AN ORDINANCE AUTHORIZING THE INSTITUTION OF PROCEEDINGS
IN EMINENT DOMAIN FOR THE ACQUISITION BY CONDEMNATION
OF REAL AND PERSONAL PROPERTY USED FOR RENDERING
ELECTRICAL UTILITY SERVICE AND PRIMARILY LOCATED IN THE
WILLOW CREEK AREA, AND OWNED BY LANE ELECTRIC
COOPERATIVE, INC, AND/OR LANE COUNTY ELECTRIC
COOPERATIVE, INC.
The City Council of the City of Eugene finds that:
1. The City of Eugene has authority under both the Eugene
Charter and applicable state law to institute proceedings in
eminent domain far the acquisition by condemnation of real and
personal property far public purposes, including for the
improvement and expansion of the City of Eugene's electrical
distribution systems and the reallocation of electric utility
service areas.
2. Management of the growth of the City of Eugene is
guided ,in the first instance by the Metropolitan Area General
Plan Metro Plan, a land use comprehensive plan. The Metro Plan
requires the City to take steps to assure that the Eugene Water &
Electric Board is the provider of electrical utility service
within the urban growth boundary. The Metro Plan also requires
the City to make electrical service available to designated
special light industrial tracts in the Willow Creek area within
the urban growth boundary. The orderly and economic provision of
electrical service to this area is necessary to implement state
law as refined in the Metro Plan. The provision of such service
is necessary far the economic well-being of citizens of the City
of Eugene. The Metro Plan contains the fallowing policies
relevant to the provision of electrical service in the Willow
Creek area:.
a. Fundamental Principle No. 6 states that the
Metro Plan 'pis based on the premise that Eugene and
Springfield . are the logical providers of services
accommodating urban levels of development within the
urban growth boundary." Metro Plan, p. II-1.~
b. Growth Management Element Policy No. 16
commands that, "Eugene and Springfield and their
respective utility branches, Eugene Water and Electric
Board and Springfield Utility Board, shall be the water
and electrical service providers within the urban
growth boundary." Metro Plan, p. II-B-6.~
c. Economic Element Policies Nas. 6, 17, 2l, and
Ordinance - l
22 require the, City of Eugene,to increase the supply of
light industrial, land, particularly for .large scale
light manufacturing users, and to aggressively pursue
an annexation, servicing and coning program for
designated special light industrial sites. €Metro Plan,
pp, III-B-~5 and III-B-6.}
d. The Metro Plan diagram designates a large
parcel in the Willow Creek area as "Special Light
Industrial." The designation of this parcel and six
other special light parcels in the metropolitan area,
occurred after a canvass of the entire .area for
suitable parcels for this type of use. The Willow
Creek parcel is the premier special light industrial
site in the Eugene-Springfield area.
3. Because of these Metro Plan policies, the City of
Eugene has spent considerable public funds extending sanitary
sewers to the Willow Creek area and constructing public
improvements in that area. Since 1982, the City has extended the
West Eugene sewer trunk line to the Willow Creek area at a cast
of $2,7 million. Investments in streets, storm drainage, and
other public improvements have totalled $823,DDD.DD, Much of the
area was annexed to the City of Eugene in 1984-82 and 1987.
Without industrial development, the return an this public
investment in the area will be minimal,
4, Cost and reliability of electrical service are key
concerns to industries who are targeted to locate in the Willow
Creek area. According to the Metro Partnership, several
companies indicated they would not locate in the Willow Creek
area unless their concerns about cost and reliability of
electrical service were resolved. There have been a number of
other cases where electrical power would have been a serious
issue if negotiations had progressed. Prospective industries
have indicated a preference for EWEB service due to EWEB's proven
ability to provide highly reliable, low-cost electric service.
Companies already located in the Willow Creek area have also
expressed concerns about the cost and reliability of electrical
service from Lane Electric Cooperative ~LEC}.
5. At current rates, typical electric bills of existing
Willow Creek customers would drop by as much as 34~ if those
customers were served by EWER, dependent upon customer
classification and monthly use. According to a study conducted
for EWER by the consulting firm of R.W. Beck, Willow Creek
customers will save $4,3 million aver 2Q years if EWEB serves
them due primarily to these lower rates.
~. before full industrial development in the area can
occur, substantial expenditures on new electric facilities will
be needed. The R.W. Beck report concludes that the cast to
Ordinance - 2
provide service to Willow Creek would be $2.65 million lower if
EWEB serves the area. These savings are due primarily to
elimination of duplicative facilities necessary to connect EWE~'s
service areas which straddle the Willow Creek area and because
EWEB's operating expenses are lower than LEC's.
7, EWEB presently services property to the north, east,
west, and partly to the south of the Willow Creek area. EWEB
currently has electrical substations .2 and 1.5 miles from the
Willow Creek area. EWEB will construct electric circuits through
the Willow Creek area to serve its present customers. EWEB must
make this investment regardless of which utility services the
Willow Creek area. LEC will need to duplicate this investment in
order to serve the Willow Creek area.
8, EWEB presently provides the southwest area of Eugene
with an urban level of electric service that is highly reliable.
LEC currently provides a rural level of reliability for electric
service to the area, with frequent and longer interruptions of
service. In order for LEC to upgrade its f acilities to provide
an urban level of electrical service to the Willow Creek area, it
will need to make substantial expenditures. EWEB will be able to
provide power to users in the Willow Creek area more cheaply than
LEC and at lower rates.
9. The R.W, Beck report states that existing customers of
LEC will not pay significantly cheaper rates if LEC services the
Willow Creek area.
10. Under CRS 758.4701}, when a municipality condemns
another person's equipment, plant ar facilities for rendering
utility service, it acquires the utility's territorial allocation
that is served by the acquired properties. Condemnation of the
assets of Lane Electric Cooperative, Inc. used to provide
electric service to the Willow Creek area is necessary to effect
a reallocation of the service territory from LEC to EWEB. This
reallocation will result in the least private injury to LEC if it
occurs at the present time before significant investments have
been made by LEC in electrical facilities far the area.
ll. Attempts to negotiate a transfer of territory between
the utilities have failed, Negotiations in 1971, 1979, and 1987
were unsuccessful. An agreement was reached in 1975 and
submitted to the Public Utility Commissioner by the utilities.
This agreement was rejected by the PUC and abandoned by the
parties.
12. The policies of the Metro Plan, the interests of the
citizens of the City of Eugene in economic diversification,
avoidanc a of duplication of investments in electrical
distribution facilities, the least cost and injury to purchasers
of electricity, and improved marketability of industrial property
Drdinance -~ 3
in the Willow Creek area can best be served if EWEB provides
electrical service to the billow Creek area, The least private
injury to LEC will occur if the transfer of territory occurs
soon. The City Council concludes that a public necessity exists
for the acquisition of property owned by LEC for any of these
reasons and does not rely on the accuracy of any particular
finding made above in reaching this conclusion.
13. Lane Electric Cooperative is presently providing
electricity to customers within the City of Eugene and using
public right-of~-way for these purposes. LEC has no franchise
from the City of Eugene for this purpose.
Now, therefore, based an the above findings, the findings
set out in the staf f report, and the record and testimony before
the Council,
THE CITY CF EUGENE DOES CRDAIN AS F4LLCWS:
Section 1. Based generally on the above findings, which are
adopted and incorporated herein, the City Council determines that
it is necessary to acquire ownership of the real and personal
property of the electric distribution system located in the
Willow Creek area and owned by Lane County Electric Cooperative,
Inc. and/ar Lane Electric Cooperative, Inc., a description of
which is attached hereto as Exhibit "A" and incorporated herein
as though fully set forth.
Section 2. The City Council directs that the City of
Eugene, acting by and through the Eugene Water & Electric Board,
at least twenty ~ 20 3 days prior to the filing of any action for
condemnation shall make a written offer to the owners or parties
having an interest in the property described in Exhibit "A"
attached hereto, of a stated amount as compensation therefor and
that if that offer is not accepted that proceedings in eminent
domain be instituted for the condemnation of the above described
property.
Section 3. The City Council declares that acquisition of
title to the property described on Exhibit "A" is necessary far
the public welfare and for the public purposes described in part
in the above findings, that acquisition of the property and
service to the affected territory by EWEB is consistent with the
greatest public good and least private injury, and that
acquisition of the property is authorized under the laws of the
State of Oregon and the Charter, ordinances, Metropolitan ,Area
General Plan and policies of the City of Eugene.
Section 4. The City Council further declares that the
property described on Exhibit "A" shall be used by the City of
Eugene far public purposes at the earliest possible date and, in
Ordinance ~- 4
any event, na later than ten years from the date this Ordinance
is adopted by the Council and approved by the Mayar.
Passed by the City Council
this loth day of August, 1988.
City Recor er
ti 1988.
Ordinance - 5
Approved by the N~ayar
this 10th dax of Auau
EXHIBIT "A" TO CITY CF EUGENE
ORDINANCE N0. 19575
All rights. title, and interest in all real and personal
property composing the equipment, plant, and facilities owned or
controlled by Lane Electric Cooperative, Inc. and/ar Lane County
Cooperative, Inc., used to specifically serve the service area of
Lane Electric Cooperative located within the city limits of the
City of Eugene and south of West 11th Avenue and west of
Bertelsen Road, and including, but not limited to all electric
distribution facilities owned by Lane Electric Cooperative and/or
Lane County Electric Cooperative, located in the southwest
portion of the City of Eugene and within the city limitsf more
specifically located west of Bailey Hill Road, south of Royal
Avenue, east of Greenhill Road, and north of the existing
southern border of the city limits.
These electric distribution facilities include, but are not
limited to, all poles, boxes, conductors, conduits, transformers,
switches, meters, lighting, and other associated facilities
utilized to provide electric service and operating at less than
15,004 volts ~15kV~; and the "west 11th Avenue Substation",
including transformers, conductors, and associated facilities an
Bertelsen Road, south of west 11th Avenue.
The following electric facilities awned by Lane Electric
Cooperative and located within the above-described area are
excluded: poles, conductors, connectors, and other associated
facilities used for an existing Lane Electric Cooperative 34.5 kV
electric transmission circuit located in part on Bertelsen Road,
West 18th Avenue, and Four oaks Grange Road.