COUNCIL RESOLUTION NO. 4862
A RESOLUTION GRANTING AN EXEMPTION FROM
COMPETITIVE SELECTION REQUIREMENTS FOR A
PERSONAL SERVICES CONTRACT RELATING TO
DEVELOPER SERVICES AND DEVELOPER'S SELECTION
OF GENERAL CONTRACTOR FOR CONSTRUCTION OF A
PUBLIC PARKING FACILITY; AND APPROVING
FINDINGS RELATING THERETO.
PASSED: 5:2
REJECTED:
OPPOSED: Bettman, Taylor
ABSENT:
RECUSED: Pape
CONSIDERED: March 15, 2006
RESOLUTION NO. 4862
A RESOLUTION GRANTING AN EXEMPTION
FROM COMPETITIVE SELECTION
REQUIREMENTS FOR A PERSONAL SERVICES
CONTRACT RELATING TO DEVELOPER
SERVICES AND DEVELOPER'S SELECTION OF
GENERAL CONTRACTOR FOR CONSTRUCTION
OF A PUBLIC PARKING FACILITY; AND
APPROVING FINDINGS RELATING THERETO.
The City Council of the City of Eugene finds that:
A. The implementation strategies and policies set forth in the Downtown Plan, the
Growth Management Policies and the Goals and Objectives from the Riverfront
Urban Renewal District Plan (the "Implementation Strategies and Policies")
support downtown development that enhances the urban qualities of density,
vitality, livability and diversity. The Implementation Strategies and Policies
recognize the advantage of public/private development opportunities in achieving
the vision of an active, vital growing downtown, facilitating dense development in
the area of the Wayne Morse Federal Courthouse ("Courthouse") and constructing
a new parking facility that supports the east side of downtown and the new
Courthouse district.
B. Broadway & High Associates, LLC owns approximately one-half of the city
block located between 8th and Broadway and Mill and High Streets. The
Oregonians Federal Credit Union (the "Credit Union") owns approximately one-
quarter of the block and the City will acquire the remaining one-quarter block for
the purposes of participating in this project. Broadway & High Associates, LLC
and Gerding/Edlen Development Company (collectively, "B&H") have entered
into a contract for development of this property, as owner and developer,
respectively. B&H has entered into certain agreements with Whole Foods Market
("Whole Foods") and the Credit Union regarding the development of the entire
block.
C. B&H's development plans include two projects: the construction of a grocery
store with two levels of parking intended for private ownership and use (the
"Whole Foods Project") and the construction of a four level, 260 space public
parking structure that includes, on the ground level, a small publicly-owned
commercial space and a second commercial space that will be privately owned
and occupied by the Credit Union (the "Parking Project").
Resolution - 1
D. The Whole Foods Project and the Parking Project are consistent with the
Implementation Strategies and Policies.
E. B&H has proposed, and the City of Eugene ("City") has agreed, that the City will
participate in the development of the Parking Project. After construction of the
Parking Project, B&H shall establish condominium units and City shall purchase
the Parking Facility (which shall be comprised of the parking facility, including a
ground level commercial space, but not the space intended for use by the Credit
Union), for approximately$6,700,000.
F. B&H proposes to act as the developer of the Parking Project and provide
necessary developer-related services including, but not limited to, contracting for
design services; conducting environmental investigations of the area in and
around the Parking Project; obtaining all necessary government approvals and
permits necessary for construction; selecting and contracting with a general
contractor to construct the Parking Project; creating condominium units; post-
construction, transferring ownership of the Parking Facility to the City; and
providing such other services as may be described in the Agreement for the
Disposition and Development of Property between the City of Eugene and B&H
(the "DDA"). The Parking Project is scheduled to be completed by the fall of
2007.
G. B&H has indicated to City that B&H wishes to select and enter into two separate
construction contracts with Lease Crutcher Lewis, LLC ("LCL") as the general
contractor for both the Whole Foods Project and the Parking Project.
H. It is the policy of the City to utilize public contracting practices and methods to
maximize the efficient use of public resources and purchasing power of public
funds. Absent particular circumstances, such rules and laws require the City to
use a competitive selection process to select a developer to provide the types of
services offered by B&H and to select and award a contract to a general
contractor.
I. The particular circumstances of the Parking Project, including the development
proposal presented by B&H involving both the Whole Foods Project and the
Parking Project (together, the "East Broadway Development Projects"), the
needed level of experience and the current schedule for completion of the Parking
Facility, do not allow for such a competitive selection process. Instead, the City
Council, after considering the attached findings, wishes to directly procure
developer-related services from B&H and to further authorize B&H to directly
select LCL as the general contractor for the Parking Proj ect, as set forth in the
DDA.
NOW, THEREFORE,
Resolution - 2
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF
EUGENE, a Municipal Corporation of the State of Oregon, as follows:
Section 1. After considering and approving the findings attached to this
resolution as Exhibit 1, the East Broadway Development Projects Disposition and
Development Agreement between the City of Eugene and Gerding/Edlen Development
Company, LLC and Broadway & High Associates, LLC (the "DDA"), which includes the
direct selection of Lease Crutcher Lewis, LLC as the general contractor for the Parking
Project, as defined herein, is specifically declared exempt from the state and city
competitive selection requirements.
Section 2. This Resolution shall become effective immediately upon its adoption.
The foregoing Resolution adopted the 15th day of March, 2006.
III ~
I; 1\ Cl'
~ity Rec rder
Resolution - 3
RESOLUTION NO. 4862
Exhibit 1: Exemption from Competitive Selection - Findings
The City wishes to execute the DDA on or before June 30, 2006. In order to proceed
with the direct procurement of B&H's developer-related services and authorize B&H to
directly select LCL as the general contractor for the Parking Project, the City must
consider and adopt certain findings and grant exemptions from the competitive selection
process. The City may grant an exemption upon finding that a direct procurement (i) is
unlikely to encourage favoritism or substantially diminish competition; (ii) is likely to
result in substantial cost savings for the City or the public; and (iii) will otherwise
substantially promote the public interest in a manner that could not practicably be
realized by complying with the competitive selection process. ORS 279B.085, ORS
279C.335, EC 2.1425, and City of Eugene Public Contract Administrative Rule R-1415,
subsection 3.1.1.
1. The exemption of the personal services contract, the DDA, is unlikely to
encourage favoritism or substantially diminish competition because of the unique
nature of the East Broadway Development Projects and the conceptual plans and
designs proposed by B&H. Even if the City were to use a competitive selection
process, it is unlikely that other proposers would be able to provide a similar plan
for development of the area because of B&H's ownership and control of the
majority of the site targeted for development, existing contracts with Whole
Foods and the Credit Union and B&H's unique plans for and familiarity with the
entire development site. Similarly, authorizing B&H to directly select LCL as the
general contractor for the Parking Project, including the Parking Facility, is
unlikely to encourage favoritism or substantially diminish competition because of
LCL's existing relationship with B&H and its existing familiarity with both
projects. If the exemption is granted, B&H and LCL shall comply with all state
and local laws relating to the development of the Parking Project as a public
improvement and a public work.
2. The exemption of the personal services contract (the DDA) which includes
authorization for B&H to directly select LCL as the general contractor for the
Parking Project, is likely to result in substantial cost savings for the City. The
City will be able to benefit from the efficiencies resulting from the familiarity of
both B&H and LCL with the project site. The City is likely to benefit from the
avoided time delays and costs associated with first a competitive selection process
and then ramp-up time. As stated above, because of the unique characteristics of
B&H, the City would not have the opportunity to participate in the development
of the Parking Project absent B&H's involvement. If the City does not allow for
an exemption from competitive selection for a general contractor, the current
pricing for the Parking Project, including the Parking Facility, will increase. The
following additional information in support of the cost-savings findings is
provided in conjunction with the requirements of ORS 279C.330:
Resolution - 4
a. Operational. budget and financial data - Because of the unique nature of
the East Broadway Development Projects, including B&H's ownership of
the majority of the Whole Foods Project property and LCL's role as
general contractor for the construction of the Whole Foods Project and the
Parking Project, the City is obtaining needed parking spaces within the
downtown area at a lower cost than it would be able to obtain the parking
spaces otherwise.
b. Value engineering - LCL has already been involved in studying the
different aspects of the Parking Project, including determining the price
and value of the Parking Facility. Granting the exemption for the direct
selection of LCL as the general contractor allows the City to benefit from
LCL's past experience in value engineering on the project and to avoid the
inefficiency, including cost increases, associated with bringing in a new
general contractor.
c. Market conditions - The construction industry is beginning to enter into
its busy season when the availability of labor will decrease and the cost of
both labor and materials will increase. The exemption for the direct
selection of LCL ensures the City will be able to use LCL as the general
contractor for the Parking Facility, allows the City to avoid the time delays
associated with the competitive selection process, and allows the City to
avoid such increased costs.
d. Technical complexity - The construction of the Parking Facility, i.e., a
multi-story, 260 space concrete parking structure that includes two
commercial spaces, is a technically complex project and requires the
contractor to understand the proj ect and handle such technical
complexities to construct the structure properly and within the required
maximum cost and scheduling parameters. LCL has such familiarity and
the requisite experience to complete the project on time and on budget, as
further detailed below.
e. Specialized expertise required - Because the construction of the Parking
Facility is a technically complex project with a set completion date, the
contractor must have sufficient specialized expertise in constructing such
structures. LCL has successfully completed projects of similar size,
complexity, type and cost and therefore has the specialized expertise
necessary to act as the general contractor on the Parking Facility.
f. Public safety - There are no public safety issues or findings associated
with the exemptions for the Parking Project.
g. Funding sources - To the extent possible, the City of Eugene Riverfront
Urban Renewal Agency (the "Agency"), through an intergovernmental
agreement between the City and the Agency, will pay for the majority of
Resolution - 5
the cost of the Parking Facility and the remaining amount will be paid for
by use of other city funds. These funds committed by the City and the
Agency to the project will be included in the Fiscal Year 2005/2006
budget.
h. Public benefits - The exemption for the direct selection of LCL as the
general contractor provides many public benefits, including, but not
limited to, cost savings, additional efficiency in constructing the Parking
Facility, ensuring the construction is done correctly and by a contractor
that has the necessary specialized expertise.
3. If granted, the exemptions will otherwise substantially promote the public interest
in a manner that could not be practicably realized by complying with the
competitive selection process. Direct procurement of personal services from
B&H and authorizing B&H to directly select LCL as the general contractor for
the Parking Project, including the Parking Facility, promotes efficiencies and cost
savings in the completion of the Parking Project. This would allow the public to
more quickly realize and enjoy the attendant revitalization of the development
area, as well as benefit from the use of the new Parking Facility within the
downtown area and the new Courthouse district.
Resolution - 6