HomeMy WebLinkAboutItem 5: Beam Development Project Extension
EURA
UGENE RBAN ENEWAL GENCY
AIS
GENDA TEM UMMARY
Action: Beam Development Project Extension
Meeting Date: May 26, 2009 Agenda Item Number: 5
Department: Planning & Development Staff Contact: Denny Braud
www.eugene-or.gov Contact Telephone Number: 682-5536
ISSUE STATEMENT
The Urban Renewal Agency (URA) and Beam Development signed a Purchase and Sale Agreement
(PSA) in May 2008, for Beam’s purchase of the Centre Court building and adjacent vacant parcel, and
the Washburne Building (the Properties). The PSA includes a requirement that Beam begin construction
of the project no later than May 31, 2009. The URA is asked to consider Beam’s request to extend the
time for the start of construction.
BACKGROUND
Beam purchased the Properties from the URA in July 2008, for a total purchase price of $3.6 million
(Centre Court $1,946,000, vacant parcel $454,000, and Washburne Building $1,200,000). The URA
provided financing to Beam totaling $3.55 million for their acquisition of the Properties. The sources of
funds for the URA’s financing included HUD Section 108 loan funds ($2.7 million), Brownfield
Economic Development Initiative (BEDI) grant funds ($440,000), and Downtown Revitalization Loan
Program funds ($404,000). To date, Beam has made payments as agreed.
The PSA includes a provision that construction of the project would begin no later than May 1, 2009,
with a provision for up to an additional 30 days, if necessary, due to events or circumstances beyond
Beam’s reasonable control. The agreement requires Beam to provide written notice of the extension no
later than April 15, 2009, with a statement of the reasons they wish to extend the commencement date.
On April 10, 2009, Beam provided written notice of the 30-day extension, citing circumstances related
to the economy, including the tight lending market, elevated pre-leasing commitments required by
lenders, longer lease-up periods experienced in the market, and uncertainty regarding their previously
anticipated historic tax credits. (The letter is included in Attachment A.)
In Beam’s request for additional time, they indicated that they are in discussions with a major tenant and
would like the URA to consider an extension of the construction commencement date for an additional
six months to complete the necessary due diligence. Last week, Lane Community College (LCC)
announced that their board directed the President to proceed with formal discussions with the City to
explore alternative downtown locations for the new Downtown Center. The location of LCC at
Broadway and Willamette Street has the potential to support the vision for a signature building at the
intersection of Broadway and Willamette Street, enhance activity in the heart of downtown, support
affordable, lifelong educational opportunities, and demonstrate the community’s commitment to
sustainable development. Beam has shown strong interest in working with LCC and has provided a
Z:\CMO\2009 Council Agendas\M090526\S0905265.doc
summary of steps they propose to take to move the project forward. (See Attachment B - letter from
Beam). Because discussions with LCC are preliminary, an extension of time in the PSA is necessary for
Beam and the URA to further investigate the LCC opportunity.
In addition to an extension of time, and in light of council discussions on the City Hall building, a new
police facility, and other possible City office space scenarios, the City and Beam are discussing the
current tenant commitment included in the PSA. Based on the current PSA terms, the City has
committed to lease up to 50,000 square feet in a newly constructed building on the vacant parcel. There
could be more flexibility in the agreement regarding the City’s commitment in order for the City to
expand its opportunities. However, the City recognizes tenancy is an important issue for this project and
wants to remain as supportive as possible, while also maintaining the City’s flexibility. The removal of
the lease commitment would not preclude the City from leasing space from Beam in the future and we
will continue to discuss the potential of adding flexibility into the PSA as part of this amendment.
RELATED CITY POLICIES
The proposed redevelopment along West Broadway is consistent with the policies and implementation
strategies included in the Downtown Plan, including:
?
Downtown development shall support the urban qualities of density, vitality, livability and
diversity to create a downtown, urban environment.
?
Actively pursue public/private development opportunities to achieve the vision for an active,
vital, growing downtown.
?
Use downtown development tools and incentives to encourage development that provides
character and density downtown.
?
Promote multi-story, mixed-use structures downtown through financial incentives or code
amendments.
?
Stimulate multi-unit housing in the downtown core and on the edges of downtown for a variety
of income levels and ownership opportunities.
?
Provide and promote development and community events that reinforce downtown’s role as the
cultural center for the city and region.
?
Reinforce the creative, distinctive culture of downtown as the arts and entertainment center of
the city.
In addition, the proposed development project is responsive to the following Growth Management
policies:
Policy 1: Support the existing Eugene Urban Growth Boundary by taking actions to
increase density and use existing vacant and under-used land within the boundary
more efficiently.
Policy 2: Encourage in-fill, mixed-use, redevelopment, and higher density
development.
Policy 3: Encourage a mix of business and residential uses downtown using incentives and
zoning.
Policy 10: Encourage the creation of transportation-efficient land use patterns and
implementation of nodal development concepts.
Z:\CMO\2009 Council Agendas\M090526\S0905265.doc
Policy 14: Development shall be required to pay the full cost of extending infrastructure and
services, except that the City will examine ways to subsidize the costs of
providing infrastructure or offer other incentives that support higher-density infill,
mixed use, and redevelopment.
COUNCIL OPTIONS
1.Direct the Agency Director to 1) amend the PSA to extend the required start of construction date by
six months to December 1, 2009; 2) negotiate with Beam to provide flexibility in the PSA, if
possible, in the City’s commitment for leased space, and if negotiations are successful to amend the
PSA without additional approval from the URA, and 3) continue discussions with Beam and LCC
regarding the possibility of locating a new LCC Downtown Center on the Beam property.
2.Direct the Agency Director to 1) amend the PSA to extend the required start of construction date by
six months to December 1, 2009, and 2) continue discussions with Beam and LCC regarding the
possibility of locating a new LCC Downtown Center on the Beam property.
3.Direct the Agency Director to not extend the required start of construction date in the PSA and
determine next steps.
AGENCY DIRECTOR’S RECOMMENDATION
The Agency Director recommends that 1) the PSA be amended to extend the start of construction date
by six months to provide the time necessary for discussions with Beam and LCC to proceed and 2) the
City negotiate with Beam to provide flexibility in the PSA, if possible, in the commitment for leased
space to allow for greater flexibility as the City considers space needs, and if negotiations are successful
to amend the PSA without additional approval from the URA, and 3) discussions with Beam and LCC
continue regarding the possibility of locating a new LCC Downtown Center on the Beam property.
SUGGESTED MOTION
Move to direct the Agency Director to 1) amend the PSA to extend the required start of construction
date by six months to December 1, 2009, 2) negotiate with Beam to provide flexibility in the PSA, if
possible, regarding the City’s commitment for leased space, and if negotiations are successful to amend
the PSA without additional approval from the URA, and 3) continue discussions with Beam and LCC
regarding the possibility of locating a new LCC Downtown Center on the Beam property.
ATTACHMENTS
A. April 10, 2009, Letter from Beam Development
B. May 7, 2009, Letter from City Manager
C. May 12, 2009, Letter from Beam Development
FOR MORE INFORMATION
Staff Contact: Denny Braud
Telephone: 682-5536
Staff E-Mail: denny.braud@ci.eugene.or.us
Z:\CMO\2009 Council Agendas\M090526\S0905265.doc