Work Session: Interstate 5 Willamette River Bridge – Oregon Department of
Transportation Project Update
Meeting Date: September 14, 2009 Agenda Item Number: B
Department: Public Works Staff Contact: Chris Henry
www.eugene-or.gov Contact Telephone Number: 541-682-8472
ISSUE STATEMENT
The Eugene City Council will receive an update from the Oregon Department of Transportation
(ODOT) about the replacement I-5/Willamette River Bridge. ODOT staff will present details of the
project construction schedule, community coordination efforts and remaining project design elements.
The council will have an opportunity to ask questions of ODOT staff.
BACKGROUND
The Oregon Department of Transportation has initiated construction to replace existing deteriorated
structures and detour bridge on Interstate 5 at the Willamette River crossing. Throughout the project,
the council has received periodic updates from the ODOT project manager and staff. Additional project
information is available through the ODOT project website at: http://www.WillametteBridge.org
RELATED CITY POLICIES
There are no remaining City policy actions necessary for the bridge construction.
COUNCIL OPTIONS
The council will receive information and provide feedback to ODOT staff.
CITY MANAGER’S RECOMMENDATION
None; this item is information only.
SUGGESTED MOTION
None; this item is information only.
ATTACHMENTS
A. ODOT Project Introduction
B. ODOT Agency and Community Coordination
C. ODOT Frequently Asked Questions
D. ODOT Project Information Paper
Z:\CMO\2009 Council Agendas\M090914\S091409B.doc
FOR MORE INFORMATION
Staff Contact: Chris Henry, Transportation Planning Engineer
Telephone: (541) 682-8472
Staff E-Mail: chris.c.henry@ci.eugene.or.us
Z:\CMO\2009 Council Agendas\M090914\S091409B.doc
Introduction
September 3, 2009
Construction of the Interstate 5 Bridge over the Willamette River began in July. Tasks for the
first six months include building a work bridge in the water, demolishing the decommissioned
bridge and widening the southbound on-ramp from Franklin Boulevard.
Detour paths in the Whilamut Natural Area are ensuring bicyclists and pedestrians safe mobility
around the bridge construction areas on the north and south banks of the river. ODOT has also
installed kiosks along paths to inform users of the detours. The kiosks will be updated and
modified on a regular basis as detours change throughout construction of the four-year project.
Motorists will see minimal impacts on I-5 and occasional closures to Franklin Boulevard and the
southbound on-ramp from Franklin Boulevard.
This packet includes a general overview of the project and a summary of agency and
community coordination.
Agency and Community Coordination
September 2009
The Willamette River Bridge project in Eugene and Springfield signifies a movement forward, an
opportunity to engage and build bridges with the community.
The WRB project is doing more than just building a new bridge; the project will leave the
surrounding area in better condition than before construction. The project is impacting three
parks, the historic millrace, commuters who utilize the bike paths and countless park users.
A 10-member Community Advisory Group has been instrumental in developing the project goals
and objectives. The group provided input and recommendations on the preferred bridge type
and will continue to help shape the project through final design and construction. A member of
the CAG is also a voting member on the Project Development Team. The PDT is the main
decision-making body for the project, and includes representatives of ODOT, FHWA, the cities
of Eugene and Springfield, Lane County and the CAG.
ODOT is extremely thankful to the hundreds of hours of volunteer time that has already been
devoted by the residents and design professionals of Eugene and Springfield on this important
project.
Coordination with the cities of Eugene and Springfield
Park impacts and improvements
To complete the project, construction crews will occupy part of the Whilamut Natural Area of
Alton Baker Park west of I-5 for about three years. Contractors will use approximately two acres
of the park as a staging area and about one mile of an existing paved path (North Walnut Road)
to access the staging area and project site. Crews will also use 770 feet of a paved path parallel
to I-5 for access. This path and a parallel running path will be closed to park users during
construction, but temporary detours for both paths will be provided west of the staging area.
ODOT has installed kiosks throughout the park to inform path users of detour routes. These will
be continuously updated as detours change throughout construction.
1
An agreement with Eugene Parks and Open Space defines ODOT’s usage of the park and
requirements to minimize and mitigate park impacts. Upon completion of the project, ODOT will
restore park areas affected by construction to an equal to or better than original condition.
Contractors will repave utilized paths and make many other improvements in the park areas. In
addition, the city of Eugene will receive additional park lands as compensation for the
permanent impacts to the Whilamut Natural Area. ODOT will not directly use the park lands for
construction activities on the Springfield side of the project. However, ODOT will make
improvements to the paths to support increased bike traffic from construction detours through
Eastgate Woodlands.
ODOT will not use the park on the Springfield side of the project, but will improve the bike path
through the Eastgate Woodlands. ODOT has coordinated closely with the Willamalane Park and
Recreation District and the Citizen Planning Committee of the Whilamut Natural Area of Alton
Baker Park.
Historic Eugene Millrace
The Millrace structure beneath the southern end of the I-5 bridges is a significant historical
resource and is eligible for inclusion in the National Register of Historic Places. The National
Historic Preservation Act requires that impacts to the millrace be avoided wherever possible and
reduced where necessary.
The project team will work to make the Millrace more visible as a historic resource and create
new pathways to improve access for closer viewing. During public outreach events, the team
will provide information about the Millrace while soliciting photographs, documents, and oral
history from the public to fill in gaps in the millrace history. The contractors will incorporate
information about structure into interpretive displays to be installed as part of the final site
restoration.
Coordination with the community
Public involvement
There have been many touch points for public outreach and involvement for the I-5 Willamette
River Bridge project, including:
?
Newsletters and a project Web site to provide information.
?
Open house meetings to provide project information and solicit public input.
?
An online survey soliciting input about the bridge type.
?
A presence in the Whilamut Natural Area to describe upcoming detours to park trails.
?
Distribution of the Environmental Assessment, a public hearing on the EA, and
opportunities to provide written and oral comments on the EA. Thirty individuals and
agencies submitted comments on the EA. All comments were reviewed and considered
by ODOT. The Revised Environmental Assessment contains revisions to information
presented in the EA that have been made in response to public comments.
2
Representatives from ODOT and the project team have also made a number of presentations
and briefings to local community and governmental groups on request. Topics included general
information about the project as well as more area specific items of concern such as sound
walls and bike-pedestrian pathway connections. The presentations to groups included:
?
Harlow Neighbors.
?
Laurel Hill Valley Citizens Association.
?
Local chapter of the American Institute of Architects.
?
Springfield City Council.
?
Eugene City Council.
?
Lane County Board of Commissioners.
?
Metropolitan Policy Committee.
?
Eugene Bethel Lions Club.
?
Eugene Metro Rotary Club.
?
Springfield Rotary.
?
Eugene Bicycle and Pedestrian Advisory Committee.
?
Citizen Planning Committee of the Whilamut Natural Area of Alton Baker Park.
Building upon the changing of the tides of positive public opinion, ODOT’s vision for construction
outreach is two-pronged. One prong will encompass traditional media outreach/
communications, including seeking out award opportunities to recognize the project. The
second prong will create and build on a groundswell of positive support; a grassroots campaign
of sorts.
Methods to be used include hosting meetings for specific communities, conducting project tours,
attending organizations’ regular meetings, and setting up information tables/booths at events to
create touch points and a presence in Eugene and Springfield for the project.
Thus far, construction outreach activities have included mailings to stakeholder groups that use
the trails and river, a high profile groundbreaking ceremony, a Web cast that tells the story of
the park with a bridge in it, and updates via Twitter at OregonDOT. Staff will once again be in
the Whilamut Natural Area on Sept. 18 and 19 to notify users of upcoming path detour changes.
Aesthetic design
The CAG and PDT have developed a theme for the design discussion to help guide the work of
the bridge design team as well as local artists and architects. "Whilamut Passage" (pronounced
“wheel-a-moot”) recognizes the unique setting of the bridge in the Whilamut Natural Area, a
place of historic and environmental significance. The setting is also a transportation hub of
bicycle, pedestrian, rail, waterway and highway traffic. Design experts continue to work together
to ensure that the bridge structure and environment fit together under this theme.
In late 2008, ODOT sought the help of local architects, artists, landscape architects, structural
engineers and transportation experts to converge around design themes for the bridge. The
local chapter of American Institute of Architects took on the project as a public service and for
3
professional development. The AIA formed a steering committee to work intensively on both the
process and the product.
In February 2009, design professionals met in workshops to make the proposed Willamette
River Bridge and its surroundings memorable, meaningful, and truly representative of
Springfield and Eugene. They created actionable ideas that could be applied above and below
the deck of the Willamette River Bridges. The CAG and PDT will continue to work with the
design experts to refine and implement these ideas through the end of 2009.
4
Frequently Asked Questions
September 2009
What are the benefits of the project?
The new bridge will improve mobility, connectivity and safety for drivers on Interstate 5. It will
also improve the regional transportation system. The new bridges will be modern facilities that
meet long-term traffic demands and allow for future expansion of Franklin Boulevard, I-5 and the
railroad. The proposed project will reduce the number of bridge piers in the Willamette River and
surrounding areas, diminishing impacts on the river environment, wildlife and park users. Traffic
volumes are projected to require three lanes in each direction of I-5 in this area within 20 years.
Even if the old bridge were repaired now, ODOT would need to replace it in 20 years at an
estimated construction cost of $350 million.
Why is ODOT replacing the bridge rather than repairing it?
A 2002 inspection identified shear cracks in the Interstate 5 bridge structure. Further inspection
determined that the bridge was structurally deficient and could not be repaired or widened to
accommodate projected traffic increases. ODOT determined that a new bridge was needed to
improve safety while maintaining connectivity and mobility.
ODOT built a temporary bridge in 2004 as an interim solution to keep I-5 open for traffic until a
new bridge could be built. The temporary bridge was constructed using materials and methods
that could be installed quickly, but that do not meet environmental or design standards for
permanent interstate bridges. The temporary bridge has alleviated safety concerns and allowed
normal commerce along I-5 to continue while ODOT works with the public and the design team
to create a distinctive permanent bridge that satisfies environmental and land-use requirements.
While repairing the I-5 bridge would have cost about $50 million, it would have required an
estimated $50,000 per year in ongoing maintenance. In addition, ODOT would not have been
able to replace the substandard shoulders that keep disabled vehicles from pulling out of the
travel lanes in an emergency.
1
ODOT is designing the new bridges wide enough to eventually carry up to six-lanes of traffic
(three-lanes in each direction) to meet the projected long-term traffic needs. The new bridges
will be striped to carry two lanes in each direction, matching the existing alignment of I-5. Any
future widening of I-5 would require a full environmental review.
How was the deck arch design chosen?
The decision to build a deck-arch bridge for the I-5 crossing over the Willamette River follows
nearly two years of discussion and relationship-building with residents and local government
officials in Eugene and Springfield, along with full consideration of design opportunities and
constraints.
ODOT’s goal is to strike a balance between design characteristics of highways and bridges and
an affordable budget that responsibly uses transportation funding. Since these discussions
began, the costs of bridge materials such as asphalt, concrete and steel have increased beyond
projections. As a result, a preliminary cost estimate for a through-arch bridge recommended in a
community survey is more than $20 million over the project budget. This means ODOT simply
cannot find a fiscally responsible way to build a through-arch bridge. After revisiting bridge
choices that fit the project budget, and considering community input, ODOT chose an option
with arches under the deck. The deck-arch bridge, with its graceful curves and attractive profile,
strikes a balance between a distinctive design and economic reality.
2
Project Information Paper
I-5 Willamette River Bridge – Eugene and Springfield
Updated September 1, 2009
Project location
?
On Interstate 5 at milepost 192.7 where it crosses the Willamette River between the cities of
Eugene and Springfield.
Project purpose and need
?
The purpose of the project is to improve safety and maintain connectivity and mobility for all
users of I-5 over the Willamette River and the Eugene/Springfield metropolitan area.
?
Bridge inspection reports in 2002 showed shear cracks growing quicker than expected
throughout the reinforced concrete beams supporting the bridge deck. Traffic has been
diverted to a temporary detour structure until a new bridge can be constructed.
Construction overview
?
Construction will have minor impacts on vehicle traffic. Bicycle and pedestrian path users
may be affected, and signed detours will be provided.
?
ODOT is designing the new bridges wide enough to eventually carry up to six lanes of traffic
(three lanes in each direction) to meet the projected long-term traffic needs. The new
bridges will be striped to carry two lanes in each direction, matching the existing alignment
of I-5. Any future widening of I-5 would require a full environmental review.
?
The new bridge design will accommodate potential future configurations of Franklin
Boulevard, to the extent feasible.
?
Lane County and the cities of Eugene and Springfield are active participants in the process
through participation on the Project Development Team.
?
The bridge design phase of the project will continue through the end of 2009.
For updated information on highway work and current travel information throughout Oregon, visit
www.tripcheck.com or call the toll-free Oregon road report at 511 or (800) 977-6368.
Visit the ODOT News Media Center at www.oregon.gov/ODOT/COMM/.
I-5 Willamette River Bridge - Eugene and Springfield Page 2
Cost estimate
?
The project is funded at $40 million for design and $147 million for construction.
?
Funding sources are Oregon Transportation Investment Act and Federal SAFETEA-LU
(Safe, Accountable, Flexible, Efficient Transportation Equity Act: A Legacy for Users)
earmark funds.
Key project milestones
?
Construction: Summer 2009 to winter 2012.
?
Construction crews establish staging and access areas in Alton Baker Park in August 2009.
?
Detours to bicycle and pedestrian paths begin in August 2009.
For more information or to schedule a meeting with your organization, contact:
?
Suzanne Roberts, Public Involvement Coordinator, (503) 471-6866;
Suzanne.Roberts@obdp.org.
?
Rick Little, ODOT Region 2 Public Information Officer, (541) 726-2442;
Richard.Little@odot.state.or.us.
Rendering of the new I-5 Willamette River Bridge
For updated information on highway work and current travel information throughout Oregon, visit
www.tripcheck.com or call the toll-free Oregon road report at 511 or (800) 977-6368.
Visit the ODOT News Media Center at www.oregon.gov/ODOT/COMM/.