inc.-------$ 14,489.00
, Cost to Abutting Property
San.Swr.Lateral $0.25/SF
San.Swr.Service $40/Each
Cost to City
None
Amount Budgeted
None
COMPLETION DATE: July 13, 1979
-------------------------------------------------------------------------------------------------
-.
2..12.
,.
9. SANITARY SEWER to serve Coast Hills
~ Vista Subdivision. (Job #1551)
Bidders:
Contract Cost
AWARD 1. Dan D. Allsup Contractor,Inc.--------$ 11,217.65
2. Shur-Way Contractor,Inc.-------------$ 11,860.77
3. Wildish Construction Co.-------------$ 12,137.70
4. H & J Construction-------------------$ 12,683.50
5. Eugene Sand & Gravel,Inc.------------$ 13,412.00
Page 5
Cost to City Amount Budgeted
None None
Cost to Abutting Property
San.Sewerlateral $ 3,565/lot
San. SewerServ1 ce $ 25/Lot
COMPLETION DATE: July 20, 1979
--------------------------------------------------------------------------------------------------
10. PAVING Broadview Street from Hawkins Heights
Boulevard to Sunrise Boulevard. (JOb #440)
Bidders:
Contract Cost
Basic A1te~ate
AWARD
1. Egge Sand & Gravel Co.---------------$ 27,079.00
2. Wild1sh Construction Co.-------------$ -0-
3, Morse Bros.,Inc.---------------------$ 31,776.00
4. Eugene Sand & Gravel, Inc.-----------$ -0-
_)(1&1
Cost to Abutting Property
281 Paving $ 37.60/FF
211 A.C. Driveway $ 0.45/SF
511 Concrete $ 2.20/SF
Cost to City
None
COMPLETION DATE: July 1, 1979
$ -0-
$ 27,629.05
$ -0-
$ 33,009.50
Amount Budgeted
None
--------------------------------------------------------------------------------------------------
11. SIDEWALK on east side of Bailey Hill Road
from Westleigh Street to Warren Avenue; and
on Warren Avenue from Bailey Hill Road to
Timberline Dri~e; and on Timberline Drive
from Warren Avenue to Wilshire Lane. (Job #1224)
Bidder:
Contract Cost
AWARD 1. Walts Concrete Co.-------------------$ 9,227.50
2. H & J Construction-------------------$ 9,248.75
3. Morse Bros., Inc.--------------------$ 10,405.00
4. Eugene Sand & Gravel,Inc.-.----------$ 13,473.00
Cost to City Amount Budgeted
-~
Cost to Abutting Property
Sidewalk $ 2.15/SF
COMPLETION DATE: July 15, 1979
$ 5,700.00
$ 5,100.00
-------------------------------------------------------------------------------------- -----------