ISSUE STATEMENT
The purpose of this work session is to provide an update on the City Hall space planning efforts related
to non-police functions located at City Hall. The update includes project scope, transition planning, and
a proposed timeline for accomplishing the objective of consolidating downtown services in a safe,
appropriately-sized facility that will reflect and inspire community pride.
BACKGROUND
Approximately 11 years ago, the council began to address the issue of renovation or replacement of City
Hall. Since then, several planning efforts have included numerous public involvement opportunities for
the community to provide input. Since planning efforts began in 1999, a number of projects have been
undertaken to achieve the goal of replacing City Hall.
In 2000, the 9-1-1 Center was relocated from City Hall to a new building at the 2nd and
Chambers Emergency Services Complex.
In September 2001, the council directed that relocation of EPD personnel from the basement of
City Hall and relocation of Fire Station #1 should be the first priority projects in the Downtown
Space Plan.
The new Police property and forensics building was completed in 2004.
The new Downtown Fire Station, which was funded with General Obligation bonds approved by
voters in May of 2002, was occupied in 2005.
The replacement of City Hall is the next project priority. In July 2007, the City Council directed that the
existing City Hall site be used for the construction of a new City Hall. Since that time the council has
made a couple of other key decisions to address space issues at City Hall:
July 29, 2009, the council authorized the City Manager to negotiate and sign a Purchase and Sale
Agreement for the acquisition, design, and construction and move-in of police services at the 300
Country Club site. The City Manager completed this negotiation and purchase in June 2010.
July 29, 2009, the council directed the City Manager to plan for a future work session with the
council to address moving remaining non-police services out of City Hall.
Z:\CMO\2010 Council Agendas\M100908\S1009082.doc
The acquisition of 300 Country Club for police services has changed the space footprint required to
consolidate a majority of City services located downtown into one site. In addition, it is likely that the
City will continue to occupy existing space in the Atrium Building and on the fourth floor of the Library
for the foreseeable future. The estimated space need for City Hall is approximately 100,000 square feet
depending on what services are located in the facility.
The cost projection to build a new City Hall on the existing site ranges from $40 to $50 million.
Projections are based on estimated space needs of City functions in a range of consolidation options.
Project costs would include demolition of the existing structure and construction of a new building
based on a more compact footprint and efficient layout leaving a good portion of the site as open space
that could be utilized for future expansion.
Ultimately, the level of consolidation will depend upon cost, the benefit derived from collocation of
various services, and consideration of how the building can best be used to serve the public. The City
Hall Master Plan provides a significant amount of detail that can be used to develop a more structured
plan.
Although the council had decided that a new City Hall should be built on the existing site, the council
also subsequently expressed interest in considering the EWEB Administrative Building site for
relocation of City Hall. In May 2009, the council directed staff to send a letter to EWEB to notify them
that city officials wish to have first right of refusal for this site if EWEB decides to sell. To-date, the
City has not received any information from EWEB regarding their intent to sell the facility.
TIMELINE
The functional, structural, and safety issues at City Hall require development of a short-term plan and
timeline to address these problems. In addition to the seismic vulnerability and deteriorating state of the
facility, a primary driver for the replacement of the building is the EWEB steam conversion process
currently scheduled to be complete by June 2012 (although that date could change). Staff will begin
working on plans to vacate City Hall and relocate in temporary space until a permanent City Hall
solution is approved and built. This will address safety concerns while addressing a permanent plan for
the site.
Funding for the City Hall project is one of several major funding priorities to be considered as part of
building a sustainable budget. Consideration of a bond measure for City Hall should take into account
other future bond measures such as street bonds, potential new revenue sources, and other funding
initiatives proposed within the jurisdiction.
If the council adopts the recommended motion, staff will (a) work on plans for the temporary relocation
of City Hall functions consistent with EWEB’s planned steam conversion timeline, and (b) return to the
council with a concept plan for a new City Hall and a proposed financial strategy.
Z:\CMO\2010 Council Agendas\M100908\S1009082.doc
RELATED CITY POLICIES
The City Hall planning process relates to the council goals of an effective, accountable municipal
government, a safe community, and sustainable community growth and change.
COUNCIL OPTIONS
The purpose of this work session is to provide the council with an update on the City Hall planning
process, particularly in light of the acquisition of 300 Country Club Road for police services. This work
session is an opportunity for the council to discuss concerns or thoughts about the proposed approach
and to give direction to the City Manager.
CITY MANAGER’S RECOMMENDATION
The City Manager recommends that the proposed motion be approved.
SUGGESTED MOTION
Move to direct the City Manager to return to the council with a concept plan for City Hall and proposed
financial strategy.
ATTACHMENTS
A. Facility Reserve History
B. City Hall Complex Master Plan Council Action History
FOR MORE INFORMATION
Staff Contact: Kristie Hammitt
Telephone: 541-682-5524
Staff E-Mail: kristie.a.hammitt@ci.eugene.or.us
Z:\CMO\2010 Council Agendas\M100908\S1009082.doc
ATTACHMENT A
FACILITY RESERVE HISTORY
The Facility Reserve was created in FY01 as a way for the organization to save for the repair or
replacement of City Hall and a new Police Facility. The intention was that the organization
could reduce the amount asked from voters to pay for the City Hall projects by saving money in
the Facility Reserve.
Overall, the amount in the Facility Reserve in FY11 is estimated to be $23 million. Below are
brief descriptions of some of the major revenues and expenditures transactions that have
occurred in the Facility Reserve since its creation in FY01.
Major Deposits into the Facility Reserve
Excess EWEB Wholesale CILT:
During FY01, $7.3 million was earned from one-time CILT
payments on wholesale electric sales to California. These funds were deposited into the Facility
Reserve during FY01and FY02.
Settlement of Telecommunications Lawsuits:
In FY05, the City deposited $15.4 million into
the Facility Reserve from the General Fund and the Telecommunications Fund. The revenues
were a result of additional licenses and permits from Qwest and other telecom providers.
Assessment Bond Fund Residual Assets:
In FY03, council reviewed the residual assets
contained in the assessment bond fund reserves and determined how to use the excess funds. At
that time, $2.3 million of the residual assets were deposited into the Facility Reserve to be used
for City Hall complex master plan projects.
Capitalization Component of Facilities Charge:
During FY02, a new component was added to
the Facilities Charge for certain downtown facilities. This charge was developed as a way to
systematically set aside funds for a new City Hall. Both General Fund and Non-General Fund
services have contributed to the Facility Reserve through Facility Capitalization Charges. In
FY10, the charge was suspended for one year, and in FY11, the charge was discontinued
indefinitely.
Other Miscellaneous Revenues:
The City deposited other one-time funds into the Facility
Reserve from time to time. Examples are proceeds from sale of the Olive Street parking lot
($350,000), the library asbestos settlement ($227,000), and return of excess budget for Library
construction project ($100,000).
Major Expenditures from the Facility Reserve
Police Facility:
In FY10, $16 million was appropriated to pay for acquisition and renovation of
a building at 300 Country Club Road that will serve as a new Police Facility. This is part of the
plan to get essential services out of City Hall and into more suitable locations.
Roosevelt Police Building:
In FY02 and FY03, $3.9 million was transferred from the Facility
Reserve to pay for construction of the Forensic Evidence Unit/Property Control Unit facility at
Roosevelt, which allowed police to discontinue using the basement space at City Hall as regular
working areas.
City Hall Master Plan:
Council dedicated approximately $3 million to the City Hall Master
Plan from the Facility Reserve in fiscal years 2006 through 2009.
Lane County Revenue Swap:
In FY09, $4.5 million was transferred to Lane County, so that
the funds could be used to pay for jail beds, prosecution services and other high-priority services.
In return, the County sent $4.5 million from their Road Fund to the City to pay for road
maintenance, repair and construction.
Transportation Utility Fund Transfer:
In FY09 and FY10, the City transferred $1 million
each year from the Facility Reserve to the Transportation Utility Fund to pay for street
maintenance, including pothole patching.
Fire Station #1 Costs:
As part of the financing plan for construction of a new Fire Station #1,
$270,000 was transferred out of the Facility Reserve in FY03 to pay for furnishings, fixtures and
equipment (FF&E). The bulk of the fire station was built with General Obligation bond funds
approved by voters, but the FF&E costs are not eligible for General Obligation Bond funding.
General Fund Budget Gap:
In FY04, $900,000 was transferred from the Facility Reserve to
fill a budget gap in the General Fund.
Other Miscellaneous Expenditures
: Facility Reserve contributions were also used to pay for
the LRCS Master Plan ($130,000), the EPD PERF Study ($35,000), and homeless prevention
services ($150,000).
ATTACHMENT B
City Hall Complex Master Plan
Council Action History
Council Actions
On May 25, 2005, the council approved the City Hall/Police Building Action Plan (subsequently
renamed the City Hall Complex Action Plan) which identifies the major policy issues to be
addressed, the overall description of project phasing, the nature of work to be accomplished,
resource needs and proposed project outcomes associated with the City Hall Complex Master
Plan.
On October 19, 2005, a consultant team led by Thomas Hacker Architects facilitated a council
workshop for the purpose of identifying and providing direction on policy issues relevant to the
City Hall Complex. Based on pre-workshop interviews with the mayor and council, six project
values were presented by the consultant team to which three additional project values were pro-
posed by council members during the workshop. In addition, eight key issues and five sub-
issues emerged from pre-workshop interviews with the mayor and council, and were presented
during the workshop.
At the November 23, 2005 work session, the council adopted the following project values to
serve as a basis for future decision making:
1.Exercise fiscal responsibility
2.Produce government efficiency
3.Be user-friendly
4.Embody environmental stewardship
5.Enhance downtown
6.Inspire civic pride
7.Maximize use of City Hall public spaces by the public and access to government and its
representatives
8.Strive for simplicity
9.Plan for the future
In addition, position statements on the four issues with the highest degree of consensus were
adopted as follows:
1.Incorporate meaningful sustainable design goals.
2.Utilize a long-term planning horizon of 25 years.
3.Consolidate City services to the greatest practical extent.
4.Develop the project in consideration of the Downtown Plan while not limiting location
th
choices to 8 Avenue.
At the December 14, 2005 work session, the council directed the City Manager to proceed with
phase 2—the Development Plan Phase—of the City Hall Complex Action Plan for $1,135,000.
This phase includes the technical work and public input required to generate an overall develop-
ment plan for the City Hall Complex. This phase will also resolve the remaining policy issues
from phase 1 and result in a concept plan for the City Hall Complex.
On March 8, 2006, the consultant team facilitated a council workshop marking the beginning of
the Development Plan Phase of this project. The purpose of the workshop was to discuss pre-
liminary space needs assumptions, facility implications relative to police service delivery
options, proposed site evaluation criteria, and emerging issues from citizen interviews, as well as
to preview the first Community Forum. Results from this workshop provided the basis for the
Forum.
At the April 26, 2006 work session, the council adopted three different Police consolidation
options for use in ongoing planning efforts related to the City Hall Complex: Option B that con-
solidates all Police functions with the rest of City Hall on a single site; Option C that consoli-
dates all Police functions except patrol with the rest of City Hall and provides for a separate
patrol facility nearby; and Option D that consolidates all Police functions except patrol with the
rest of City Hall and provides for a separate patrol facility in a more remote location outside the
downtown area.
On May 10, 2006, the consultant team facilitated a council workshop that introduced the City
Hall Space Requirements Program, presented Renovate, Hybrid, and New options for City Hall,
and previewed the second Community Forum which took place on May 25, 2006. Results from
this workshop provided the basis for the Forum.
At the July 19, 2006 work session, the council adopted new construction as the preferred option
for future planning and design of the City Hall Complex rather than renovating the existing city
hall building or doing a hybrid of renovation and new construction. This action reflected a
majority of support at the Community Forum for construction of a new City Hall.
On August 9, 2006, the consultant team facilitated a council workshop to discuss and refine the
site evaluation criteria for potential sites related to a new City Hall Complex and then apply the
criteria to specific sites. The consultant team also received direction from the council on elicit-
ing public input during the third Community Forum held on August 24, 2006. Results from this
workshop provided the basis for the Forum.
At the September 20, 2006 work session, the narrowed down to two the number of sites to be
carried forward for use in developing concept designs for a new City Hall. The two sites
selected were the existing City Hall site and the Butterfly Lot/Rock N Rodeo sites. This action
reflected a majority of support for these two sites at the Community Forum, while also acknowl-
edging that a third preferred site—the former Sears—might be a viable site if development plans
for that site do not move forward.
On October 18, 2006, the consultant team facilitated a council workshop to introduce to the
council principles of architectural design and urban planning that will guide the concept design
options for City Hall, discuss factors that will influence decisions about police consolidation and
site, and preview the fourth and final community forum. Results from the workshop provided
the basis for the Forum.
At the November 20, 2006 work session, the council voted to proceed with planning for a new
city hall with police patrol in a separate facility. Then at the December 11, 2006 work session,
the council selected the Butterfly Lot/Rock N Rodeo site for use in schematic design and other
planning for a new city hall. This marked the completion of Phase 2, the Development Plan
Phase, of the City Hall Complex Master Plan. Both of these council actions reflected the major-
ity opinion from the Community Forum.
At the February 14, 2007 work session, the council requested the Design Team to perform
statistical public opinion research to inform future work. The research was intended to
understand what elements of a new city hall mattered most to voters and test the initial level of
voter support.
At the June 20, 2007 workshop, the Project Team introduced public opinion research,
consolidation options, and a conceptual scope of work for the remainder of the Implementation
Plan Phase. At that time the council requested additional information on the costs of the police
patrol facility, escalated relocation and leasing costs, comparison costs for leasing and
purchasing space in the Federal Building, potential City Hall sites other than the existing City
Hall and the Rock N’ Rodeo/Butterfly sites, deed restrictions related to the Butterfly Lot site, and
costs for the remaining Implementation Plan Phase scope of work.
At the July 20, 2007 work session, the council decided to continue master planning efforts for a
new City Hall.
At the September 26, 2007 workshop, the project team introduced the Police Patrol Facility site
selection analysis, City Hall design progress showing concept options with and without patrol
functions, and cost models for police patrol facilities on generic sites downtown, out of down-
town, and at a new City Hall. Council requested additional information on site ownership,
availability, and owners’ willingness to sell.
At the October 17, 2007 work session the council voted to proceed with development of a Police
Patrol Facility concept design for site E, a portion of Land Transit District’s RideSource site, lo-
nd
cated near the intersection of Garfield Street and West 2 Avenue. The council also voted to
continue to explore acquisition of sites E and F. The council will receive an update on the status
of acquisition efforts at the December 12 workshop.
At the November 28, 2007 work session, council voted to proceed with planning for a City
Hall/Police Patrol Facility based tentatively on a 2010 ballot measure.
At the December 12, 2007 workshop the council reviewed multiple options on City Hall concept
designs and provided feedback that shaped the development of a single concept design. The
council also reviewed Police Patrol Facility plans and costs and requested more refined cost
analysis.