Work Session: Review of 2009 Implementation of Bond Measure to Fix Streets
Meeting Date: April 14, 2010 Agenda Item Number: B
Department: Public Works Staff Contact: Kurt Corey
www.eugene-or.gov Contact Telephone Number: 541-682-8421
ISSUE STATEMENT
This work session is an opportunity for the Eugene City Council to review the first year of the
implementation of Measure 20-145, the bond measure to fix streets. To facilitate this review, two
documents were prepared: the Citizen Street Repair Review Panel 2009 Report and the independent
accountant’s report prepared by Isler CPA. These reports were provided to the council on February 25,
2010, as informational items in compliance with the council resolution placing the bond measure on the
ballot.
BACKGROUND
Council Action History
Following considerable study and discussion, including forming a Council Committee on Transportation
Funding and convening an ad hoc citizen Street Maintenance Task Force, the council on July 28, 2008,
approved Resolution 4953, calling a city election on a measure authorizing the issuance of $35.9 million
of general obligation bonds to fund street preservation projects. Eugene voters on November 4, 2008,
approved the measure.
In the council resolution and the information provided to voters there were specific requirements related
to accountability:
?
In order to promote accountability in the use of bond proceeds, the City Manager will contract
with an outside auditor to prepare a written report on the use of the bond proceeds on a regular
basis. The auditor will ascertain and report on whether the bond proceeds were used for the
authorized purposes and in compliance with the restrictions set forth above. The City Manager
will provide the report to the council and make the report publicly available. (Resolution 4953,
Section H)
?
To further promote accountability and citizen involvement in street preservation projects, the City
Manager has advised that he intends to create a street repair review panel. The street repair review
panel will prepare a report, separate and distinct from the report prepared by the outside auditor,
documenting the City’s use of the bond proceeds and noting whether the bond proceeds were used
in compliance with the terms of this resolution. The City Manager will provide the street repair
review panel’s report to the council and make the report publicly available. (Resolution 4953,
Section I)
Z:\CMO\2010 Council Agendas\M100414\S100414B.doc
Street Repair Review Panel
In October 2009, a citizen group was formed to evaluate the City’s use of the bond proceeds and report
whether the bond funds were used in compliance with the council resolution. The 12 community
members selected to serve on the Street Repair Review Panel were Paul Adkins, John Barofsky, Howard
Bonnett, Dan Brown, Janet Calvert, Paul Holbo, Bob Kline, Steve Lee, Clayton Walker, Gary Wildish,
Bruce Mulligan and Jim Wilcox. The group met three times over a three-month period and also
conducted a physical inspection of the bond measure projects completed in 2009, and those scheduled for
2010.
On January 26, 2010, the Street Repair Review Panel unanimously approved its first-year annual report
(Attachment A), which included the following conclusion:
“Based on the information we received and our subsequent study and discussions, we unanimously
conclude that the bond proceeds were used for the authorized purposes and in compliance with the
limitations and restrictions outlined in Council Resolution 4953, calling the election for the
purpose of referring the bond measure to the voters.” (SRRP 2009 Report, Page 1)
The panel also found that the City was able to complete its 2009 bond measure projects with significant
cost savings due to favorable bids from contractors and, as a result, encouraged the City and the Public
Works Department to accelerate the street repair schedule as much as is reasonable to take advantage of
anticipated continued favorable bidding conditions in the future. Additionally, the panel agreed that
giving the public accurate information as to why some streets get repaired while roads in worse shape do
not get repaired is an ongoing educational issue with city residents.
A web site tracking the bond measure implementation has been established and may be accessed at
www.eugene-or.gov/gobonds. The panel’s 2009 report has been placed on the internet, and links to the
online report have been sent to the Neighborhood Leaders Council. The Street Repair Review Panel is
scheduled to reconvene in fall 2010, upon completion of the 2010 construction season.
Independent Accountant’s Report
The accounting firm of Isler CPA, who also performed the annual audit of the City’s FY09 financial
statements, was contracted to perform sufficient agreed-upon procedures in order to determine whether
the expenditure of G.O. bonds were made in accordance with the purposes and limitations outlined in the
street repair bond resolution – namely, that expenditures were:
1.Used only for costs related to street preservation projects, off-street bicycle and pedestrian path
preservation projects and payment of bond issuance costs, and not to expand the capacity of the
street system; and also,
2.Limited to projects included in Exhibit A to the resolution, unless upon completion of all of the
projects listed in Exhibit A, the council adds other street preservation projects to the list in order
to utilize unspent bond proceeds.
The accountant’s procedures were performed for the period from the date of initial bond issuance
through November 30, 2009, and were conducted in accordance with standards established by the
American Institute of Certified Public Accountants. It was the summary conclusion of the independent
accountant that, “Based on the procedures performed, the bond proceeds were used for the authorized
purposes and in compliance with the restrictions set forth in City Council Resolution No. 4953.”
Z:\CMO\2010 Council Agendas\M100414\S100414B.doc
The Isler CPA 2009 report has been placed on the internet along with the report of the citizen panel at
www.eugene-or.gov/gobonds.
RELATED CITY POLICIES
The council’s goals include “Transportation Initiative: Develop mechanisms to adequately fund our
transportation system for cars, trucks, bikes and pedestrians including maintenance and preservation and
capital reconstruction.”
COUNCIL OPTIONS
This work session is informational; no action is requested.
CITY MANAGER’S RECOMMENDATION
This work session is informational; no action is requested.
SUGGESTED MOTION
This work session is informational; no motion is requested.
ATTACHMENTS
None.
FOR MORE INFORMATION
Contact: Kurt Corey, Public Works Director
Telephone: 541-682-8421
Staff E-Mail: Kurt.A.Corey@ci.eugene.or.us