HomeMy WebLinkAboutAdmin Order 58-26-04-F -- Urban Forestry Fee AmendmentsAdministrative Order – Page 1 of 2
ADMINISTRATIVE ORDER NO. 58-26-04-F
of the
City Manager of the City of Eugene
ADOPTING THE URBAN FORESTRY FEE SCHEDULE FOR TREE
REMOVAL / FELLING AND THE STREET TREE PLANTING
PROGRAM AND SUPERSEDING THE FEE SCHEDULE ADOPTED BY
ADMINISTRATIVE ORDER NO. 58-18-12-F.
The City Manager of the City of Eugene finds as follows:
A. Sections 2.020, 6.310 and 7.280 of the Eugene Code, 1971 (EC) authorize the City
Manager to determine and set fees and charges to be imposed by the City for tree felling permit
applications and street tree planting costs.
B. Pursuant to the above authority, on September 4, 2018, Administrative Order No.
58-18-12-F was issued making the most recent changes to the tree removal and street tree planting
fees and adopting an updated Tree Removal and Street Tree Planting Fee Schedule (“the Fee
Schedule”).
C. On March 31, 2026, Administrative Order No. 58-26-04 was issued, ordering that
notice be given of the opportunity to submit written comments on my proposal to set new tree
removal and street tree planting fees and to rename the Fee Schedule. The Notice specified that
comments on the proposed amendments would be accepted for 15 days from April 6, 2026, the
date the Notice was published and posted. The written comments received during the public
comment period are addressed in the City Manager's Findings attached as Exhibit B to this Order.
D. Based on my investigation pursuant to the provisions of Sections 2.020, 6.310 and
7.280 of the Eugene Code, 1971, and after considering the comments that were submitted, I find
that the fees should be set as proposed. (See Exhibit B to this Order)
E. The unamended tree removal and street tree planting fees adopted by
Administrative Order No. 58-18-12-F are incorporated into the Fee Schedule attached as Exhibit
A to this Order.
On the basis of these findings, I order that:
1. The Urban Forestry Fee Schedule for Tree Removal / Felling and the Street Tree
Planting Program attached as Exhibit A to this Order is the schedule of fees to be charged for the
described services effective May 15, 2026.
2. The Fee Schedule attached to Administrative Order No . 58-18-12-F is superseded
by the Urban Forestry Fee Schedule for Tree Removal / Felling and the Street Tree Planting
Program attached as Exhibit A to this Order, effective May 15 , 2026.
Dated this 04 day of May, 2026.
Administrative Order -Page 2 of 2
J?!:,~~~mat~UJa~f!qg eon
Jennifer D. Haruyama
City Manager
Exhibit A
to Administrative Order No. 58-26-04-F
Page 1 of 2
Urban Forestry Fee Schedule for Tree Removal / Felling and the Street Tree Planting Program
(Effective May 15, 2026)
Fee Category Year 1
May 15, 2026
Year 2
Jul. 1, 2027
Year 3
Jul. 1, 2028
Year 4
Jul. 1, 2029
Year 5
Jul. 1, 2030
A. TREE REMOVAL / FELLING
Permit Application Fee
1–10 trees to be felled,
no public notice or
comment period
required
$137.00 $141.11 $145.34 $149.70 $154.19
1–10 trees to be felled,
public notice and
comment period
required
$275.00 $283.25 $291.75 $300.50 $309.51
11–50 trees to be
felled
$550.00 $566.50 $583.50 $601.00 $619.03
51–100 trees to be
felled
$893.00 $919.79 $947.38 $975.80 $1,005.07
101 or more trees to
be felled (base fee)
$893.00 $919.79 $947.38 $975.80 $1,005.07
101 or more trees to
be felled
(per tree over 100)
$1.72 $1.77 $1.82 $1.87 $1.93
Appeal Fee $859.00 $884.77 $911.31 $938.65 $966.81
Modification to Approved Permit: Same as the initial permit application fee.
Enforcement -- Enhanced Permit Fees (after-the-fact permit for tree(s) felled without a permit)
First Enhanced Permit issued to Responsible Person: Double the applicable permit fee.
Subsequent Enhanced Permits issued to Responsible Person: Ten times the applicable permit fee.
Enforcement -- Replacement Fee (for street tree or other public tree felled without a permit): The value of tree(s)
felled as calculated using the appraisal method established by the Council of Tree & Landscape Appraisers (CTLA),
with a minimum value of the cost to plant and establish a 2-inch caliper tree for three years plus the actual cost for the
City to obtain that appraisal.
Felling of City-Identified Hazard Tree(s): There is no fee required to accompany a permit to fell trees identified by the
City as requiring removal due to poor health or hazard.
B. STREET TREE PLANTING PROGRAM
Per Eugene Code Section 7.280, developers creating new public street shall submit and obtain City approval of a street
tree plan including selection of either the Developer Planting Option or the City Planting Option.
Application Processing and Review
Initial Application for
Approval of Street
Tree Plan
$515.00 +
$0.02/ft*
$530.45 +
$0.02/ft*
$546.36 +
$0.02/ft*
$562.75 +
$0.02/ft*
$579.63 +
$0.02/ft*
Application to Modify
Approved Street Tree
Plan
Same as initial
fee
Same as initial
fee
Same as initial
fee
Same as initial
fee
Same as initial
fee
Exhibit A
to Administrative Order No. 58-26-04-F
Page 2 of 2
Fee Category Year 1
May 15, 2026
Year 2
Jul. 1, 2027
Year 3
Jul. 1, 2028
Year 4
Jul. 1, 2029
Year 5
Jul. 1, 2030
Developer Planting Option
Development of street
tree plan agreement,
review, administration
and monitoring
$344.00 $354.32 $364.95 $375.90 $387.18
Annual maintenance
inspection (per year x
3 years)
$0.43/ft* $0.44/ft* $0.45/ft* $0.46/ft* $0.47/ft*
Final establishment
inspection
$0.43/ft* $0.44/ft* $0.45/ft* $0.46/ft* $0.47/ft*
Tree establishment
bond
(security bond or cash
deposit)
$12.23/ft* $12.60/ft* $12.98/ft* $13.37/ft* $13.77/ft*
City Planting Option
Agreement processing
fee
$172.00 $177.16 $182.47 $187.94 $193.58
Tree establishment fee
(one-time)
$12.23/ft* $12.60/ft* $12.98/ft* $13.37/ft* $13.77/ft*
*Footage = total footage of the development site abutting public street right-of-way, including exterior and interior
subdivision streets except footage exempted by the City pursuant to R-7.280-D 1. or E 6.11.
Exhibit B
to Administrative Order 58-26-04-F
Findings - Page 1 of 6
City Manager’s Findings
Urban Forestry Fee Schedule for Tree Removal / Felling and the Street Tree Planting Program
Pursuant to Section 2.020(2) of the Eugene Code, 1971, the City Manager has considered the following factors in
determining the proposed amendments to the (currently titled) “Tree Removal and Street Tree Planting Program Fee
Schedule.” The proposal to rename of the document is intended to more accurately describe the fees it establishes,
since tree “removal” is only one of the ways a tree may be “felled” under the definition of “fell” at EC 6.030. This
Findings document addresses fee adjustments for both the Tree Removal/Felling Permit Program (Section A of the
Fee Schedule) and the Developer Street Tree Planting Program (Section B of the Fee Schedule).
PART I: TREE REMOVAL PERMIT PROGRAM FINDINGS
The following findings address the proposed fee adjustments for the Tree Removal Permit Program pursuant to
Eugene Code Section 6.310.
(a) Applicable policies, enactments and directives of the Council.
Findings:
The Eugene City Council has established urban forestry policies through Eugene Code Section 6.310, which
establishes the tree felling permit program to regulate tree removal on private property. This regulatory framework
reflects Council’s recognition that urban trees provide significant public benefits including air quality improvement,
stormwater management, urban heat island mitigation, wildlife habitat, and community aesthetics.
Eugene Code Section 2.020 authorizes the City Manager to set fees for city services, including permit application
fees. The proposed fee adjustment ensures that the administrative costs of the tree removal permit program are borne
by applicants seeking permits rather than subsidized by the general fund, consistent with Council’s directive for cost
recovery where appropriate.
The permit program serves dual purposes: (1) ensuring appropriate oversight of tree removal activities that affect the
urban forest canopy, and (2) deterring unpermitted tree removal through the enhanced permit fee structure. The
escalating fee structure for subsequent permits by the same responsible person reflects Council’s intent to strongly
discourage repeat violations.
(b) The amount charged by the City in the past.
Findings:
The current tree removal permit fees were established by Administrative Order No. 58-04-03-F, effective March 18,
2004. These fees have remained unchanged for over 21 years despite significant cumulative inflation.
Fee History — Tree Removal Permits:
Fee Category March 2004 Year 1 May 15, 2026 Years 2–5 (see Exhibit A)
1–10 trees (no public notice) $80.00 $137.00 $141.11 → $154.19
1–10 trees (public notice required) $160.00 $275.00 $283.25 → $309.51
11–50 trees $320.00 $550.00 $566.50 → $619.03
51–100 trees $520.00 $893.00 $919.79 → $1,005.07
101+ trees $520.00 + $1.00/tree $893.00 + $1.72/tree $919.79 + $1.77/tree →
$1,005.07 + $1.93/tree
Appeal fee (R-6.305-J) $500.00 $859.00 $884.77 → $966.81
Fee History Timeline:
March 18, 2004 — Administrative Order No. 58-04-03-F established the current tree removal permit fee schedule.
The tiered structure based on number of trees was designed to scale administrative burden with project complexity.
Exhibit B
to Administrative Order 58-26-04-F
Findings - Page 2 of 6
September 4, 2018 — Administrative Order No. 58-18-12-F updated certain program rules. Tree removal permit
fees remained unchanged.
March 31, 2026 (Year 1 Proposed) — Fee adjustment of 71.76% based on CPI-U inflation from May 2004 through
September 2025, bringing fees to current-dollar equivalents. Subsequent annual increases of 3% are established for
Years 2 through 5 (July 1, 2027 through July 1, 2030) as shown in Exhibit A.
The 21-year gap without fee adjustment means that the current fees represent only 58% of their inflation-adjusted
value, resulting in an effective subsidy of permit processing costs by the general fund.
(c) The full costs of providing the service supported by the fee.
Findings:
Tree removal permit processing involves multiple cost components within the Urban Forestry Program:
Permit Processing Activities:
Receipt and logging of permit applications; review of tree inventory database and field verification (as needed);
evaluation of tree condition, context, and applicable code requirements; applicant consultation regarding
preservation options and design alternatives; appraisal coordination for development-related permits (when
applicable); permit issuance and documentation; and compliance monitoring and enforcement.
Staff Time and Administrative Costs:
Permit processing requires trained Urban Forestry staff with arboricultural expertise. Simple permits (1–10 trees, no
public notice) typically require 1–2 hours of staff time. Complex permits involving public notice, multiple trees, or
development contexts require substantially more staff involvement, including field visits, design consultation, and
coordination with other City departments.
The current fee of $80.00 for the simplest permit category does not cover the fully-loaded cost of staff time at
current wage rates. The proposed Year 1 fee of $137.00 represents an inflation-adjusted amount that moves closer
to, but does not exceed, actual processing costs. The five-year schedule provides for continued, incremental cost
recovery through Year 5.
Enhanced Permit Fee Structure:
The fee schedule includes an enhanced permit fee (double the standard fee) for the first permit issued subsequent to
unpermitted tree felling, and an escalating fee (ten times the standard fee) for each permit thereafter by the same
responsible person. These enhanced fees are not designed for cost recovery but rather as deterrent measures
consistent with Council policy to protect the urban forest from unauthorized removal. The proposed adjustments
maintain the same multiplier relationships (2× and 10×) while applying the fee adjustments to the base fees.
(d) The amounts charged by other comparable providers.
Findings:
Tree removal permit programs vary significantly among Oregon municipalities in scope, complexity, and fee
structure. The following comparison provides regional context:
Oregon Municipal Tree Removal Permit Fees (2024–2025):
Jurisdiction Simple Permit Fee Notes
Portland, OR $0 (as of July 2025) Fees eliminated through PCEF funding; permits still
required
Springfield, OR ~$1,563+ (corrective) Corrective tree felling permit; varies by circumstance
Lake Oswego, OR $122 (3 or fewer trees) Tiered: $171 (4–10), $354 (11–25), $379+ (26+)
West Linn, OR Type A: $24 Tiered based on permit complexity
Fee structures across Oregon reflect different policy approaches. Eugene’s proposed fees fall within the mid-range
of comparable Oregon municipalities when adjusted for program scope and regulatory requirements. Portland’s
recent elimination of most tree permit fees was made possible through dedicated funding from the Portland Clean
Energy Community Benefits Fund. Eugene does not have access to comparable dedicated funding, necessitating fee-
based cost recovery for permit administration.
Exhibit B
to Administrative Order 58-26-04-F
Findings - Page 3 of 6
(e) The revenue needs of the City as determined by the adopted city budget.
Findings:
The Tree Removal Permit Program operates within the Urban Forestry Program budget under Parks and Open
Space. Unlike development-driven fees that generate predictable revenue streams, tree removal permit revenue is
variable and depends on property owner decisions to remove trees.
Revenue Considerations:
The primary purpose of tree removal permit fees is not revenue generation but rather: (1) cost recovery for permit
processing activities; (2) deterrence of unnecessary tree removal; (3) encouraging compliance with permit
requirements; and (4) supporting the administrative infrastructure necessary for urban forest management.
The proposed 71.76% Year 1 fee adjustment based on CPI-U brings tree removal permit fees to current-dollar
equivalents. Subsequent annual increases of 3% in Years 2 through 5 provide for continued cost recovery and
program sustainability. This five-year schedule ensures permit processing costs are not subsidized by general fund
revenues and maintains the deterrent effect of enhanced permit fees in current dollars.
PART II: STREET TREE PLANTING PROGRAM FINDINGS
The following findings address the proposed fee adjustments for the Street Tree Planting Program, which provides
for street tree establishment in new development areas pursuant to Eugene Code Section 7.280.
(a) Applicable policies, enactments and directives of the Council.
Findings:
The Eugene City Council has established policies supporting urban forestry through Eugene Code Section 7.280,
which authorizes the Developer Street Tree Program to ensure street tree planting in new development areas. The
program supports the City’s broader goals for environmental sustainability, community livability, and climate
resilience. The Council has also adopted Eugene Code Section 6.310 regarding tree removal permits and Section
2.020 authorizing the City Manager to set fees for city services. For the city-plant option, EC 7.280 requires the City
Manager to establish fees that are “equal to the cost of the purchase, installation and establishment of the street trees
required by the approved street tree plan.” For the developer-plant option, EC 7.280, fees must “reimburse the city
for its costs in connection with plan review, inspection, administration and monitoring”
The proposed fee adjustment aligns with Council’s directive that city programs operate on a cost-recovery basis
where appropriate, ensuring that development-related costs are borne by development rather than subsidized by the
general fund.
(b) The amount charged by the City in the past.
Findings:
The current street tree establishment fee of $7.12 per linear foot was established by Administrative Order No. 58-04-
03-F, effective March 18, 2004. This fee has remained unchanged for over 21 years despite significant cumulative
inflation.
Fee History:
March 18, 2004 — Administrative Order No. 58-04-03-F established the street tree establishment fee at $7.12 per
linear foot for the City-Plant option, with the same rate applied to the Developer-Plant bond calculation.
September 4, 2018 — Administrative Order No. 58-18-12-F updated program rules and administrative procedures.
The per-linear-foot fee remained unchanged at $7.12.
December 2022 — Urban Forestry staff prepared an internal memo recommending a fee increase based on CPI-U
methodology. The fee update was not completed at that time.
March 31, 2026 (Year 1 Proposed) — Fee of $12.23 per linear foot, representing a 71.76% increase based on CPI-U
adjustment from May 2004 through September 2025. Subsequent annual increases of 3% are established for Years 2
through 5 (July 1, 2027 through July 1, 2030), reaching $13.77 per linear foot by Year 5.
The 21-year gap between fee establishment and the proposed adjustment represents the longest period without a fee
update in the program’s history.
Exhibit B
to Administrative Order 58-26-04-F
Findings - Page 4 of 6
(c) The full costs of providing the service supported by the fee.
Findings:
The Developer Street Tree Program has been operating at a deficit for several fiscal years. An estimated $120,000
deficit is projected spread over the next several fiscal years due to the gap between the fee collected and actual tree
planting and establishment costs. For the city-plant option, EC 7.280 requires the City Manager to establish fees that
are “equal to the cost of the purchase, installation and establishment of the street trees required by the approved
street tree plan.” For the developer-plant option, EC 7.280, fees must “reimburse the city for its costs in connection
with plan review, inspection, administration and monitoring”
Program Cost Components:
Cost Component Rate/Amount
Current contract tree planting and establishment $650 per tree
Average program volume ~350 trees annually
Estimated annual program cost ~$227,500
Projected multi-year program deficit $120,000+
Current Contract Reference: Four Seasons Trees, LLC Contract #2021-05306, Amendment #5 (November 7, 2025)
— Tree Planting with Three-year Establishment at $650/tree.
Case Study — The McKenzie at Crescent (recalculated at current contract rates):
Metric Amount
Fee received ($7.12/lf × 2,335 lf) $16,625
Actual cost at current rates (52 trees × $650/tree) $33,800
Project deficit $17,175 (51% shortfall)
The current fee of $7.12 per linear foot covers only approximately 49% of actual program costs at current contract
rates. The proposed Year 1 fee of $12.23 per linear foot represents an inflation adjustment using the Consumer Price
Index for All Urban Consumers (CPI-U), reflecting 71.76% cumulative inflation from May 2004 through September
2025. At the Year 1 rate, fee coverage improves to approximately 84% of actual program costs.
CPI-U Calculation:
May 2004 CPI-U: 189.1; September 2025 CPI-U: 324.8; Cumulative inflation: (324.8 – 189.1) ÷ 189.1 = 71.76%;
Adjusted fee: $7.12 × 1.7176 = $12.23 per linear foot.
For reference, full cost recovery (100%) would require a fee of approximately $14.48 per linear foot based on
current contract rates. The proposed CPI-adjusted Year 1 fee of $12.23/lf represents a conservative approach that
brings the program substantially closer to cost recovery. The five-year schedule reaches approximately $13.77/lf by
Year 5, approaching full cost recovery over time.
(d) The amounts charged by other comparable providers.
Findings:
Street tree requirements and fee structures vary among Oregon municipalities. Many jurisdictions use in-lieu fees,
per-tree charges, or frontage-based calculations. Direct fee comparisons are challenging due to different program
structures, but the following provides regional context:
Oregon Municipal Street Tree Programs:
Jurisdiction Fee Structure Notes
Portland, OR 1 tree per 25 lf of frontage In-lieu fees when planting not feasible
Hillsboro, OR Developer plants; City oversight Development code requires street trees
Corvallis, OR "Tree for a Fee" program Cost-recovery basis
Salem, OR Developer plants; bond required Performance bond covers 3-year establishment
Exhibit B
to Administrative Order 58-26-04-F
Findings - Page 5 of 6
Bend, OR Developer plants per approved plan City reviews and inspects
Eugene’s Developer Street Tree Program is distinctive in offering a City-Plant option where the City assumes full
responsibility for tree selection, planting, and establishment. This model provides consistent quality outcomes but
requires adequate fee support. The proposed Year 1 fee of $12.23 per linear foot remains competitive with regional
programs while achieving necessary cost recovery for the City of Eugene.
(e) The revenue needs of the City as determined by the adopted city budget.
Findings:
The Developer Street Tree Program operates within the Urban Forestry Program budget under Parks and Open
Space. The program’s current fee structure results in a deficit that must be absorbed by the work unit operating
budget, reducing resources available for other urban forestry services.
The proposed fee adjustment is necessary to: (1) achieve cost recovery for the Developer Street Tree Program; (2)
ensure program sustainability without general fund subsidy; (3) preserve Urban Forestry resources for citywide tree
maintenance; and (4) maintain service levels for the approximately 350 trees planted annually through the program.
The five-year fee schedule provides a structured and predictable path toward improved cost recovery, with specific
fee amounts established for each year through July 1, 2030, allowing the development community to plan
accordingly.
SUMMARY OF PROPOSED FEE ADJUSTMENTS
A. Tree Removal Fees
Fee Category Current Year 1
5/15/26 Year 2 7/1/27 Year 3 7/1/28 Year 4 7/1/29 Year 5 7/1/30
1–10 trees (no public notice) $80.00 $137.00 $141.11 $145.34 $149.70 $154.19
1–10 trees (public notice) $160.00 $275.00 $283.25 $291.75 $300.50 $309.51
11–50 trees $320.00 $550.00 $566.50 $583.50 $601.00 $619.03
51–100 trees $520.00 $893.00 $919.79 $947.38 $975.80 $1,005.07
101+ trees (base) $520.00 $893.00 $919.79 $947.38 $975.80 $1,005.07
101+ per tree over 100 $1.00 $1.72 $1.77 $1.82 $1.87 $1.93
Appeal fee (R-6.305-J) $500.00 $859.00 $884.77 $911.31 $938.65 $966.81
B. Street Tree Planting Program Fees
Fee Category Current Year 1
5/15/26 Year 2 7/1/27 Year 3 7/1/28 Year 4 7/1/29 Year 5 7/1/30
App processing (base) $300.00 $515.00 $530.45 $546.36 $562.75 $579.63
App processing (per lf)* $0.01/ft $0.02/ft $0.02/ft $0.02/ft $0.02/ft $0.02/ft
Developer-plant agreement $200.00 $344.00 $354.32 $364.95 $375.90 $387.18
Developer-plant inspections
(per ft) $0.25/ft $0.43/ft $0.44/ft $0.45/ft $0.46/ft $0.47/ft
Developer-plant
establishment bond $7.12/ft $12.23/ft $12.60/ft $12.98/ft $13.37/ft $13.77/ft
City-plant agreement $100.00 $172.00 $177.16 $182.47 $187.94 $193.58
City-plant establishment fee $7.12/ft $12.23/ft $12.60/ft $12.98/ft $13.37/ft $13.77/ft
*Footage is the total footage of the development site that abuts street right of way.
**Application per-lf fee held at $0.02/ft through Year 5 (rounded per administrative simplicity from exact CPI
calculation of $0.0172).
Exhibit B
to Administrative Order 58-26-04-F
Findings - Page 6 of 6
Factors listed above that are irrelevant or inapplicable:
Not applicable. All factors listed in EC 2.020(2) were considered in determining the proposed fee amendments for
both Tree Removal Permits and Street Tree Planting Program fees.
Data Sources:
1. U.S. Bureau of Labor Statistics, Consumer Price Index for All Urban Consumers (CPI-U), All Items, U.S. City
Average, Not Seasonally Adjusted. Series CUUR0000SA0. May 2004 index: 189.1; September 2025 index: 324.8.
2. City of Eugene Administrative Order No. 58-04-03-F (March 18, 2004) — Established current fee schedule.
3. City of Eugene Administrative Order No. 58-18-12-F (September 4, 2018) — Updated program rules; fees
unchanged.
4. Developer Street Tree Program Summary and Financials (Internal tracking spreadsheet).
5. Four Seasons Trees, LLC Contract #2021-05306, Amendment #5 (November 7, 2025) — Current tree planting
contract rate: $650 per tree.
6. Urban Forestry memo to Craig Carnagey, Matt Rodrigues and Lacey Risdal (December 27, 2022) — Program
background and recommendations.
7. Municipal code and fee schedule review of comparable Oregon jurisdictions (December 2025–January 2026).
8. City of Portland Parks & Recreation, Urban Forestry Fee Changes (June 2025).
9. Clackamas County Tree Code Comparison Document (January 2024).
Response to Public Comments
During the 15-day comment period, the City received two written comments regarding the proposed amendments to
the Tree Removal & Developer Street Tree Planting Fee Schedule/Administrative Rule. A summary of the
comments received, and findings addressing the comments, are set out below:
Comment: Mr. Shaun Hyland, of John Hyland Construction, Inc., expressed concern about increasing fees during a
period of economic difficulty for local development and business recruitment, noting developers are already over-
taxed and over-regulated.
Response: The proposed fee adjustment is a measured, CPI-based update reflecting inflationary increases since
2004 and phased across five years to reduce impacts. No changes will be made to the fee schedule as a result of this
comment.
Comment: Mr. Jim Atkins, of Atkins Dame, Inc., commented that the City should complete replanting of trees
previously removed in the river district before adjusting fees. This comment is outside the scope of the proposed fee
schedule amendment.
Response: No changes will be made to the fee schedule as a result of this comment. Staff will follow up with Mr.