Public Hearing: 2004 Metropolitan Wastewater Management Commission
Facilities Plan and 20-Year Project List
Meeting Date: June 14, 2004 Agenda Item Number: 3
Department: Public Works Staff Contact: Peter Ruffler
www. cl. eugette, or. us Contact Telephone Number: 682-8606
AGENDA ITEM SUMMARY
This is a public hearing on the 2004 Metropolitan Wastewater Management Commission (MWMC)
Facilities Plan and associated 20-Year Project List. These items are subsequently scheduled for council
action on June 28, 2004. The 2004 MWMC Facilities Plan, adopted by MWMC on May 6, 2004, is
intended to address improvements of the regional wastewater facilities needed to meet community
growth through 2025, state and federal requirements, and community expectations for protection of the
public's health and safety and the environment. It is being forwarded to the City of Eugene for
concurrence.
BACKGROUND
Council Action History
The Metropolitan Wastewater Management Commission (MWMC) was established by an
intergovernmental agreement (ICA) dated February 9, 1977, signed by the governing bodies of Eugene,
Springfield, and Lane County. The approved 1977 "208 Plan" for the construction of the Eugene-
Springfield regional wastewater facilities set out the original projections, requirements, and projects to
serve the wastewater treatment needs of the Eugene-Springfield community for a 20-year period.
To address the peak flow capacity issues, the commission, the City of Eugene, and the City of
Springfield adopted the Wet Weather Flow Management Plan (WWFMP) in 2001. This plan remains
the guiding policy document in setting the cities' annual Capital Improvement Plan (CIP) for sanitary
sewer rehabilitation and replacement, as well as the commission's capital improvements and operations
for addressing peak flows to the regional wastewater facilities.
The City Council ratified the MWMC FY04 Budget and CIP on May 12, 2003.
The City Council had a work session on the 2004 MWMC Facilities Plan on May 19, 2004.
At the May 24, 2004, City Council meeting, questions were raised concerning efforts toward public
outreach and involvement activities. Attachments to the Agenda Item Summary on the Ratification of
the Metropolitan Wastewater Management Commission (MWMC) FY04-05 Regional Wastewater
Program Budget and Capital Improvement Program (CIP) which is being distributed for tonight's City
L:\CMO\2004 Council Agendas\M040614\S0406143.doc
Council meeting provide the following regarding the 2004 MWMC Facilities Plan: 1) a chart of the
history of the plan with outreach and involvement activities; 2) a summary table of the regional
wastewater program's relevant public awareness, education, and involvement efforts; and 3) a
comprehensive memorandum with detailed explanations and representative samples of the history of the
plan with outreach and involvement activities.
The 2004 MWMC Facilities Plan and 20-Year Project List was adopted by the City of Springfield on
May 17, 2004, after a public hearing. Lane County Commissioners had a work session on the 2004
MWMC Facilities Plan and 20-Year Project List on May 19, 2004; a public hearing will be on June 9
and action scheduled for June 16, 2004.
Policy Issues
The primary policy question before the council is: Does the council agree with the MWMC that the
2004 MWMC Facilities Plan and 20-Year Project List provide for the wastewater treatment needs of the
community in a cost-effective and responsible manner? A related issue is the financial implications of
the proposed 2004 MWMC Facilities Plan and associated 20-Year Project List. Funding of the
improvements identified in the plan will come from user rates and systems development charges
(SDCs). Approximately two-thirds of the system's users are located in Eugene. Adoption of the 20-
Year Project List is required to establish a basis for the proposed SDC rates needed to fund growth's
equitable share of capital improvements.
Wastewater collection and treatment infrastructure are critical components in the support of community
and environmental health and well-being. Periodic updates to wastewater facilities are necessary to
ensure that the infrastructure remains adequate to handle the projected demands for wastewater
collection and treatment without an interruption or deficiency in service that can lead to public health
risks, damage to the environment, or economic restrictions due to sewer connection moratoriums.
Previous plans, established policies, strategies, significant modeling, evaluation, and citizen involvement
provide the foundation for the 2004 MWMC Facilities Plan and 20-Year Project List. The plan provides
the most cost-effective set of capital improvements to meet capacity and performance needs while
utilizing existing plant assets and building new plant expansions only where necessary. Existing
commission policies and guidance, the wastewater discharge permit requirements, and state/federal
regulations have provided the context for the 2004 MWMC Facilities Plan. No new policies were
developed in connection with the proposed plan.
The 2004 MWMC Facilities Plan is based on the least costly system-wide set of improvements needed,
addressing both the peak flow and treatment requirements. Failure to implement the 2004 MWMC
Facilities Plan in a timely manner would increase the probability of regulatory violations, pose risk to
public and environmental health, result in shorter planning and construction timeframes for reacting to
system shortfalls, and increase overall costs to sewer users and the community from less efficient
planning and financial management processes. It might also result in restrictions to the community's
ability to add new users to the system.
Council Goals
The 2004 MWMC Facilities Plan and 20-Year Project List is related to the council goals of:
L:\CMO\2004 Council Agendas\M040614\S0406143.doc
· SUSTAINABLE COMMUNITY DEVELOPMENT
A community that retains a high quality of life and a healthy economy, effectively links land use and
planning, and successfully manages growth and change in the urban environment.
· HEALTHY NATURAL AND BUILT ENVIRONMENT
A community that conserves and enhances the natural environment and provides an attractive and
healthy place to live
Financial and/or Resource Considerations
MWMC acquired $85,000,000 in federal grant funds to support the construction of regional wastewater
facilities that began in the early 1980s. The majority of the facilities were brought on-line in 1984 at a
total cost of $105,000,000. General obligation bonds were issued by the Lane County Metropolitan
Wastewater Service District (CSD) for $29,000,000 and were repaid through property taxes. The bonds
were retired in 2002. Implementation of the 2004 MWMC Facilities Plan will require a financial
investment which is most significant over the first five years of the 20-year planning period. In 2004
dollars, the 20-year total cost is projected to be $144,000,000. No grant funding is anticipated in the
projected capital financing. About $90,000,000 of this need will be realized in the first five years of the
CIP to reasonably ensure compliance with peak flow management requirements by the year 2010, as
established by the Department of Environmental Quality (DEQ). Revenues to support the anticipated
capital project needs will be derived from user rates and systems development charges. In order to
mitigate potentially significant short-term impacts to user rates, a significant amount of debt financing
will be necessary. The MWMC Financial Plan, adopted in 2003, anticipates this need and provides
financial policies and tools which will serve the commission in managing the revenue requirements over
the coming years to minimize overall costs and user rate increases. (User rates have not yet been
finalized, but the anticipated total increase for a typical residence over the first five years would range
from approximately $5.60 to $6.50 per month.) SDC rates will increase by approximately 79% to
support growth's equitable share of necessary capital improvements.
Other Background Information
The Facilities Plan is the culmination of a year-long effort involving significant public review. Facility
planning analyses conducted by CH2M HILL began in March, 2003, with the oversight of a 12-member
Eugene-Springfield staff steering committee. The commission reviewed the draft 2004 MWMC
Facilities Plan in a special, publicly advertised evening workshop on November 24, 2003, and gave
consensus instruction to finalize the 20-Year Project List to include the recommended preferred
solutions and new disinfection system. On January 8, 2004, the commission, after another review of the
draft 2004 MWMC Facilities Plan and associated costs, gave direction to proceed with the finalization
of the 20-Year Project List. A third public open house was advertised and held the evening of March 3,
2004. The commission held a public hearing on adoption of the 2004 MWMC Facilities Plan and 20-
Year Project List on April 22, 2004, and carried over the hearing to May 6, 2004, to allow time for
additional public review and testimony.
Except for the original 1977 "208 Plan," MWMC has not until this time updated the formal Facility Plan
to be approved by the DEQ. An approved Facilities Plan will incorporate the existing adopted plans (the
WWFMP and the Biosolids Management Plan), contain updated technical analyses and projections of
flows and loads, provide reasonable assurance of compliance with state and federal regulations and new
L:\CMO\2004 Council Agendas\M040614\S0406143.doc
limitations and requirements in the NPDES permit (see next paragraph), and revise the capital
improvement projects to meet the needs for adequate operational facilities. Having a formally approved
Facilities Plans will also make MWMC eligible for public loans and grants.
As stated, the 2004 MWMC Facilities Plan will help to ensure continued compliance with regulatory
requirements that govern the quality of effluent discharged from the treatment works as well as
conditions for the collection and transmission ofwastewater to the treatment plant. These regulations
present legal requirements for the provision ofwastewater services to the community and form the
foundation for the design criteria used in formulating the 2004 MWMC Facilities Plan and associated
20-Year Project List. The DEQ reissued MWMC's National Pollutant Discharge Elimination System
(NPDES) permit in May 2002, which prompted the commission to pursue a thorough, updated Facilities
Plan to include the new ammonia and thermal load limits of the renewed permit, as well as the new
requirements to implement a Temperature Management Plan (TMP) and the WWFMP. Furthermore, a
comprehensive analysis of the treatment plant's processes and hydraulic capacities has led the
commission to include an evaluation and recommendation of alternative disinfection systems to mitigate
worker safety and community risk concerns in the 2004 MWMC Facilities Plan.
The treatment plant also currently faces a significant peak flow capacity deficit, which was projected in
the earlier WWFMP and has been validated and updated to the year 2025 based on an updated modeling
using more recent 2003-04 data. The present facility effort is prompted by the original
intergovernmental agreement which specified that when the sewage loading into the treatment plant
reached 85% of the initial design capacity, the commission would institute a program to expand and/or
upgrade the treatment system beyond the initial design capacity. This trigger point is now being reached
for several of the unit process capacities.
In the mid-1990s, the regional wastewater treatment facilities were modified to improve their
performance, and the commission recognized that the facilities were experiencing capacity limitations
relative to original design specifications. As a result, additional expansions would be needed to
actualize the projected 2004 design life. In 1996, the commission responded with a directive to produce
a master plan to evaluate short-term and long-range improvements necessary to improve facility
operations and meet increasing capacity and evolving performance demands. The MWMC Master Plan
was completed in 1997. Although it is not as comprehensive as the 2004 MWMC Facilities Plan, it did
provide analysis of historic flows, pollutant loads, and reporting data to identify capital improvements
needed to resolve shortfalls in the capacity for biosolids processing and peak flow management.
Later in 1997, the commission adopted the Biosolids Management Plan, which was derived from a
Citizen Advisory Committee (CAC) and engineering evaluation processes. This plan reflects the
commission' s adoption of strategy to resolve shortfalls in biosolids processing capacity and is based
upon an evaluation of available technologies, cost effectiveness, reliability, and public acceptance. The
biosolids dewatering facility (completed in 2001), the ongoing maintenance of drying beds, the
composting operation, the cooperative land application on private farms, and the development of the
Biocycle Farm are the beneficial results of the commission's adopted biosolids management strategy.
To address the peak flow capacity issues, the commission, the City of Eugene, and the City of
Springfield adopted the WWFMP in 2001. The objectives of this plan were to eliminate overflows and
basement flooding and provide the most cost-effective means to mitigate flows in excess of system
capacity. The plan developed a sophisticated hydraulic model that was calibrated and refined with
actual system performance over several years of the study. The Wet Weather CAC reviewed a wide mix
L:\CMO\2004 Council Agendas\M040614\S0406143.doc
of solutions and recommended the policies and capital improvements included in the WWFMP, and the
plan remains the guiding policy document in setting the cities' annual CIP for sanitary sewer
rehabilitation and replacement, as well as the commission's capital improvements and operations for
addressing peak flows.
Timing
Planning projections indicate that important capacity limitations and needs for upgraded treatment
capabilities will be realized in the relative short-term future. In addition, optimization of the various
capital projects to meet multiple objectives and maximize the capabilities of existing infrastructure
requires an integrated and synchronized process for design and construction. This process needs
appropriate lead-time in order to ensure that the necessary projects can be designed, built, and brought
on-line in time to meet regulatory deadlines and increased demands on the wastewater system. The
significant financial needs presented by the magnitude of the Facilities Plan Project List also require
careful planning for adequate cash-flow and implementation of revenue generation processes.
While the commission is assigned the responsibility of planning for plan upgrade/expansion, and for
constructing, operating, and maintaining them, the MWMC 2004 Facilities Plan and 20-Year Project
List is being forward to the governing bodies for consideration, as it will in result expanded capacity and
provide for community growth through 2025. Therefore, the commission is formally requesting that the
governing bodies acknowledge their concurrence with the 2004 MWMC Facilities Plan. The City of
Eugene has a public hearing on June 14 and council action on June 28. The 2004 MWMC Facilities
Plan will subsequently be submitted to the DEQ for formal review and approval. If the DEQ requires
changes, the 2004 MWMC Facilities Plan will be re-routed for additional consideration as needed.
Timing is also affected by the adoption of The MWMC FY 04-05 Budget and CIP which must go
through the established approval process with MWMC and the governing bodies. The budget and CIP
was adopted by the commission on May 6, 2004, and is now scheduled for ratification at the Eugene
City Council meeting on June 14, 2004.
Finally, timing is also affected by the establishment of new regional wastewater user rates and systems
development charges (SDC), which need to be adopted for FY 04-05 to provide adequate revenues for
MWMC operations, administration, and capital programs. The City of Eugene has a scheduled public
hearing on June 14 and council action on June 28 on the SDCs.
OPTIONS
1. Approve the motion to move forward with the process for concurrence with the 2004 MWMC
Facilities Plan and 20-Year Project List as scheduled, with council action on June 28, 2004.
2. Provide the Metropolitan Wastewater Management Commission with specific guidance for revising
the 2004 MWMC Facilities Plan and 20-Year Project List.
STAFF RECOMMENDATION
It is recommended that the City of Eugene concur with the 2004 MWMC Facilities Plan and 20-Year
Project List as adopted by MWMC on May 6, 2004.
L:\CMO\2004 Council Agendas\M040614\S0406143.doc
Regional Wastewater Program staff has had significant ongoing involvement in the development of the
Facilities Plan and project list, and continual guidance from the commission, as well as input from
public hearings, during this year-long planning process. The "preferred" Alternative 5 approved by the
commission in the 2004 MWMC Facilities Plan has been identified as the most cost-effective plan as it
has the lowest capital costs to achieve permit compliance and maximizes the use and effectiveness of the
existing facilities.
SUGGESTED MOTION
None; this is a public hearing only.
ATTACHMENTS
Please refer to the following material distributed for the work session on May 19, 2004: · 2004 MWMC Facilities Plan with 20-Year Project
· Frequently Asked Questions About the 2004 MWMC Facilities Plan and System Development
Charge Methodology
· Response to April 2, 2004, Questions from Eugene Chamber of Commerce - 2004 MWMC
Facilities Plan and System Development Charge Update
FOR MORE INFORMATION
Staff Contact: Peter Ruffler
Telephone: 682-8606
Staff E-Mail: peter.j.ruffler~ci.eugene.or.us