ADMINISTRATIVE ORDER
OF THE
PUBLIC WORKS DIRECTOR
City of Eugene, Oregon
IN ORDER TO:
A. Charge to local improvement districts, engineering fees that closely
reflect average costs, and,
B. Provide a fair and equitable charge for services to property owners,
THE PUBLIC WORKS DIRECTOR FINDS THAT:
1. The amount currently charged for engineering services to local
improvement districts is not adequate to recover the actual costs
incurred.
2. A study and analysis of these fees has been completed.
3. An increase in the current charge rate needs to be implemented in
order that the City may recover, on current and new projects, an
amount that more closely reflects actual costs.
4. The analysis indicates that engineering costs over the past
three years have averaged 21.35% of project construction costs.
BASED ON THE ABOVE FINDINGS, THE PUBLIC WORKS DIRECTOR ORDERS THAT:
--Property owners in local improvement districts be assessed a charge
for engineering services at a rate of 21% of actual project construc-
tion costs. This rate will apply to all projects assessed after
June 1, 1990 until changed by administrative order.
In accordance with authority granted by Section 7.007 of the Eugene Code,
1971, this administrative order is issued and dated ~I'~s- , 19Qo .
(j/~~
istine Andersen, Public Works Director