Work Session: Lane Community College Downtown Center Project
Meeting Date: January 25, 2010 Agenda Item Number: B
Department: Planning & Development Staff Contact: Denny Braud
www.eugene-or.gov Contact Telephone Number: 541-682-5536
ISSUE STATEMENT
th
Lane Community College (LCC) has identified the 10 and Charnelton property owned by the
Urban Renewal Agency (URA) as the preferred site for a new LCC downtown education facility.
th
The URA is being asked to select LCC to redevelop the 10 and Charnelton property as the site
for its downtown facility. Terms for the transfer of the property to LCC would be brought back
for URA Board consideration at a later date.
BACKGROUND
LCC has provided educational services from its Downtown Center for over 30 years. The
Downtown Center, located at 1059 Willamette Street, no longer meets the needs of the college,
and LCC intends to build and own a new, mixed-use building from which to offer educational
and other services in downtown Eugene (see map Attachment A). The URA currently owns the
th
vacant half-block site bounded by Charnelton Street on the west, 10 Avenue on the south and
Olive Street on the east (see map Attachment B). LCC has approached the URA regarding
acquisition of the property for the new facility.
The City Council has had ongoing discussions regarding downtown revitalization and local
economic development actions that support jobs and redevelopment. LCC’s new downtown
center has emerged as one of eight projects that could be pursued to foster a vibrant downtown
and boost the local economy. Public involvement, conducted to date and focused on the eight
th
projects, has demonstrated strong support for the proposed LCC project on the 10 and
Charnelton property. A detailed description of the project and impacts is included in Attachment
C.
LCC plans to utilize a three-phase process to complete the project. The first phase will result in
a feasibility report addressing site conditions, code requirements, potential tenants, housing
feasibility, conceptual design, and a preliminary cost estimate. LCC has hired Gerding/Edlen
Development (GED) as the Project Manager. GED is in the process of completing the feasibility
report, which is expected to be completed in early March 2010. The second phase will include
design, budgeting, financing and legal agreements. The final phase will include construction and
move-in. A draft timeline for the project is included in Attachment D.
Because there are significant costs and commitments associated with the second phase of the
project work, LCC will need to secure site control before moving into phase two. Site control
will also be important for LCC to access potential financial resources that are targeted for
Z:\CMO\2010 Council Agendas\M100125\S100125B-and att's A-D.doc
“shovel ready” projects. Site control will occur when the URA enters into an agreement with
LCC regarding the site. LCC is seeking to enter into an agreement with the URA by April 2010,
regarding the transfer of ownership.
RELATED CITY POLICIES
The new LCC Downtown Center project addresses many goals for Eugene and downtown,
including activity in the core, culture and education, employment and job training, and
sustainability. This project is supported by the Downtown Plan; Downtown Code Amendments;
West Broadway Advisory Committee Recommendations; Downtown Urban Renewal Plan;
Central Area Transportation Study; Downtown Vision; City Council’s Downtown Collective
Statements from August 2009; Downtown Policing Action Plan Team Short-Term Public Safety
Strategy Recommendations 2004; Cultural Policy Review; Mayor’s 2004 Committee on
Economic Development; Growth Management Policies; Sustainable Business Initiative; and
JEO’s regional economic development principles.
URA BOARD OPTIONS
th
1.Select LCC to redevelop the 10 and Charnelton property as the location for its new
downtown education facility, direct the Agency Director to enter into an exclusive
negotiation agreement with LCC for a period of six months, negotiate a purchase and sale
agreement, and return to the URA Board for final approval of the terms.
2.Take no action at this time.
AGENCY DIRECTOR’S RECOMMENDATION
th
The Agency Director recommends that the URA Board select LCC to redevelop the 10 and
Charnelton property as the location for its new downtown education facility. Further, the
director recommends that the board direct the Agency Director to enter into an exclusive
negotiation agreement with LCC for a period of six months, negotiate a purchase and sale
agreement, and return to the URA Board for final approval of the terms.
SUGGESTED MOTION
th
Move to select LCC to redevelop the 10 and Charnelton property as the location for its new
downtown education facility. Direct the Agency Director to enter into an exclusive negotiation
agreement with LCC for a period of six months, negotiate a purchase and sale agreement, and
return to the URA Board for final approval of the terms.
ATTACHMENTS
A.1059 Willamette Street Map
th
B.10 and Charnelton Property Map
C.LCC Project Description
D.LCC Project Timeline
Z:\CMO\2010 Council Agendas\M100125\S100125B-and att's A-D.doc
FOR MORE INFORMATION
Staff Contact: Denny Braud
Telephone: 541-682-5536
Staff e-mail: denny.braud@ci.eugene.or.us
Z:\CMO\2010 Council Agendas\M100125\S100125B-and att's A-D.doc
ATTACHMENT A
1059 Willamette Street Map
Z:\CMO\2010 Council Agendas\M100125\S100125B-and att's A-D.doc
ATTACHMENT B
th
10 & Charnelton Property Map
Z:\CMO\2010 Council Agendas\M100125\S100125B-and att's A-D.doc
ATTACHMENT C
LCC Project Description
GENERAL BACKGROUND
Lane Community College (LCC) is in the planning stages for a new 80,000 square foot
th
Downtown Center. LCC has selected the 10 & Charnelton Development Site as the preferred
location for the project.
The new facility will house the programs currently located in LCC’s Downtown Center –
continuing education, non-credit workforce development programs, English as a Second
Language, and Adult Basic Education. In addition, Career and Technical Energy Programs, the
Business Development Center and Employee Training, eDev, Senior Companion Program, and
th
Successful Aging Institute will relocate from LCC’s facility at 14 and Willamette. Career and
Technical programs that support training for “green” jobs such as Energy Management and
Renewable Resources will be relocated from the main campus to the downtown facility. It is
intended that the multi-use facility will include space for lease by tenants and other community
uses. For example, the Oregon Small Business Development Center Network, hosted by LCC
and currently leasing space from the City of Eugene, will move into the building. The building
is projected to have a 100% utilization rate for approximately 16 hours per day, 6 or 7 days a
week. A feasibility study regarding the inclusion of student housing in the building is currently
being conducted.
The new building will be a “state of the art” educational building and a learning laboratory for
the Energy Management students to use for experiments and monitoring. LCC is targeting
1
LEED Platinum certification and the Living Building Challenge as standards for the building.
Both building programs include standards which will add to the overall cost of construction but
will ultimately provide significant operating savings to LCC.
To date, LCC has secured approximately $17 million for the project through a local bond
measure and state matching funds. Although the total cost of the project is unknown at this time,
the most recent estimate is $27 million. Because LCC’s operating funds (used to make debt
service payments) are limited, the Downtown Center project is actively seeking alternative, non-
debt funding sources.
1
The Living Building Challenge (LBC) was established by the Cascadia Region Green Building Council. LBC
goes beyond LEED Platinum certification in terms of sustainability. To date the Living Building Challenge has not
been met by any single building.
Z:\CMO\2010 Council Agendas\M100125\S100125B-and att's A-D.doc
JOBS/ECONOMIC DEVELOPMENT IMPACT
ImpactDescriptionTotal
Temporary Construction Jobs based on cost of construction project, business purchases
300-400
Related Jobsrelated to construction, and employee purchases
Permanent JobsJobs relocated to downtown45+
Job Training ProgramsAt least 6 job training programs servicing 8,000 students
Influx of LCC students and employees will attract new
Indirect Economic & Other
businesses, housing, and related services; exceptional building
Impacts
replaces the current hole and parking lot.
2
Temporary Construction Related Jobs:
Expansion of LCC’s downtown presence will impact
downtown’s economy as well as the regional economy. The benefits to downtown will be
realized beginning with the construction phase of the building. With a projected total investment
of $25-35 million, the project will result in as many as 272 to 380 temporary construction jobs
estimated to last 18 months and approximately 26 indirect and induced jobs in areas such as
production and transportation of construction materials.
Permanent Jobs:
The new Downtown Center investment will ensure that LCC’s existing,
professional employment base will remain downtown. LCC plans to employ approximately 150
individuals at the new facility, about 45 of these employees will be new or relocated from other
college sites. It is projected that a portion of the LCC building will be occupied by tenants.
Specific tenants are unknown at this time; however, it can be assumed that one employee per 400
square feet would occupy additional leased space.
Job Training Programs:
The facility will include programs that lead to degrees and/or
certificates in energy management, renewable energy, water conservation, building operations,
sustainable building advising, and building auditing/inspecting. These programs represent some
of the fastest growing career fields in today’s economy, and the new Downtown Center will be
well positioned to prepare the workforce for the rapidly growing green jobs sector. Additionally,
core career and technical training programs offered through the Downtown Center create career
pathways, enhanced job skills, and retraining opportunities for community members. The
Downtown Center will offer education and training in areas such as massage therapy, nutritional
therapy, emergency medical technician, fitness education, AutoCAD, graphics, word processing,
and English as a second language.
In the 2008-2009 school year, LCC served 36,909 individuals. Approximately 3,500 of those
students were served through the current LCC downtown center. LCC anticipates serving up to
8,000 students through the programs that will be housed in the new LCC downtown center.
Based on the most current data available, in the 2007-2008 school year, LCC awarded 738
degrees and certificates. An average of 84% of LCC’s former career technical students who
2
Temporary construction jobs were calculated based on the estimated costs of construction. Staff applied the U.S.
Department of Energy standard: for every $92,000 invested in a project one temporary construction job will be
created. Staff provided the estimated construction costs to the Oregon Employment Department to calculate the
number of temporary construction jobs that would be created by “new” money flowing into the local economy.
Z:\CMO\2010 Council Agendas\M100125\S100125B-and att's A-D.doc
graduated found employment in jobs related to their LCC training within nine months. LCC
reports that its full-time enrollment grew by 15.7% last year and growth is expected to continue
as displaced workers return to college to train for the new economy and as high school graduates
seek a quality and affordable post-secondary education. LCC’s programs will have the ability to
expand in the downtown building to meet this growing demand. Therefore, more people will
benefit from these programs that advance skills, improve salaries and wages, and develop
businesses.
The living laboratory aspect of the building for the Energy Management Program will further the
national reputation of LCC’s Energy Management program and attract even more students to this
already desirable field. Of the LCC students graduating from the energy programs, 90% find
employment within three months of graduation and earn an annual salary between $48,000 and
$50,000. The cultivation of a significant labor pool of highly-trained energy management
specialists is in Eugene’s best interest. The presence of these programs and the skilled graduates
that the program produces will be assets in attracting new, green industries to Eugene and in
advancing the sustainability of our existing businesses.
Indirect Economic Impacts:
The extensive hours of operation will create both daytime and
evening activity at a key intersection of downtown. Economic opportunities for current and
future downtown businesses will be created as students, employees, and visitors support
restaurants, retail, services and cultural venues.
Z:\CMO\2010 Council Agendas\M100125\S100125B-and att's A-D.doc
ATTACHMENT D
LCC Project Timeline
Lane Community College Downtown Campus building
January 15, 2010
PROJECT SCHEDULE
PHASE 1. FEASIBILITY REPORT
2009 – Nov. Issue RFP for Project Manager
Dec. Select Project Manager
Begin 90 day Feasibility Report
Issue RFP for Architect
2010 – Jan. Select Architect
Mar. Presentation of Feasibility report to board of Education
Apr. Enter into agreement with URA on land transaction
PHASE 2. DESIGN AND CONSTRUCTION DOCUMENTS PHASE
2010 May Issue RFP for Project Manager & Architect
Issue RFP for Commissioning Agent
June Select Project Manager, Architect and Commissioning Agent
Finalize financing plan
Issue RFP for CMGC firm (if CMGC delivery method is adopted)
July Select CMGC firm
2011 April Complete Design & Construction documents phase work
PHASE 3. CONSTRUCTION AND MOVE-IN PHASE
2011 May Obtain building permit and start construction (if CMGC method is to be
used)
Put Contract documents out to bid (if Design-Bid-Build method is used)
2013 June Building reaches substantial completion
July Install College purchased Furniture, Fixtures & Equipment
Aug. Move people, supplies, etc. from existing Downtown Center to new
building
Sept. Start classes in new building