Work Session: Lane Community College Downtown Project
Meeting Date: March 10, 2010 Agenda Item Number: B
Department: Planning & Development Staff Contact: Denny Braud
www.eugene-or.gov Contact Telephone Number: 541-682-5536
ISSUE STATEMENT
th
Lane Community College (LCC) has been selected to redevelop the 10 and Charnelton property (see
Attachment A map) for its new downtown campus project. The Urban Renewal Agency (URA) Board
provided direction to enter into an exclusive negotiation with LCC, negotiate a purchase and sale
agreement, and return to the URA Board for final approval of the terms. The URA Board is being
asked to review and approve the terms.
BACKGROUND
At the January 25, 2010 URA work session, the following motion passed:
th
Move to select LCC to redevelop the 10 and Charnelton property as the location for its new
downtown education facility. Direct the Agency Director to enter into an exclusive negotiation
agreement with LCC for a period of six months, negotiate proposed terms for a purchase and
sale agreement for review and approval by the URA Board.
LCC is currently conducting a feasibility analysis addressing site conditions, code requirements,
potential tenants, housing feasibility, conceptual design, and a preliminary cost estimate. The
feasibility report is the first phase of the project and is expected to be completed in early March. The
project concept being analyzed in the feasibility phase includes a new 80,000 square foot education
building and adjoining 80,000 square feet of student housing which would accommodate
approximately 200 students.
LCC has had preliminary discussions with their Board of Education regarding the needs associated
th
with acquisition of the 10 & Charnelton property. The URA’s negotiations with LCC have centered
on assistance provided by the URA to help remove specific project barriers including 1) site control, 2)
timing of the disposition of the existing Willamette Street property (see Attachment B map), and 3)
maximizing funds available for project financing.
Because there are significant costs and commitments associated with the second phase of the project
work, LCC will need to secure site control before moving into phase two. Site control will also be
important for LCC to access potential financial resources that are targeted for “shovel ready” projects.
Site control will occur when the URA enters into an agreement with LCC regarding the site. LCC is
seeking to enter into an agreement by April 2010.
The timing of the disposition of LCC’s existing Willamette Street property also has implications that
impact the amount of project financing available for the new downtown campus project. LCC may
need to capture the value of their existing Willamette Street property up front so that it can be
contributed to the overall construction financing for the new project. LCC selling its property after it
has been vacated does not provide an upfront source of funding for construction and creates
uncertainty regarding the timing and amount of sale proceeds that can be generated in the future.
Additionally, LCC has expressed concern regarding the Willamette Street property remaining vacant
for a long period after they move out and believe that the URA would be more successful facilitating
the reuse or redevelopment of the property.
The outline of terms proposed for the purchase and sale agreement between the URA and LCC are
th
included in Attachment C. The basis for the proposed agreement includes selling the 10 & Charnelton
th
Street property to LCC at no cost. (The most recent appraisal of the 10 & Charnelton site indicated a
value of $1.6 million)
The URA would also commit to purchasing LCC’s Willamette Street property for the appraised value of
$1.2 million, but only if the City Council amends the downtown urban renewal plan to increase the
maximum indebtedness limit, and includes LCC as a project in that amendment. The agreement would
require the $1.2 million to be used in the new downtown campus project. The $1.2 million cost of
purchasing the LCC property will be deducted from the amount of URA financial assistance called for if
the urban renewal plan is amended (i.e., if the plan amendment includes $8 million of assistance, then
the URA’s actual financial contribution would be reduced to $6.8 million). The agreement would not
include or imply a commitment of additional financial assistance beyond the property transactions.
The agreement would allow LCC to occupy the Willamette Street building until the new project is
complete. If LCC’s project does not move forward in a timely manner (generally based on the projected
project timeline forecasted in LCC’s pending feasibility report), the URA would have the right to
th
repurchase the 10 & Charnelton property at no cost. In this scenario, the URA’s commitment to
purchase the Willamette Street property would be removed. The agreement would also allow either
party to void the agreement if an environmental investigation of the property is not satisfactory.
RELATED CITY POLICIES
The new LCC Downtown Center project addresses many goals for Eugene and downtown, including
activity in the core, culture and education, employment and job training, and sustainability. This
project is supported by the Downtown Plan; Downtown Code Amendments; West Broadway Advisory
Committee Recommendations; Downtown Urban Renewal Plan; Central Area Transportation Study;
Downtown Vision; City Council’s Downtown Collective Statements from August 2009; Downtown
Policing Action Plan Team Short-Term Public Safety Strategy Recommendations 2004; Cultural
Policy Review; Mayor’s 2004 Committee on Economic Development; Growth Management Policies;
Sustainable Business Initiative; and JEO’s regional economic development principles.
URA BOARD OPTIONS
1.Authorize the Agency Director to enter into a purchase and sale agreement with LCC consistent
with the terms and conditions included in Attachment C.
2.Amend the terms and conditions included in Attachment C, and authorize the Agency Director
to enter into a purchase and sale agreement with LCC consistent with the amended terms and
conditions.
3.Take no action at this time.
AGENCY DIRECTOR’S RECOMMENDATION
The Agency Director recommends that the URA Board authorize the Agency Director to enter into a
purchase and sale agreement with LCC consistent with the terms and conditions included in
Attachment C.
SUGGESTED MOTION
th
Move to authorize the Agency Director to enter into an agreement with LCC to 1) sell the 10 &
Charnelton property to LCC at no cost (or $1.00) consistent with the terms and conditions included in
Attachment C, and 2) if the City Council amends the downtown urban renewal plan to increase the
maximum indebtedness limit, and includes LCC as a project in that amendment, then the URA will
agree to purchase LCC’s Willamette Street property for $1,200,000 consistent with the terms and
conditions included in Attachment C.
ATTACHMENTS
th
A. Map of 10 & Charnelton Site
B. Map of LCC Willamette Street Property
C. Terms for the Transfer of Property
FOR MORE INFORMATION
Staff Contact: Denny Braud
Telephone: 541-682-5536
Staff e-mail: denny.braud@ci.eugene.or.us
ATTACHMENT A
th
10 & Charnelton Property Map
Z:\CMO\2010 Council Agendas\M100310\S100310B-Att A-C.doc
ATTACHMENT B
LCC Willamette Street Property Map
Z:\CMO\2010 Council Agendas\M100310\S100310B-Att A-C.doc
ATTACHMENT C
Terms for the Transfer of Property
Lane Community College – Eugene Urban Renewal Agency
February 24, 2010
An agreement will be executed by Lane Community College (LCC) and the Eugene Urban Renewal
Agency (URA) following URA Board approval and LCC Board approval consistent with the following
terms:
th
?
The URA will sell to LCC the 10 & Charnelton site (valued at approximately $1.6 million) for
th
$1. LCC will develop the 10 & Charnelton property in a timely manner and generally
consistent with the proposed new downtown campus project description (see Exhibit A). In
the event that LCC does not proceed with the development of its new downtown campus at that
site in a timely manner (generally based on the projected project timeline forecasted in LCC’s
pending feasibility report) the URA will have the right to repurchase the property for $1.
?
If the City Council amends the downtown urban renewal plan to increase the maximum
indebtedness limit, and includes LCC as a project in that amendment, then the URA will
purchase LCC’s Willamette Street property for the appraised value ($1,200,000). The actual
sale will happen only if and after LCC gives notice to the URA that it is ready to transfer the
property to the URA (and again, only if the urban renewal plan was amended to increase the
maximum indebtedness). The cost of purchasing this site will be deducted from the amount of
URA financial assistance called for by that urban renewal plan amendment (i.e., if the plan
amendment includes $8 million of assistance, then the URA’s actual financial contribution
would be reduced to $6.8 million).
?
If the URA purchases LCC’s downtown site, LCC will be allowed to lease back the property
for a nominal amount until construction of the new downtown campus building is complete.
?
Real estate transactions will be contingent on due diligence, including environmental due
diligence.
Z:\CMO\2010 Council Agendas\M100310\S100310B-Att A-C.doc
Exhibit A
Lane Community College Downtown Campus
– project description
Lane Community College (LCC) is in the planning stages for a new 80,000 square foot downtown
campus education facility. LCC is also considering the feasibility of including approximately 200 beds
of student housing within approximately 80,000 square feet of new housing construction. LCC has
th
selected the 10 & Charnelton Development Site as the preferred location for the project.
The new education facility will house the programs currently located in LCC’s Downtown Center
(1059 Willamette Street) – continuing education, non-credit workforce development programs, English
as a Second Language, and Adult Basic Education. In addition, Career and Technical Energy
Programs, the Business Development Center and Employee Training, eDev, Senior Companion
th
Program, and Successful Aging Institute will relocate from LCC’s facility at 14 and Willamette.
Career and Technical programs that support training for “green” jobs such as Energy Management and
Renewable Resources will be relocated from the main campus to the downtown facility. It is intended
that the multi-use facility will include space for lease by tenants and other community uses.
The new building will be a “state of the art” educational building and a learning laboratory for the
Energy Management students to use for experiments and monitoring. LCC is targeting LEED
Platinum certification.