ADMINISTRATIVE ORDER NO. 58-25-31
of the
City Engineer
of the City of Eugene
CONCERNING ON-STREET PARKING ON KINSROW AVENUE
BETWEEN MARTIN LUTHER KING JR. BOULEVARD AND COMMONS
DRIVE
The City Engineer of the City of Eugene finds that:
A. Under the provisions of Chapter IV, Section 16 of the Eugene Charter of 2002, the
City Manager is designated as the administrative head of the City and is specifically authorized to
enforce all ordinances of the City. In addition, EC 5.040 authorizes the City Manager or the
Manager’s designee to “establish, maintain, remove, or alter . . . parking areas and time limitations,
including the form of permissible parking” and to “impose conditions upon which the streets and
other public property may be used for parking.” EC 5.055 sets forth the criteria the City Manager
or the City Manager’s designee should consider when taking administrative action authorized by
EC 5.040.
B. On August 5, 2020, the City Manager issued Administrative Order No. 58-20-17
granting the Executive Director of the Public Works Department the authority to exercise all of
the duties and responsibilities specifically defined as those of the City Manager in Sections 5.040,
5.045 and 5.050 of the Eugene Code, 1971. That Order also granted the Executive Director of the
Public Works Department the authority to further delegate those duties and responsibilities to such
person or persons qualified to perform the delegated duties.
C. On August 6, 2020, the Executive Director of the Public Works Department issued
Administrative Order No. 58-20-18 granting the City Engineer the authority to perform the duties
and responsibilities specifically defined as those of the City Manager in Sections 5.040, 5.045 and
5.050 of the Eugene Code, 1971. That Order also granted the City Engineer the authority to further
delegate those duties and responsibilities to such person or persons qualified to perform the
delegated duties.
D. For the safety and welfare of the public, it is necessary to remove motor vehicle
parking on the south side of Kinsrow Avenue between Martin Luther King Jr. Boulevard and
Commons Drive beginning approximately 320 feet east of the intersection between Kinsrow
Avenue and Martin Luther King Jr. Boulevard and extending approximately 24 feet farther east
for the purpose of expanding an existing community bike share hub on the street. See Exhibit A.
E. In making the decision, I have considered all of the applicable criteria set forth in
EC 5.055. The following findings support my decision to remove motor vehicle parking:
(a) Traffic engineering principles and traffic investigations.
i. The portion of Kinsrow Avenue between Martin Luther King Jr. Boulevard and Commons
Drive shown in Exhibit A is classified as a neighborhood collector street with a speed limit
Administrative Order -- Page 2 of 5
of 25 miles per hour. The street segment is approximately 34 feet wide with parking on
both sides of the street in most places, allowing approximately 20 feet of roadway for two-
way travel in a residential area. Sidewalks are present on both sides of the street. There are
no bike lanes. There is an existing bike share hub located approximately 344 feet east of
the intersection between Kinsrow Avenue and Martin Luther King Jr. Boulevard, extending
approximately 17 feet farther east. There are also two on-street bike racks for bike parking
located approximately 652 feet west of the intersection between Kinsrow Avenue and
Commons Drive, extending approximately 22 feet farther west.
ii. There were 15 motor vehicle crashes reported between 2019 and 2023 on the portion of
Kinsrow Avenue between Martin Luther King Jr. Boulevard and Commons Drive (three
with minor injuries, two with suspected injuries, and 10 with property damage only).
(b) Standards, limitations, and rules promulgated by the Oregon Transportation Commission
or the Oregon Public Utility Commission or their successors.
There are no such standards, limitations or rules that apply.
(c) Other recognized traffic control standards.
There are no recognized traffic control standards that apply.
(d) The city’s adopted transportation-related plans and policies.
The City’s 2035 Transportation System Plan (TSP) does not include any policies that
specifically relate to the provision or removal of on-street parking. Roadway and Parking
Policy No. 1 a “Complete Streets Policy,” is to “Design, construct, maintain, and operate
all streets to provide comprehensive and integrated transportation networks that serve
people of all ages and abilities, promote commerce, and support the comprehensive land
use plan’s vision for growth and development in a responsible and efficient manner. A
“complete street” allows safe travel for automobiles and emergency responders, bicycles,
walking, transit, and freight. In addition to fulfilling a street’s basic transportation functions
and providing access to properties, streets and sidewalks should be designed to be
attractive, safe, accessible, sustainable, and healthy components of the City's
environment.” The TSP reiterated the City Council goal in the Climate Recovery
Ordinance (CRO) #20567 of achieving a 50 percent citywide reduction of fossil fuel use
by 2030. Accordingly, the TSP included Goal 5 to triple the number of trips made by
walking, bicycling and using transit by 2035. To encourage increased travel by bicycle, the
TSP provides a list of projects and programs to improve safety, convenience, and direct
connections for people traveling by bike. Bicycling promotes the health of individuals, has
a low impact on the environment, and allows people to move independently throughout the
community without motorized vehicles, including many who cannot or choose not to drive.
Supporting a Eugene bike share system is one of the Plan’s four Bicycle Policies. The
placement of bike share stations in convenient location with demonstrated use further
supports this program.
(e) Existing state and local laws regulating use of public ways.
Administrative Order -- Page 3 of 5
The use of the City’s public ways for parking is regulated at the local level. EC
5.040(1)(h)(5) and EC 5.040(1)(p) establish authority to manage parking.
(f) The efficient use of the public way by the public.
Removal of approximately 24 feet of motor vehicle parking allowances on Kinsrow
Avenue is needed for more efficient use of the roadway to expand an existing community
bike share hub.
(g) The use of abutting property.
The abutting land use is residential, consisting of multi-family housing developments.
(h) The intensity of use of the street by vehicles and pedestrians.
i. By Ordinance No. 20181, the City Council adopted the Street Classification Map that
designated Kinsrow Avenue as a neighborhood collector street. By Resolution 4608, the
City Council adopted the Design Standards and Guidelines for Eugene Streets, Sidewalks,
Bikeways and Access Ways. Parking is an optional feature on streets.
ii. There are sidewalks on both sides of the street segment. This order will not impact accessibility of the sidewalk by pedestrians.
(i) The physical condition and characteristics of the street and abutting property.
i. The portion of Kinsrow Avenue between Martin Luther King Jr. Boulevard and Commons
Drive shown in Exhibit A is classified as a neighborhood collector street with a speed limit
of 25 miles per hour. The street segment is approximately 34 feet wide with parking on
both sides of the street in most places, allowing approximately 20 feet of roadway for two-
way travel in a residential area. Sidewalks are present on both sides of the street. There are
no bike lanes. There is an existing bike share hub located approximately 344 feet east of
the intersection between Kinsrow Avenue and Martin Luther King Jr. Boulevard, extending
approximately 17 feet farther east. There are also two on-street bike racks for bike parking
located approximately 652 feet west of the intersection between Kinsrow Avenue and
Commons Drive, extending approximately 22 feet farther west.
ii. The abutting properties on the northern side of the street segment are all multi-family
housing developments of two- and three-stories, each with asphalt surface parking lots.
The properties abutting the south side of the street segment are all multi-family housing
developments with two- and five-story buildings, each with asphalt surface parking lots.
(j) Emergencies.
i. Emergency service vehicles are accommodated through bi-directional travel on Kinsrow
Avenue.
ii. Kinsrow Avenue is not designated as an emergency ice or snow removal route.
(k) The public health, safety and welfare.
Expansion of the community bike share hub supports public health.
Administrative Order -- Page 4 of 5
(l) Special events of community interest including parades and public gatherings.
There are no special events of community interest that occur on the portion of Kinsrow
Avenue between Martin Luther King Jr. Boulevard and Commons Drive shown in Exhibit
A.
(m) Construction within or adjacent to the street.
No construction is currently taking place on the portion of Kinsrow Avenue between
Martin Luther King Jr. Boulevard and Commons Drive as shown in Exhibit A. The order
will not impede access for future construction.
(n) When establishing conditions upon the use of parking in the public way and city-
owned parking facilities:
(1) Applicable and appropriate time limits;
There are no existing time limits on motor vehicle parking. This Order does not
establish time limits.
(2) The vehicle type and purpose;
This Order does not establish conditions on vehicle type and purpose.
(3) The relative, seasonal and special event demands for parking spaces within the areas
of the requested parking;
This Order is not a response to a request for new / additional parking spaces.
(4) The other public uses for the property;
The area is zoned Special Area, High-Density Residential, and Agricultural; the public
parking areas are intended to serve those uses. The addition of a community bike share
hub adds travel options for both residents and customers of the nearby commercial
properties.
(5) The location and physical characteristics of the parking area or facility;
Existing parking includes six asphalt surface lots belonging to adjacent multi-family
housing developments and another belonging to the property zoned Agricultural as well
as on-street parking on both sides of the street.
(6) The demand for operating revenues, the costs of operations and enforcement;
i. Removal of this approximately 24-foot section of motor vehicle parking is not expected
to significantly impact operating revenues.
(7) The use of parking regulations to promote city adopted goals and policies;
Removal of motor vehicle parking is consistent with City-adopted goals and policies,
including Bicycle Policy 4 of the 2035 Transportation System Plan to “Support a
Eugene bike share system.”
Administrative Order -- Page 5 of 5
(8) Abuse by applicants of any parking-related permits;
Not applicable.
(9) The impact on nearby commercial uses;
Removal of motor vehicle parking to install a community bike share hub supports
resident access to bike share vehicles that enable quick trips to nearby commercial
properties.
(10) The ease of enforcing the provisions of this chapter; and
i. No need for enforcement is expected.
(11) The availability of other parking spaces.
i. Motor vehicle parking is available on adjacent private property.
ii. Motor vehicle parking will remain available on the street.
On the basis of these findings, I order that on-street parking shall be removed from the north
side of Kinsrow Avenue between Martin Luther King Jr. Boulevard and Commons Drive
beginning approximately 320 feet east of the intersection between Kinsrow Avenue and Martin
Luther King Jr Boulevard and extending 24 feet farther east.
Dated and effective this 16th day of October, 2025.
Jenifer Willer (Oct 16, 2025 09:56:42 PDT)
Jenifer M. Willer, PE
City Engineer
City of Eugene Public Works
Kinsrow Avenue between Martin Luther King Jr. Boulevard and Commons Drive
Hub expansion to be installed 320’ east of the intersection of Kinsrow Ave and MLK Jr. Blvd.
24’ Bike Share Hub expansion
7’ hub depth 5’ to curb cut
17’ Existing Bike Share Hub on Yellow Curb to remain
EXHIBIT A