Action: Ratification of the Metropolitan Wastewater Management Commission
(MWMC) FY12 Regional Wastewater Program Budget and
Capital Improvements Program
Meeting Date: May 23, 2011 Agenda Item Number: 3
Department: Public Works Staff Contact: John Huberd
www.ci.eugene.or.us Contact Telephone Number: 541-682-8603
ISSUE STATEMENT
This agenda item relates to the ratification of the FY12 budget for the regional wastewater program
serving the Eugene/Springfield metro area, as established under the 1977 Intergovernmental Agreement
(IGA) between the City of Eugene, the City of Springfield, and Lane County. The regional wastewater
program is managed by the Metropolitan Wastewater Management Commission (MWMC) pursuant to
the provisions of the IGA. The regional Wastewater budget provides funds for all regional operations,
maintenance, administration, and capital project management and implementation for regional facilities.
These include the Eugene/Springfield Water Pollution Control Facility, the Biosolids Management
Facility, the Biocycle Farm, the Reclaimed Water Facility, and regional wastewater pump stations.
BACKGROUND
The purpose of the regional wastewater program is to protect public health and safety and the
environment by providing high quality wastewater management services to the Eugene/Springfield
metropolitan area. The MWMC and the regional partners are committed to providing these services in a
manner that
will achieve, sustain, and promote balance between community, environmental, and economic
.
needs while meeting customer service expectations
Since the mid-1990’s the commission and the regional wastewater program staff have worked together
to identify the following key outcomes:
1.High environmental standards.
2.Fiscal management that is effective and efficient.
3.A successful intergovernmental partnership.
4.Maximum reliability and useful life of regional assets and infrastructure.
5.Public awareness and understanding of MWMC, the regional wastewater system, and MWMC’s
objectives for maintaining water quality and a sustainable environment.
These key outcomes and goals are in direct alignment with the City of Eugene City Council goals.
Every year MWMC develops a budget that covers resource needs of the operations, maintenance, and
capital improvement activities for the regional wastewater program. These activities are divided
between Eugene and Springfield. The regional budget combines the portions of the City of Eugene and
City of Springfield budgets that are dedicated to the regional wastewater program. The commission
conducted a public hearing on the proposed draft budget for FY12 and subsequently adopted the budget
\\Cesrv500\cc support\CMO\2011 Council Agendas\M110523\S1105233.doc
on April 8, 2011. The commission’s adopted budget is attached for council consideration (see
Attachment A). The budget reflects the continuing focus on design and construction of capital
improvements in the approved 2004 Facilities Plan, needed to ensure that the operation of the Regional
Wastewater Facilities meets increasing environmental regulations and the collection and treatment
capacity will be available to provide for growth in the service area. The adopted budget includes the
financial resources necessary to support the regional program. The personnel, operations and
maintenance budget increases by 3.7 percent from the FY11 budget. The capital budget decreases in
FY12 due to the recent completion of several major capacity expansion projects at the treatment plant.
During the April 8 meeting, the commission approved an overall four percent increase in the regional
wastewater user rates to generate revenue for the proposed budget and, pursuant to the recommendations
of the MWMC financial advisor, to address needs for future Capital Improvement Program (CIP)
financing consistent with the commission’s Financial Plan policies and net revenue objectives. The
revenues generated by the user rate increase are consistent with the MWMC's approved financial plan to
maintain an unenhanced credit rating of A and adequately fund operations, administration, capital
financing, debt service, and reserves.
RELATED CITY POLICIES
This action item is related to the City Council goals of "Sustainable Development", "Effective,
Accountable, Municipal Government" and “Fair, Stable and Adequate Financial Resources.”
COUNCIL OPTIONS
1. Approve motion to ratify the FY12 MWMC budget.
2. Return the FY12 MWMC Regional Wastewater Program Budget and Capital Improvements
Program to MWMC with specific requests for modification and reconsideration.
CITY MANAGER’S RECOMMENDATION
The City Manager recommends that the council ratify the proposed FY12 MWMC Budget and Capital
Improvements Program.
SUGGESTED MOTION
Move to ratify the FY12 MWMC Budget.
ATTACHMENTS
A. Transmittal letter and MWMC FY12 Proposed Regional Wastewater Program Budget and Capital
Improvements Program
FOR MORE INFORMATION
Staff Contact: John Huberd, Finance and Administration Manager, Wastewater Division
Telephone: 541-682-8603
Staff E-Mail: john.c.huberd@ci.eugene.or.us
\\Cesrv500\cc support\CMO\2011 Council Agendas\M110523\S1105233.doc
PARTNERS IN
WASTEWATER
MANAGEMENT
www.mwmcpartners.org
April 27, 2011
MWMC
Commission
Mr. Jon Ruiz, City Manager
City of Eugene
Bill Inge
Lane County Citizen
777 Pearl Street
MWMC President
Eugene, OR 97401
Walt Meyer
Eugene Citizen
MWMC Vice-President
Subject: Metropolitan Wastewater Management Commission (MWMC)
FY 11-12 Regional Wastewater Program (RWP) Budget and
George Brown
Eugene City Councilor
Capital Improvements Program (CIP)
Jay Bozievich
Dear Mr. Ruiz:
Lane County
Commissioner
On April 8 the MWMC held a public hearing on the FY 11-12 Regional
Hilary Loud
Wastewater Program (RWP) Budget and Capital Improvements Program
Eugene Citizen
(CIP). At this meeting, the FY 11-12 RWP Budget and CIP were approved.
Doug Keeler
The RWP Budget funds operating and capital project requirements, and
Springfield Citizen
maintains targeted contributions to reserves.
Marilee Woodrow
Springfield City Councilor
Consistent with the Intergovernmental Agreement, the RWP Budget and
CIP need to be ratified by the governing bodies of Eugene, Springfield and
Lane County prior to final adoption by MWMC. Please forward the enclosed
Administration
budget and CIP documents to the Eugene City Council for their
consideration on May 23, 2011. If I can be of any additional assistance,
Ron Bittler
please contact me at 541-744-4170.
Environmental Services/
MWMC General Manager
Thank you for your consideration and assistance in this matter.
City of Springfield
225 Fifth Street
Springfield, Oregon 97477
Sincerely,
(541) 726-3694
FAX (541) 726-2309
ëûÔÉÉÑØË
Operations
Ron Bittler
MWMC General Manager
Michelle Cahill
Director of Wastewater Div
City of Eugene
410 River Avenue
Eugene, Oregon 97404
(541) 682-8600
FAX (541) 682-8601
REGIONAL WASTEWATER PROGRAM
BUDGET
and
CAPITAL IMPROVEMENTS PROGRAM
FY 11-12
The Metropolitan Wastewater Management Commission adopted its Operating Budget and Capital
Improvements Program (CIP) for FY 11-12 April XX, 2011. The Budget and CIP were ratified by the
Springfield City Council on May XX, 2011, the Eugene City Council on May XX, 2011, and the Lane
County Board of Commissioners on May XX, 2011. The Commission gave final ratification to the
.
budget and CIP on June XX, 2011
COMMISSION MEMBERS:
Doug Keeler, President (Springfield)
Bill Inge, Vice-President (Lane County)
Marilee Woodrow (Springfield)
George Brown (Eugene)
Walt Meyer (Eugene)
Jay Bozievich (Lane County)
Hilary Loud (Eugene)
STAFF:
Susie Smith, MWMC Executive Officer/Springfield Public Works Director
Ron Bittler, MWMC General Manager/Springfield Environmental Services Manager
Michelle Cahill, Eugene Wastewater Division Director
Robert Duey, MWMC Finance Officer/Springfield Finance Director
METROPOLITAN WASTEWATER MANAGEMENT COMMISSION
ADOPTED FY 11-12 BUDGET AND CAPITAL IMPROVEMENTS PROGRAM
for the
REGIONAL WASTEWATER PROGRAM
TABLE OF CONTENTS
Budget Message ..................................................................................................................... 1
Regional Wastewater Program Overview ..............................................................................
3
Exhibit 1: Interagency Coordination Structure ...............................................................
9
Regional Wastewater Program
Budget and Program Summary ................................................... 10
Exhibit 2: Regi
onal Operating Budget Summary ..................................................................... 10
Exhibit: Lin
3e Item Summary by Program Area ...................................................................... 12
Exhibit: Budget Summary and Comparison ................................................................
413
Regional Wastewater Program Staffing .................................................................................
17
Exhibit: Regional Wastewater
5 Program Organizational Chart ............................................ 17
Exhibit: Regional Wastew
6ater Program Position Summary ................................................. 18
Regiona
l Wastewater Program Reserves ........................................................................................... 20
Exhibit:
7 Operating Reserves - Line Item Budget .................................................................... 21
BUDGET APPENDICES
Appendix A: Springfield
Program and Budget Detail ................................................................... 25
Exhibit: Springfield Administrati
8on Program Budget Summary ........................................ 28
Exhibit: Springfield Adm
9inistration Line Item Summary .................................................... 29
Appendix B: Eug
ene Program and Budget Detail ........................................................................... 30
Exhibit 1: Eugene
0 O & M Program Budget Summary ........................................................... 35
Exhibit 1: Eugene Adm
1inistration Line Item Summary ........................................................ 36
Capital Improvements Programs ......................................................................................................... 37
Exhibit 12: Capital Programs – Adopted Capital Improvements Program Projects.................... 41
Exhibit 13: Capital Programs 5-Year Plan .................................................................................. 42
Regional Wastewater Capital Program Project Sheets ....................................................................... 47
Metropolitan Wastewater Management Commission Budget Message
BUDGET MESSAGE
To the Metropolitan Wastewater Management Commission:
I am pleased to present the Metropolitan Wastewater Management Commission’s (MWMC) budget for
fiscal year (FY) 2011-12. This budget funds operations, administration, and capital projects planned for
the Regional Wastewater Program (RWP). The MWMC administration and Capital Improvements
Program (CIP) components of the budget are reflected in the City of Springfield’s RWP budget. The
operations, maintenance, equipment replacement, and major rehabilitation components are reflected in
the City of Eugene’s RWP budget. The Cities’ Industrial Pretreatment Programs, managed locally in
compliance with the MWMC Model Ordinance, also are included in the RWP budget.
This year’s budget reflects a continued focus on design and construction of capital improvements
planned to ensure that operation of the Regional Wastewater Facilities meets environmental regulations,
and that adequate capacity will be provided to meet the needs of a growing service area. The FY 11-12
capital budget and FY 11-12 – FY 15-16 capital improvements work plan, which are included in this
budget document, are derived from the 2004 MWMC Facilities Plan. The budgeted amount for FY 11-
12 Facilities Plan capital improvement projects is $25,932,282; $4,345,577 is carryover from unfinished
projects budgeted in FY 10-11, and $1,586,7054, is new funding programmed in FY 11-12. The FY 11-
12 capital budget also includes Equipment Replacement, Major Rehabilitation and Major Capital Outlay
capital projects, budgeted at $720,355, $507,400 and $275,000 respectively. The total capital budget for
FY 11-12 is approximately $27,435,037. Approximately $10 million of the total capitalbudget will not
be spent in FY 11-12, but is included to enable contracts for construction that will occur in FY 11-12.
Unspent funds will be carried forward to the FY 12-13 budget as appropriate. In order to fund the actual
cash flow requirements of the FY 11-12 CIP, the Commission will use State Revolving Fund (SRF)
loans as well as strategic draw downs of capital reserves.
The FY 11-12 RWP Operating Budget for Personnel Services, Materials and Services and Capital
Outlay expense is $15,722,799. Consistent with the Commission’s Financial Plan and policies, the FY
11-12 budget maintains and uses several reserves, which are fully described in this budget document.
Finally, the FY 11-12 budget includes debt service payments totaling $8,518,080 as scheduled for
repayment of $47.3 million of revenue bonds issued in November 2006, and an additional $52.7 million
in borrowing in FY 08-09 to fund the Facilities Plan capital improvements.
Revenue sources necessary to fund Operations, Capital programs, debt service requirements and
reserves include user charges, system development charges (SDCs), interest earnings and a small
amount of miscellaneous revenues. For FY 11-12 user fee revenues (including septage service and SDC
Compliance Charge) are projected at $27,160,427. This level of revenue is projected based on a 4%
increase in regional wastewater user fees, as recommended by the MWMC financial advisor in order to
meet the Commission’s Financial Plan policies and net revenue objectives. Projected SDC revenues are
projected at approximately $589,281.
In summary, the projected FY 11-12 budget funds operations and administration sufficiently to maintain
existing levels of service, and to meet the environmental performance and other legal obligations of the
Commission. It funds Capital Programs at a level necessary to implement the 2004 Facilities Plan
Page 1 DRAFT FY 11-12 BUDGET AND CIP
Metropolitan Wastewater Management Commission Budget Message
objectives for compliance with the National Pollutant Discharge Elimination System (NPDES) permit
issued to MWMC and the two Cities. Finally, this budget implements the Commission’s adopted
Financial Plan policies regarding reserves, asset management, and capital financing.
* Includes three equipment replacement contributions totaling $782,564, a Capital Reserve contribution of
$8,354,604, $16,884 from Reimbursement SDC Compliance Charge to Operating and $6,409,596 transfers
from Operating and Improvement SDCs to finance debt service.
** In governmental budgeting, projects are fully budgeted in the fiscal year in which the contract is awarded.
At the end of each fiscal year, unspent funds are carried forward until the project is completed. This
provides budget appropriations necessary for MWMC to commit to contracts that span more than one fiscal
year. Therefore, although the budgeted amount in the capital budget for FY 11-12 is $27,435,037, which
includes Equipment Replacement, Major Rehab and Major Capital Outlay totaling $1,502,755, the capital
project spending for FY 11-12 is only expected to total about $9,920,259.
*** Because all capital projects for which contracts will be awarded in FY 11-12 must be fully budgeted in FY
11-12, the revenue requirements, and in this case, any necessary borrowing, must also be shown in the
budget year.
Respectfully submitted,
Susie Smith,
MWMC Executive Officer
Page 2 DRAFT FY 11-12 BUDGET AND CIP
Metropolitan Wastewater Management Commission Overview
REGIONAL WASTEWATER PROGRAM
OVERVIEW
The Metropolitan Wastewater Management Commission
The MWMC was formed by Eugene, Springfield, and Lane County through an intergovernmental
agreement (IGA) in 1977 to provide wastewater collection and treatment services for the Eugene-
Springfield metropolitan area. The seven-member Commission is composed of members appointed by
the City Councils of Eugene (3 representatives), Springfield (2 representatives), and the Lane County
Board of Commissioners (2 representatives). Since its inception, the Commission, in accordance with the
IGA, has been responsible for oversight of the RWP including: construction, maintenance, and operation
of the regional sewerage facilities; adoption of financing plans; adoption of budgets, user fees and
connection fees; adoption of minimum standards for industrial pretreatment and local sewage collection
systems; and recommendations for the expansion of regional facilities to meet future community growth.
Staffing and services have been provided in various ways over the 34 years of MWMC’s existence.
Since 1983, the Commission has contracted with the Cities of Springfield and Eugene for all staffing and
services necessary to maintain and support the RWP. Lane County’s partnership has involved
participation on the Commission and support to the Lane County Metropolitan Wastewater Service
District (CSD), which managed the proceeds and repayment of general obligation bonds issued to
construct RWP facilities.
Regional Wastewater Program Purpose and Key Outcomes
The purpose of the RWP is to protect public health and safety and the environment by providing high
quality wastewater management services to the Eugene-Springfield metropolitan area. The MWMC and
the regional partners are committed to providing these services in a manner that will achieve, sustain, and
promote balance between community, environmental, and economic needs while meeting customer
service expectations. Since the mid-1990s, the Commission and RWP staff have worked together to
identify key outcome areas within which to focus annual work plan and budget priorities. The FY 11-12
RWP work plans and budget reflect a focus on the following key outcomes or goals.
In carrying out the daily activities of managing the regional wastewater system, we will strive to achieve
and maintain:
1.High environmental standards;
2.Fiscal management that is effective and efficient;
3.A successful intergovernmental partnership;
4.Maximum reliability and useful life of regional assets and infrastructure;
5.Public awareness and understanding of MWMC, the regional wastewater system, and
MWMC’s objectives for maintaining water quality and a sustainable environment.
The Commission believes that these outcomes, if achieved in the long term, will demonstrate
success of the RWP in carrying out its purpose. In order to determine whether we are successful,
indicators of performance and targets have been identified for each key outcome. Tracking
performance relative to identified targets over time assists in managing the RWP to achieve
desired results
. The following indicators and performance targets provide an important framework for
the development of the FY 11-12 RWP Operating Budget, Capital Improvements Program and associated
work plans.
Page 3 DRAFT FY 11-12 BUDGET AND CIP
Metropolitan Wastewater Management Commission Overview
Outcome 1:
Achieve and maintain high environmental standards.
Indicators:Performance:
FY09-10 FY 10-11 FY 11-12
Actual Estimated Actual Target
100 %; 10.9 100 %; 12.0 100 %; 13.0
Amount of wastewater treated to
billion gallons billion gallons billion gallons
water quality standards
Compliance with environmental
performance requirements of all
100% compliance 100% compliance 100% compliance
permits
<50% EPA <50% EPA <50% EPA
MWMC target for high quality
biosolids
40CFR Part 40CFR Part 40CFR Part 503.13
503.13 -Table 3 503.13 -Table 3 -Table 3
PollutantPollutantPollutant
Concentrations:Concentrations:Concentrations:
Policy Met Policy Met Policy Met
Volume of reclaimed water
55.2 million 60 million
60 million gallons
beneficially reused (million gallons)
gallonsgallons
75% of 100% of 100% of
Performance targets under the
Environmental Management System
numeric EMS numeric EMS
numeric EMS
are achieved
targets met or on targets met or on targets met or on
schedulescheduleschedule
Outcome 2:
Achieve and maintain fiscal management that is effective and efficient.
Indicators:Performance:
FY09-10 FY 10-11 FY 11-12
Actual Estimated Actual Target
Policies Met Policies Met Policies Met
Annual Budget and Rates meet
MWMC Financial Plan Policies
Clean Audit Clean Audit Clean Audit
Annual audited financial statements
AA- AA- A
Uninsured Bond Rating
yes yes yes
Reserves Funded at Target Levels
1.92 >1.25 >1.25
Net Revenue to Debt Service coverage
ratio
Outcome 3:
Achieve and maintain a successful intergovernmental partnership.
Indicators:Performance:
FY09-10 FY 10-11 FY 11-12
Actual Estimated Actual Target
Industrial Pretreatment Program—
Implementation in compliance with
100% 100% 100%
State/Federal requirements; any
Page 4 DRAFT FY 11-12 BUDGET AND CIP
Metropolitan Wastewater Management Commission Overview
required corrections completed
WWFMPContinuation of Wet weather
Wet Weather Flow Management Plan
(WWFMP) implemented (MWMC
provisionswet weather planning
portion – treatment plant upgrades)
implemented planning, draft document
and updated in a timely manner
framework complete
completed
100% of capacity
MWMC Facilities Plan projects
100% of initiated 100% of initiated
consistent with CIP budget and
related project
projects within projects within
schedule
substantially
budget and on budget and on
complete by
scheduleschedule
December 31,
2009
Outcome 4:
Maximize reliability and useful life of regional assets and infrastructure.
Indicators:Performance:
FY09-10 FY 10-11 FY 11-12
Actual Estimated Actual Target
Preventive maintenance completed
95% 95% 90%
on time (best practices benchmark is
90%)
Preventative maintenance to
4.1:1 4:1 5:1
corrective maintenance ratio
(benchmark 4:1-6:1)
Emergency maintenance required
0.9% 1.0% <2% of labor
(best practices benchmark is <2% of
hours
labor hours)
Page 5 DRAFT FY 11-12 BUDGET AND CIP
Metropolitan Wastewater Management Commission Overview
Outcome 5:
Achieve and maintain public awareness and understanding of MWMC, the regional
wastewater system, and MWMC’s objectives for maintaining water quality and a sustainable
environment.
Indicators:Performance:
FY09-10 FY 10-11 FY 11-12
Actual Estimated Actual Target
Produced Produced Produce
MWMC Annual Report
Develop new MWMC
---Complete
Communication Plan
---
Create and distribute e-newsletters
------2Newsletters
Interpretive Signs at Wastewater
---Project Delayed Complete
Pollution Control Facility
Complete initial recycled water
------Complete
marketing efforts
Redesign existing MWMC Website
---Complete ---
Facilities Plan Milestone Open House
---Complete ---
Establish framework for Pollution
---Complete ---
Prevention Plans
Page 6 DRAFT FY 11-12 BUDGET AND CIP
Metropolitan Wastewater Management Commission Overview
Roles and Responsibilities
In order to effectively oversee and manage the RWP, the partner agencies provide all staffing and services
to MWMC. The following sections describe the roles and responsibilities of each of the partner agencies,
and how intergovernmental coordination occurs on behalf of the Commission.
City of Eugene
The City of Eugene supports the RWP through representation on MWMC, provision of operation and
maintenance services, and active participation on interagency project teams and committees. Three of the
seven MWMC members represent Eugene--two citizens and one City Councilor. Pursuant to the IGA,
the Eugene Wastewater Division operates and maintains the Regional Water Pollution Control Facility
(WPCF), the Biosolids Management Facility (BMF) and associated residuals and reclaimed water
activities, along with regional wastewater pumping stations and transmission sewers. In support of the
RWP, the Division also provides technical services for wastewater treatment; management of equipment
replacement and infrastructure rehabilitation; biosolids treatment and recycling; industrial source control
(in conjunction with Springfield staff); and regional laboratory services for wastewater and water quality
analyses. These services are provided under contract with MWMC through the regional funding of 76.30
FTE.
City of Springfield
The City of Springfield supports the RWP through representation on MWMC, provision of MWMC
administration services, and active coordination of and participation on interagency project teams and
committees. Two MWMC members represent Springfield--one citizen and one City Councilor. Pursuant
to the IGA, the Springfield Public Works Director and the Environmental Services Manager serve as the
MWMC Executive Officer and General Manager, respectively. The Environmental Services Division and
Finance Department staff provide ongoing staff support to the Commission and administration of the
RWP in the following areas: legal and risk management services; financial management and accounting;
coordination and management of public policy; regulatory and permit compliance issues; coordination
between the Commission and the governing bodies; long-range capital project planning, design, and
construction management; coordination of public information, education, and citizen involvement
programs; and coordination and development of regional budgets, rate proposals, and revenue projections.
Springfield staff also provides local implementation of the Industrial Pretreatment Program, as well as
billing coordination and customer service. These services are provided under contract with MWMC
through the regional funding of 15.8 FTE of Public Works Department staff and .88 FTE of Finance
Department staff, as reflected in the adopted FY 11-12 budget.
Lane County
Lane County supports the RWP through representation on MWMC, and by maintaining the CSD when in
use. Two MWMC members represent Lane County--one citizen and one County Commissioner. The
Board of County Commissioners oversees the CSD, including administration of local General Obligation
(GO) bond proceeds and governance of the District. The District was formed, under agreement with
MWMC and the partner agencies, to enable long-term financing of regional facilities through issuance of
GO bonds. The CSD adopts an annual budget for CSD funds, which is separate from the MWMC budget.
The GO bond debt, which was retired in August, 2002, was repaid by CSD through an annual property
tax assessment for Eugene and Springfield properties. Sewer users in the unincorporated areas such, as
the River Road/Santa Clara area, contributed to bond repayment through an “in-lieu-of-tax charge”
Page 7 DRAFT FY 11-12 BUDGET AND CIP
Metropolitan Wastewater Management Commission Overview
(ILOTC). Because the bond debt has been fully repaid, property tax assessments and ILOTC payments
are no longer being assessed.
Interagency Coordination
The effectiveness of MWMC and the RWP depends on extensive coordination, especially between
Springfield and Eugene staff, who provide ongoing program support. This coordination occurs in several
ways. The Springfield ESD/MWMC General Manager and the Eugene Wastewater Division Director
coordinate regularly to ensure adequate communication and consistent implementation of policies and
practices as appropriate. The Eugene and Springfield Industrial Pretreatment Program supervisors and
staff meet regularly to ensure consistent implementation of the Model Industrial Pretreatment Ordinance.
Additionally, interagency project teams provide input on and coordination of ongoing MWMC
administration issues and ad hoc project needs.
Exhibit 1 on the following page reflects the interagency coordination structure supporting the RWP.
Special project teams are typically formed to manage large projects such as design and construction of
new facilities. These interagency staff teams are formulated to provide appropriate expertise, operational
knowledge, project management, and intergovernmental representation.
Relationship to Eugene and Springfield Local Sewer Programs
The RWP addresses only part of the overall wastewater collection and treatment facilities that serve the
Eugene-Springfield metropolitan area. The Cities of Eugene and Springfield both maintain sewer
programs that provide for construction and maintenance of local collection systems and pump stations,
which discharge to the regional system. Sewer user fees collected by the two cities include both local and
RWP rate components.
Page 8 DRAFT FY 11-12 BUDGET AND CIP
Metropolitan Wastewater Management Commission Overview
EXHIBIT 1
Page 9 DRAFT FY 11-12 BUDGET AND CIP
Metropolitan Wastewater Management Commission Budget and Program Summary
REGIONAL WASTEWATER PROGRAM
FY 10-11 BUDGET
The MWMC’s RWP Operating Budget provides the Commission and governing bodies with an integrated
view of the RWP elements. Exhibit 2 provides a summary of the overall Operating Budget. Separate
Springfield and Eugene agency budgets and staffing also are presented within this budget document.
Major program areas supported by Springfield and Eugene are described in the pages that follow and are
summarized in Exhibit 3 on page 12. Finally, Exhibit 4 on page 13 combines revenues, expenditures, and
reserves to illustrate how funding for all aspects of the RWP is provided. It should also be noted that the
“Amended Budget FY 10-11” column in all budget tables represents the updated FY 10-11 RWP budget
as of February 11, 2011 which reconciled actual beginning balances at July 1, 2010, and approved budget
transfers and supplemental requests.
Notes:
1.The Change column and Percent Change column compare the adopted FY 11-12 budget with the originally
Adopted FY 10-11 Budget column.
2.Personnel Services, Materials and Services, and Capital Outlay budget amounts represent combined
Springfield and Eugene Operating Budgets that support the RWP.
3.Capital Outlay does not include CIP, Equipment Replacement, Major Capital Outlay, or Major
Rehabilitation, which are capital programs.
Page 10 DRAFT FY 11-12 BUDGET AND CIP
Metropolitan Wastewater Management Commission Budget and Program Summary
4.The Equipment Replacement Contribution is a budgeted transfer of operating revenues to “sinking funds”
(reserves) for scheduled future replacement of major equipment, vehicles, and computers. See table on page
22 for year-end balance.
5.The Capital Reserve Contribution is a budgeted transfer of operating revenues to “sinking funds” (reserves).
Capital is passed through the Springfield Administration Budget. See table on 24-end balance.
6.The Working Capital Reserve acts as a revolving account which is drawn down and replenished on a
monthly basis to fund Eugene’s and Springfield’s cash flow needs.
7.The Rate Stability Reserve is used to accumulate revenues available at year-end after the budgeted
Operating Reserve target is met. It is budgeted based on projected revenues and expenditures and is
intended to lessen the size of needed rate increases over time. See Exhibit 7 on page 21 for year-end
balance.
8.The Operating Reserve is used to account for the accumulated operating revenues net of operations
expenditures. The Commission has adopted a policy of maintaining a minimum Operating Reserve balance
approximately equal to 10% of the adopted Operating Budget. This targeted level of funding provides for
contingency funds in the event unanticipated expenses or revenue shortfalls occur during the budget year.
9.The Debt Service line item is the sum of annual interest and principal payments on the Revenue Bonds and
SRF loans made from the Operating Budget (derived from user rates). The total amount of debt service
budgeted in FY 11-12 is $5,215,576, the balance of which is budgeted from SDCs.
10.The Rate Stabilization Reserve was established as a result of the 2006 MWMC Revenue Bond Declaration
and Covenants. It holds funds that are available if needed, to ensure debt service payments can be made.
11.The SRF loan reserve is budgeted as required per loan agreements
12.The Revenue Bond Reserves are established to cover the 2006 bond ($4 million), the 2008 bond issue ($4.1
million).
Page 11 DRAFT FY 11-12 BUDGET AND CIP
Metropolitan Wastewater Management Commission Budget and Program Summary
Page 12 DRAFT FY 11-12 BUDGET AND CIP
Metropolitan Wastewater Management Commission Budget and Program Summary
Notes
: * The Change (Inc/Decr) column compares the adopted FY 11-12 budget to the originally adopted FY 10-11 budget column.
Page 13 DRAFT FY 11-12 BUDGET AND CIP
Metropolitan Wastewater Management Commission Budget and Program Summary
OPERATING BUDGET AND RATE HISTORY
The graphs on pages 15 and 16 show a 5-year Regional Operating Budget Comparison and Regional
Residential Sanitary Sewer costs over a fourteen-year period. Because the Equipment Replacement and
Major Infrastructure Rehabilitation programs are managed in the Eugene Operating Budget, these
programs are incorporated into both the 5-year Regional Operating Budget Comparison graph on page 16
and the 5-Year Capital Programs graph on page 42. The Regional Wastewater Capital Improvement
Programs graph on page 16 shows the expenditures in the MWMC’s Capital Program over the past five
years.
As shown on the Regional Residential Sanitary Sewer Rate graph, regional sewer user charges remained
highly stable through 2004. During the late 1990s, considerable efforts were made by MWMC to absorb
increased costs due to inflation and service level increases through improvements in organizational
efficiency and effectiveness. However, as the Regional Wastewater Facilities approached the end of their
original design lives, and increased regulatory requirements emerged, MWMC completed a
comprehensive update to its Facilities Plan in 2004. This Plan demonstrated the need for a significant
capital investment in new and expanded facilities to meet environmental performance requirements and
capacity to serve the community through 2025. Although a portion of these capital improvements can be
funded through system development charges (SDCs), much of the funding for approximately $196 million
(in 2006 dollars) in capital improvements over the twenty-year period will come from user charges. Since
2004, this has become the major driver of MWMC’s need to increase sewer user rates on an annual basis.
In FY 08-09, there was an 11% user rate increase over FY 07-08 rates applied uniformly across all user
classes. This rate increase provided adequate revenue to meet current bond covenants and meet
requirements to issue $50.7 million in bonds in FY 08-09.
In October of 2008, the Commission adopted an interim user rate increase of 7% due to the closure of
Hynix Semiconductor. This increase was necessary to issue new revenue bonds and maintain bond
covenants for existing bonds. The typical residential monthly wastewater bill (based on 5,000 gallons of
usage) increased an additional $1.10 per month and went into effect on December 1, 2008.
The FY 09-10 RWP operating budget was based on an 18% user rate increase over FY 08-09 rates applied
uniformly across all user classes. This rate provided for Operations, Administration, Capital programs,
reserves and debt service to be funded at sufficient levels to meet FY 09-10 requirements.It met the
capital and operating requirements, the Commission’s Financial Plan policies, and covenants associated
with MWMC’s 2006 and 2008 revenue bonds as well as provided adequate debt service coverage ratios
for an additional $20 million bond sale in FY 09-10.
In FY 09-10, there was an 18% user rate increase over FY 08-09 rates and was applied uniformly across
all user classes. The increase was driven by the need to finance the capital improvement program and
establish rates to borrow an additional $20M in revenue bonds.
Page 14 DRAFT FY 11-12 BUDGET AND CIP
Metropolitan Wastewater Management Commission Budget and Program Summary
In FY 10-11, there was a 5% user rate increase over the FY 09-10 rates providing for Operations,
Administration, Capital programs, reserves and debt service to be funded at sufficient levels to meet FY
10-11 requirements.
The FY 11-12 budget is based on a 4% user rate increase over the FY 10-11 rates. This increase will
continue to provide for Operations, Administration, Capital programs, reserves and debt service and meet
capital and operating requirements, and support the Commission’s Financial Plan policies, and covenants
associated with MWMC’s 2006 and 2008 revenue bonds.
The figure below compares the regional component of average monthly residential sewer rates.
ÆÐ㪱ÆÃªÃ±ÂªÃYÂ_Æ3+++2432
2/È44
24È44
3/È44
34È44
/È44
4È44
3+++24442443244224412440244/244.244-244,244+243424332432
¦
Page 15 DRAFT FY 11-12 BUDGET AND CIP
Metropolitan Wastewater Management Commission Budget and Program Summary
5-YEAR REGIONAL
OPERATING BUDGET COMPARISON
$15,722,799
$15,158,940
$15,243,872
$16,000,000
$14,540,521
$13,773,806
$14,000,000
$12,000,000
$10,000,000
$8,000,000
$6,000,000
$4,000,000
$2,000,000
$0
FY 07-08FY 08-09FY 09-10FY 10-11FY 11-12
Regional Wastewater Capital Improvement Programs
5-Year Comparison
$120,000,000
$96,902,414
$100,000,000
$76,226,346
$80,000,000
$65,434,192
$60,000,000
$40,000,000
$32,520,347
$27,435,037
$20,000,000
$-
FY 07-08FY 08-09FY 09-10FY 10-11FY 11-12
Page 16 DRAFT FY 11-12 BUDGET AND CIP
Metropolitan Wastewater Management CommissionStaffing
EXHIBIT 5
Notes:
*FTE figures represent portions of Eugene and Springfield staff funded by regional wastewater funds.
** The chart represents groups of staff dedicated to program areas rather than specific positions.
Page 17 DRAFT FY 11-12 BUDGET AND CIP
Metropolitan Wastewater Management CommissionStaffing
Note: Springfield’s Industrial Pretreatment Program staffing of 3.20 FTE is incorporated into the position summary
because the Industrial Pretreatment Programs are funded through the RWP.
Page 18 DRAFT FY 11-12 BUDGET AND CIP
Metropolitan Wastewater Management CommissionStaffing
EXHIBIT 6 (Continued)
REGIONAL WASTEWATER PROGRAM
POSITION SUMMARY
ADOPTEDADOPTEDPROPOSED
CLASSIFICATIONFY 09-10FY 10-11FY 11-12CHANGE
EUGENE WASTEWATER DIVISION & OTHER PW
Division Directo0.750.750.850.10
r
Operations Manage0.930.930.930.00
r
Finance and Administration Manage0.890.890.890.00
r
0.820.820.820.00
Pretreatment/Laboratory/Sampling Superviso
r
Operations Superviso1.001.01.000.00
r0
Residuals Superviso1.001.01.000.00
r0
Electrical Maintenance Superviso1.001.01.000.00
r0
Equipment Maintenance Superviso0.970.970.970.00
r
0.910.910.910.00
Facilities Superviso
r
Parts and Supply Supervisor/Buye0.890.890.890.00
r
Environmental Data Analyst0.650.650.650.00
0.890.890.890.00
Health and Safety Superviso
r
Technical Services Analyst0.890.890.890.00
Project Manage0.930.930.930.00
r
PW Financial Services Manage0.200.20.200.00
r0
PW Maintenance Superviso0.050.00.000.00
r0
Applications System Analyst2.671.781.780.00
Applications Support Technician1.000.950.950.00
Pump Station Tech Specialist 20.570.570.38-0.19
16.01.00
Wastewater Technician (Operator)15.0015.0
00
Wastewater Technician (Residuals)5.005.05.000.00
0
Wastewater Technician (Pretreatment)3.143.143.140.00
4.300.00
Wastewater Technician (Laboratory)4.734.3
0
Wastewater Technician (Sampling)1.891.891.890.00
Wastewater Technician (Mechanical)7.837.837.78-0.05
Wastewater Instrument/Electrician3.883.883.82-0.06
Electrician1.001.01.000.00
0
9.3110.299.59-0.70
Maint Worke
r
Billing Specialist1.001.01.000.00
0
Engineering Associate0.350.350.450.10
0.890.890.890.00
Senior Office Superviso
r
Admin Specialist,S0.890.891.780.89
r
Admin Specialist1.791.790.95-0.84
Parts and Supply Specialist1.781.841.78-0.06
Custodial Worke1.001.01.000.00
r0
T OT A0.19
L
76.4976.1176.30
95.8992.5692.980.42
GRAND TOTAL
Page 19 DRAFT FY 11-12 BUDGET AND CIP
Metropolitan Wastewater Management Commission Reserves
REGIONAL WASTEWATER PROGRAM
RESERVES
The RWP maintains reserve funds for dedicated purpose to sustain stable rates while fully funding
operating and capital needs. Commission policies and guidance, which direct the amount of reserves
appropriated on an annual basis, are found in the MWMC Financial Plan (2005). Further details on the
FY 11-12 reserves are provided below.
OPERATING RESERVES
The MWMC Operating Budget includes four separate reserves: the working capital reserve, rate stability
reserve, rate stabilization reserve, and the operating reserve. Revenues are appropriated across the
reserves in accordance with Commission policy and expenditure needs. Each reserve is explained in
detail below.
WORKING CAPITAL RESERVE
The Working Capital Reserve acts as a revolving account that is drawn down and replenished on
a monthly basis to provide funds for payment of Springfield Administration and Eugene
Operations costs prior to the receipt of user fees from the Springfield Utility Board and Eugene
Water and Electric Board. The Working Capital Reserve is set at $900,000 for FY 11-12,
$200,000 of which is dedicated to Administration and $700,000 is dedicated to Operations.
RATE STABILITY RESERVE
The Rate Stability Reserve was established to implement the Commission’s objective of
maintaining stable rates. It is intended to hold revenues in excess of the current year’s operating
and capital requirements for use in future years, in order to avoid “rate spikes.” The amount
budgeted on an annual basis varies in response to the variability of actual revenues net of
expenses, and annual budgeted amounts for the operating and capital reserves.
RATE STABILIZATION RESERVE
The Rate Stabilization Reserve contains funds to be used at any point in the future when net
revenues are insufficient to meet the bond covenant coverage requirement. The Commission
shall maintain the Rate Stabilization account as long as bonds are outstanding. In FY 11-12 no
additional contribution to this reserve is budgeted and the balance at June 30, 2012 will remain at
$2,000,000.
Page 20 DRAFT FY 11-12 BUDGET AND CIP
Metropolitan Wastewater Management Commission Reserves
OPERATING RESERVE
The Operating Reserve is used to account for accumulated operating revenues net of operating
expenditures (including other reserves). The Commission’s adopted policy is to budget the Operating
Reserve at approximately 10% of the adopted operating budget. For FY 11-12, the Operating Reserve is
budgeted at $1,571,289,which is 10% of total Personal Services, Materials and Services, and Capital
Outlay in accordance with Commission policy.
EXHIBIT 7
CAPITAL RESERVES
The MWMC Capital Budget includes five reserves: the Equipment Replacement Reserve, SDC Reserves
(i.e. Reimbursement and Improvement), the Capital Reserve and the Bond Reserve. These reserves
accumulate revenue to help fund capital projects including equipment replacement and major
rehabilitation. They are funded by annual contributions from user rates, SDCs, bond proceeds, and SRF
loans. Each reserve is explained in detail below.
EQUIPMENT REPLACEMENT RESERVE
The Equipment Replacement Reserve accumulates replacement funding for three types of equipment: 1)
major/stationary equipment items costing less than $200,000 with useful lives of 20 years or less; 2) fleet
vehicles maintained by the Eugene Wastewater Division; and 3) computers that serve the Eugene
Page 21 DRAFT FY 11-12 BUDGET AND CIP
Metropolitan Wastewater Management Commission Reserves
Wastewater Division. Contributions to the Equipment Replacement Reserve in the FY 11-12 budget total
$782,564, additional budget details are provided below.
The Equipment Replacement Reserve is intended to accumulate funds necessary to provide for the timely
replacement or rehabilitation of equipment, and may also be borrowed against to provide short-term
financing of capital improvements. An annual analysis is performed on the Equipment Replacement
Reserve. The annual contribution is set so that all projected replacements will be funded over a 20-year
period and at the end of the 20-year period, the reserve will contain replacement funds for all equipment
projected to be in use at that time. Estimates used in the analysis include interest earnings, inflation rates
and useful lives for the equipment.
SYSTEM DEVELOPMENT CHARGE (SDC) RESERVES
SDCs are required as part of the MWMC IGA. They are connection fees charged to new users to recover
the costs related to system capacity, and are limited to funding Capital Programs. The purpose of the
SDC Reserves is to collect and account for SDC revenues separately from other revenue sources, in
accordance with Oregon statutes. The Commission’s SDC structure includes a combination of
“Reimbursement” and “Improvement” fee components. Estimated SDC revenues for FY 11-12 are
approximately $589,821. Budgeted expenditures include $2,000,000from Improvement Fees to fund
portions of the annual debt service payments on the 2006 and 2008 revenue bonds. The projected
beginning SDC Reserve balance on July 1, 2011 is $2,505,183.
Page 22 DRAFT FY 11-12 BUDGET AND CIP
Metropolitan Wastewater Management Commission Reserves
CAPITAL RESERVE
The Capital Reserve accumulates funds transferred from the Operating Reserve for the purpose of funding
the CIP, Major Capital Outlay and Major Rehabilitation Program costs. The intent is to collect sufficient
funds over time to construct a portion of planned capital projects with cash in an appropriate balance with
projects that are funded with debt financing. The FY 11-12 Budget includes a contribution from the
Operating Reserve of $8,354,604. The beginning balance on July 1, 2011 is projected to be $57,717,443.
Additional budget detail on the CIP, Major Capital Outlay and Major Rehabilitation Program reserves is
provided below.
BOND RESERVE
The Bond Reserve was created to provide assurances to the bond holders that adequate revenue coverage
will be provided for future debt service payments. For FY 11-12 the Bond Reserve is budgeted at
$8,100,000 in order to meet reserve requirements of the bond issuances ($4,100,000 for 06 issuance and
$4,000,000 for 08 issuance).
Page 23 DRAFT FY 11-12 BUDGET AND CIP
Metropolitan Wastewater Management Commission Reserves
* Includes $450,000 in sponsorship contributions
Page 24 DRAFT FY 11-12 BUDGET AND CIP
Metropolitan Wastewater Management Commission Springfield Budget Detail
CITY OF SPRINGFIELD
REGIONAL WASTEWATER PROGRAM RESPONSIBILITIES
The City of Springfield manages administration services for the RWP under a contract with the
MWMC. The programs maintained by Springfield to support the RWP are summarized below and are
followed by Springfield’s regional wastewater budget summaries. Activities, and therefore program
budgets, for MWMC administration vary from year to year depending upon the major construction
projects and special initiatives underway. A list of the capital projects Springfield staff will support in
FY 11-12 is provided in Exhibit 12 on page 41.
MWMC ADMINISTRATION
The Springfield Environmental Services Division (ESD) and Finance Department provide ongoing
support and management services for MWMC. The Public Works Director and the Environmental
Services Manager serve as the MWMC Executive Officer and General Manager, respectively.
Springfield provides the following administration functions: financial planning management,
accounting and financial reporting; risk management and legal services; coordination and management
of public policy; coordination and management of regulatory and permit compliance issues;
coordination between the Commission and the governing bodies; long-range capital project planning
and construction management; coordination of public information, education, and citizen involvement
programs; sewer user customer service; and coordination and development of regional budgets, rate
proposals, and revenue projections.
INDUSTRIAL PRETREATMENT (SOURCE CONTROL) PROGRAM
The Industrial Pretreatment Program is a regional activity implemented jointly by the cities of Eugene
and Springfield. The Industrial Pretreatment section of the ESD is charged with administering the
program for the regulation and oversight of wastewater discharged to the sanitary collection system by
industries in Springfield. This section is responsible for ensuring that these wastes do not damage the
collection system, interfere with wastewater treatment processes, result in the pass-through of harmful
pollutants to treated effluent or biosolids, or threaten worker health or safety.
This responsibility is fulfilled, in part, by the use of a permit system for industrial dischargers. This
permit system, common to both Eugene and Springfield, implements necessary limitations on waste
characteristics and establishes inspection, monitoring, and reporting requirements for documenting
waste quality and quantity controls. The Industrial Pretreatment section is also responsible for locating
new industrial discharges in Springfield and evaluating the impact of those discharges on the regional
WPCF. As of February 2011, there were 20 significant industrial users under permit in Springfield.
The Industrial Pretreatment Program also addresses the wastewater discharges of some
commercial/industrial businesses through the development and implementation of Pollution
Management Practices. Pretreatment program staff also coordinates pollution prevention activities in
cooperation with the Pollution Prevention Coalition of Lane County.
Page 25 DRAFT FY 11-12 BUDGET AND CIP
Metropolitan Wastewater Management Commission Springfield Budget Detail
ACCOUNTING & FINANCIAL REPORTING
Accounting and financial reporting services for the RWP are provided by the Accounting section in the
Springfield Finance Department, in coordination with ESD. Springfield Accounting staff maintains
grant and contract accounting systems, as well as compliance with all local, State and Federal
accounting and reporting requirements for MWMC finances. This section also assists ESD with
preparation of the MWMC budget, capital financing documents, sewer user rates, and financial policies
and procedures.
PROGRAMS AND SIGNIFICANT SERVICE/EXPENDITURE CHANGES
In FY 11-12, the City of Springfield will support the following major regional initiatives in addition to
ongoing Commission administration and industrial pretreatment activities:
Revise the Wet Weather Flow Management Plan (WWFMP), focusing on continued Inflow and
Infiltration reductions, including flow monitoring, data tracking, and regional coordination, and
continue to explore methods of addressing private laterals.
Implement Capital Financing strategies necessary to meet current revenue bond obligations,
prepare for additional debt financing, and ensure sufficient revenues in accordance with the
2005 MWMC Financial Plan.
Continue implementation of the 2004 MWMC Facilities Plan to meet all regulatory
requirements and capacity needs and update the 2004 Facilities Plan in FY 11-12. Considering
emerging environmental regulations that may impact the operation of the WPCF.
Continue public information and outreach activities focused on the MWMC Facilities Plan and
MWMC work to maintain river health.
Protect RWP interests through participation in Association of Clean Water Agencies activities
and Board of Directors.
Coordinate temperature TMDL compliance through the development and implementation of the
recycled water program.
Continue participation with ACWA and DEQ in the development of the Capacity Management
Operations and Maintenance (CMOM) Program.
Complete a Poplar Marketing and Harvest Plan, which was initiated in FY 07-08.
water end-use market/feasibility study and capital plan, which was FY 078.
Continue participation in the Pollution Prevention Coalition of Lane County.
SIGNIFICANT CHANGES FOR FY 11-12
The budget for Springfield Personnel Services, Materials and Services, and Capital Outlay for FY 11-12
totals $3,609,970 representing an overall increase of $63,138 over the adopted FY 10-11 budget (1.8%).
Personnel Services
Personnel Services totaling $1,688,835 represent a FY 11-12 increase of $101,880 or (6.4%) over the
originally adopted FY 10-11 budget.
Page 26 DRAFT FY 11-12 BUDGET AND CIP
Metropolitan Wastewater Management Commission Springfield Budget Detail
Staffing
A net increase of .23 FTE is included in the FY 11-12 budget which represents a re-allocation of an
Environmental Services Technician II in the Pretreatment Program and re-allocation of FTE in the
Accounting Department.
Regular Wages - $1,117,535 [Increase of $74,449 or (7%)]
This increase represents the Class and Comp Study implementation approved by the Springfield
City Council.
Employee Benefits (includes Employee Benefits, Medical/Dental Insurance and PERS/PSRP), -
Budget Request $558,952 [Increase $87,449 or 18.5%]
Fringe benefits are increased by $87,480, primarily as a result of the implementation of the Class
and Comp study as well as increases in insurance premiums and contributions to the PERS/OPSRP
retirement system.
Materials and Services
The Materials and Services budget represents a total FY 11-12 decrease of $38,742 or (2.0%) over the
originally adopted FY 10-11 budget. The major changes are in the following budget categories:
Contractual Services –$208,500 [Decrease of $50,000 or (19%)]
Decrease in FY 11-12, due to the reassignment of the regional condition assessment of the
interceptor sewer lines to the Eugene operations budget. Eugene maintenance staff will perform the
assessment and produce a condition assessment report, and identify any necessary rehabilitation.
Travel & Meeting Expenses - $29,750 [Decrease of $3,750 or (11%)]
Internal Vehicle & Equipment Rent - $6,984 [Decrease of $3,228 or (32%)]
Page 27 DRAFT FY 11-12 BUDGET AND CIP
Metropolitan Wastewater Management Commission Springfield Budget Detail
Note: * Change column and Percent Change column compare proposed FY 11-12 budget to originally adopted
FY 10-11 budget.
Page 28 DRAFT FY 11-12 BUDGET AND CIP
Metropolitan Wastewater Management Commission Springfield Budget Detail
Page 29 DRAFT FY 11-12 BUDGET AND CIP
Metropolitan Wastewater Management Commission Eugene Budget Detail
CITY OF EUGENE
REGIONAL WASTEWATER PROGRAM RESPONSIBILITIES
The Wastewater Division for the City of Eugene manages all Regional Wastewater Pollution Control
Facilities (WPCF) serving the Eugene and Springfield Urban Grow Boundary areas under the
Intergovernmental Agreement for the Metropolitan Wastewater Management Commission (MWMC).
These regional facilities include the Eugene/Springfield Regional Water Pollution Control Facility, the
Biosolids Management Facility, the Beneficial Reuse Site, the Biocycle Farm site, and regional
wastewater pumping stations and transmission sewers.
Program Responsibilities
Administration & Management
Facility Operations
Facility Maintenance
Biosolids Management
Industrial Source Control
Management Information Services
Project Management
In support of the water pollution control program, the Division provides technical services for
wastewater treatment, management of equipment replacement and infrastructure rehabilitation,
biosolids treatment and recycling, and an industrial source control and pretreatment program in
conjunction with City of Springfield staff. Other services include regional laboratory services for
wastewater and water quality analyses and flow monitoring on the regional sanitary trunk sewers.
ADMINISTRATIVE AND MANAGEMENT SERVICES
Administrative Services provides management, administrative, and office support to the Wastewater
Division. This support includes the general planning, directing, and managing of the activities of the
Division; development and coordination of the budget; administration of personnel records; and
processing of payroll, accounts payable, and accounts receivable. This section also provides tracking
and monitoring of all assets for the regional wastewater treatment facilities and clerical support for
reception, telephone services, and other miscellaneous needs. The Administrative services include
oversight and coordination of the Division’s Environmental Management System, safety, and training
programs. Another area this program administers is the coordination of local and regional billing and
rate activities.
REGIONAL WASTEWATER TREATMENT
FACILITY OPERATIONS
The Wastewater Division operates the WPCF to treat domestic and industrial liquid wastes to achieve
an effluent quality that protects and sustains the beneficial uses of the Willamette River. The WPCF is
designed to treat an average of 49 million gallons per day (mgd) of dry weather flow, with a wet
weather peak flow of 277 mgd. The Operations section optimizes wastewater treatment processes to
ensure effluent quality requirements are met in an energy efficient and cost effective manner. In
addition, the Operations section provides continuous monitoring of the alarm functions for all plant
processes, regional and local pump stations, and the Biosolids and Beneficial Reuse Site.
Page 30 DRAFT FY 11-12 BUDGET AND CIP
Metropolitan Wastewater Management Commission Eugene Budget Detail
REGIONAL WASTEWATER TREATMENT
FACILITY MAINTENANCE
The Maintenance section of the Wastewater Division is responsible for preservation of the multi-
million dollar investment in the equipment and infrastructure of the WPCF. This section provides a
preventative maintenance program to maximize equipment life and performance; a corrective
maintenance program for repairing unanticipated equipment failures; a facility maintenance program to
maintain the buildings, treatment structures, and grounds; and a stores unit that purchases and stocks
parts and supplies and assists with professional services contracting. Also included within the
Maintenance section's charge are the pump stations and sewers in the regional collection system, and
the facilities and equipment at the Biosolids Management and Beneficial Reuse Site.
BIOSOLIDS MANAGEMENT
The Residuals Management section of the Wastewater Division manages the handling and beneficial
reuse of the biological solids (biosolids) produced as a result of the activated sludge treatment of
wastewater. This section operates the Biosolids Management Facility (BMF) and the Biocycle Farm
located at Awbrey Lane in Eugene. Approximately 4,000 dry tons of biosolids are produced annually
by the WPCF. These biosolids are treated using anaerobic digestion, stored in facultative lagoons
(which provide some additional treatment benefits), and then processed through a belt filter press and
air-dried to reduce the water content and facilitate transport. The dried material is ultimately applied to
agricultural land or irrigated on poplar trees at the Biocycle Farm as a beneficial fertilizer and soil
conditioner. This section also manages the Beneficial Reuse Site, which formerly served to treat
wastewater from food processing operations.
INDUSTRIAL SOURCE CONTROL (Pretreatment) and ANALYTICAL SERVICES, SAMPLING
TEAM
The pretreatment program is a regional activity implemented jointly by the cities of Eugene and
Springfield. The Industrial Source Control group of the Wastewater Division is charged with
administering the pretreatment program for the regulation and oversight of commercial and industrial
wastewaters discharged to the sanitary collection system by fixed-site industries in Eugene and by
mobile waste haulers in the Eugene and Springfield areas. This group is also responsible for ensuring
that these wastes do not damage the collection system, interfere with wastewater treatment processes,
result in the pass-through of harmful pollutants to treated effluent or biosolids, or threaten worker health
or safety.
This responsibility is fulfilled through the use of a permit system for industrial dischargers. This permit
system, common to both Eugene and Springfield, implements necessary limitations on waste
characteristics and establishes inspection, monitoring, and reporting requirements for documenting
waste quality and quantity controls. The staff is also responsible for locating new industrial discharges
in Eugene and evaluating the impact of new non-residential discharges on the WPCF. As of December
2010, there were 22 significant industrial users under permit in Eugene. The section also has
responsibilities related to environmental spill response activities.
The Analytical Services group provides necessary analytical work in support of wastewater treatment,
residuals management, industrial source control, stormwater monitoring, and special project activities
Page 31 DRAFT FY 11-12 BUDGET AND CIP
Metropolitan Wastewater Management Commission Eugene Budget Detail
of the Wastewater Division. The laboratory's services include sample handling and analyses of influent
sewage, treated wastewater, biosolids, industrial wastes, stormwater, and groundwater. Information
from the laboratory is used to make treatment process control decisions, document compliance with
regulatory requirements, demonstrate environmental protection, and ensure worker health and safety.
The Sampling Team is responsible for the sampling activities related to regional wastewater program
functions. These include the Eugene pretreatment program, wastewater treatment process control,
effluent and ambient water quality, groundwater quality, facultative sludge lagoons, and stormwater
samples. The Division’s Environmental Data Analyst evaluates and reports on the sampling data for
various programs.
MANAGEMENT INFORMATION SERVICES (MIS)
The MIS section provides services for electronic data gathering, analysis, and reporting as necessary in
compliance with regulatory requirements and management functions. This section also maintains the
electronic communication linkages with the City of Eugene and the Regional Information System, and
supplies technical expertise and assistance in the selection, operation, and modification of computer
systems (hardware and software) within the Division.
PROJECT MANAGEMENT
Management of wastewater system improvements and ongoing developments is carried out by the Project
Management staff. Activities include coordination of CIP activities with the City of Springfield staff,
problem-solving and action recommendations, project management, technical research, coordination of
activities related to renewal of the NPDES wastewater discharge permit, computer-aided design and
electronic storage of design drawings, and planning of projects to anticipate and prepare for new
regulatory and operational requirements. The Project Management staff develops Request for Proposals
and Request for Quotes, coordinates special project activities between work sections, and coordinates the
procurement of building permits as necessary in support of project activities.
PROGRAMS AND SIGNIFICANT SERVICE/EXPENDITURE CHANGES
In FY 11-12, Eugene staff will support the following major regional initiatives in addition to ongoing
operational activities.
Manage the O&M responsibilities of the NPDES permits for the wastewater discharge and treatment
plant stormwater programs and the LRAPA air emissions permit for the regional wastewater
treatment plant.
Continue to evaluate impacts of regulatory actions (such as the federal SSO and blending policy
development, Willamette River TMDLs implementation, and any newly adopted state water quality
standards) upon operational responsibilities.
Provide technical input and O&M assessments related to proposed initiatives for addressing TMDL
compliance, greenhouse gas emission controls, and renewable energy objectives.
Complete scheduled major rehabilitation, equipment replacement, and other capital projects in an
efficient and timely manner.
Page 32 DRAFT FY 11-12 BUDGET AND CIP
Metropolitan Wastewater Management Commission Eugene Budget Detail
Work cooperatively on the CIP elements and effectively integrate capital project work with ongoing
O&M activities, with emphasis on maintaining an effective CIP management and coordination
program with Springfield.
Achieve ongoing sustainable efficiencies by initiating projects to reduce energy consumption. This
includes the Aeration Blower Design & Engineering project that will provide significant ongoing
electrical energy savings. The two-year project includes $275,000 in the proposed FY11-12 budget
for design and engineering work, and an estimated $1,225,000 to be budgeted in FY12-13 for
equipment and construction costs to complete the project.
Manage the Operations & Maintenance (O&M) aspects of the Biocycle Farm, continuing the
development of the biosolids irrigation practices and poplar tree management.
SIGNIFICANT CHANGES IN THE O & M BUDGET FOR FY 11-12
The proposed budget for Operations and Maintenance of the regional wastewater treatment facilities
.
(personnel, materials and services, and capital outlay) for FY 11-12 totals $12,112,828 The amount
represents an increase of 4.3% from the FY 10-11 budget. The largest cost centers for the proposed budget
are personnel costs, utilities, materials, maintenance, and chemicals. Details of significant items and changes
proposed for the FY 11-12 Operations and Maintenance budget as compared to the FY 10-11budget include:
Personnel Services
Personnel Services totaling $7,445,623 represents a FY 11-12 increase of $423,498 or 6%. The major
changes are in the following budget categories:
Staffing
An increase of 0.19 FTE is proposed for FY11-12 due to rebalancing FTE between local and regional
funds.
FTE Fund Reallocations – During the preparation of the annual budget proposal, the distribution of FTE
hours for regional and non-regional activities from the previous year are reviewed and adjustments are
made to the proposed year’s budget. This is done to project proper charges of staffing based on actual
time spent between the regional and local funds, and planned labor activities for the coming fiscal year.
(+0.19 FTE increase)
Regular Wages $4,726,022 [Increase of $120,028 or 2.6%]
Salaries are based upon negotiated management/labor contracts between the City of Eugene and the local
union (AFSCME). The Cost of Living (COLA) is projected at 2.0%.
The increase is also a result of annual merit increases for existing staffs, as applicable.
Employee Benefits $1,484,936 [Increase of $174,706 or 13.3%]
Page 33 DRAFT FY 11-12 BUDGET AND CIP
Metropolitan Wastewater Management Commission Eugene Budget Detail
The employee benefits increase is due primarily to higher PERS/OPSRP retirement system
contributions.
Health Insurance $1,071,997 [Increase of $140,274 or 15.1%]
The increase is based on group claims experience and cost projections. Costs are calculated based on the
number of employees.
Materials and Services
The proposed Materials and Services budget totaling $4,650,205 and represents an FY 11-12 increase of
$60,223 or 1.3%. The major changes are in the following budget categories:
Utilities $775,345 [Increase of $69,840 or 9.9%]
The increase is due to a projected 9% increase in electric rates and slightly increased electric usage due to
additional odorous air controls.
Fleet Operating Charges ($302,822) [Decrease of $29,945 or (9.0%)]
Each year fleet rates are estimated by proportioning historic costs by vehicle category. The decrease in
this line item is based on the previous year’s expenditures for equipment.
Page 34 DRAFT FY 11-12 BUDGET AND CIP
Metropolitan Wastewater Management Commission Eugene Budget Detail
Note: * Change column and Percent Change column compare adopted FY 11-12 budget to originally adopted FY
10-11 budget.
Page 35 DRAFT FY 11-12 BUDGET AND CIP
Metropolitan Wastewater Management Commission Eugene Budget Detail
Page 36 DRAFT FY 11-12 BUDGET AND CIP
Metropolitan Wastewater Management Commission Capital Improvement Program
REGIONAL WASTEWATER PROGRAM
CAPITAL PROGRAMS
Overview and Goals
The FY 11-12 Regional Wastewater Program (RWP) Capital Budget and the FY 11-16 five-year Capital
Improvement Program (CIP) are based on the MWMC Facilities Plan (the Plan). The Plan was
approved by the MWMC, the governing bodies of Eugene, Springfield and Lane County, and the
Oregon Department of Environmental Quality in 2004. The Plan, and its 20-year capital project list,
was the result of a comprehensive evaluation of the regional wastewater treatment facilities serving the
Eugene-Springfield metropolitan area.
The Plan built on previous targeted studies, including the 1997 Master Plan, 1997 Biosolids
Management Plan, 2001 Wet Weather Flow Management Plan (WWFMP), and the 2003 Management
Plan for a dedicated biosolids land application site. The Plan was intended to identify facility
enhancements and expansions needed to meet changing regulatory and wet weather flow requirements
and to serve the community’s wastewater capacity and treatment needs through 2025.
The objectives of the Capital Program are:
Compliance with applicable local, state, and federal laws and regulations;
Protection of the health and safety of people and property from exposure to hazardous
conditions such as untreated or inadequately treated wastewater;
Provision of adequate capacity to facilitate community growth in the Eugene-Springfield
metropolitan area consistent with adopted land use plans;
Construction, operation, and management of the MWMC facilities in a manner that is as cost-
effective, efficient, and affordable to the community as possible in the short and long term;
Implementation of Citizens Advisory Committee recommendations, which represent diverse
community interests, values and involvement, and that have been adopted by the Commission as
the MWMC plans and policies; and
Mitigation of potential negative impacts of the MWMC facilities on adjacent uses and
surrounding neighborhoods (ensuring that the MWMC facilities are “good neighbors” as judged
by the community).
Attaining these objectives is the basis for the projects included in the five-year CIP and FY 11-12
Capital Projects budget administered by the Capital Projects Section staff in the City of Springfield. The
capital program objectives also guide the capital projects administered by the City of Eugene that extend
the life of the existing facilities through equipment replacement, facility rehabilitation and capital outlay.
With respect to the first objective above, the MWMC completed improvements needed to achieve the
estimated peak hydraulic capacity in the regional conveyance and treatment systems as of December 31,
2009.
Page 37 DRAFT FY 11-12 BUDGET AND CIP
Metropolitan Wastewater Management Commission Capital Improvement Program
CIP Financial Planning and Policy Overview
The RWP CIP is funded primarily through proceeds from revenue bond sales, system development
charges, and transfers from the operating fund to Capital Reserves. Project financing is also available
through the Clean Water State Revolving Fund (SRF) loan program. In 2008, staff applied for a
construction SRF loan, and in 2009, staff applied for a planning SRF loan. As a result, the MWMC
entered into loan agreements with the State of Oregon Department of Environmental Quality (DEQ) in
2008, 2009, and 2010 that allows the MWMC to borrow up to $20.8 million over the next five years for
qualified projects.
Through the construction SRF loan program, $8,000,000 of financing was approved for the Tertiary
Filtration—Phase 1 project, $7,500,000 approved for Odorous Air Treatment—Phase 1, and $4,000,000
approved for Primary Sludge Thickening. Of the $7,500,000 approved for the Odorous Air Control
project, $4,000,000 was funded through the American Reinvestment and Recovery Act (ARRA, or
“Stimulus”). This funding was part of the federal government’s economic stimulus program, with loans
issued under favorable conditions to stimulate infrastructure and capital project investment.
The ARRA funding agreement provided that 50% of the loan’s principal would be forgiven, and the
remaining 50% of principal to be repaid at 0% interest. This resulted in $2,000,000 of net revenue to the
CIP. Additionally, $1,279,200 in SRF financing was made available to the MWMC for RWP planning
efforts. Loan payments on both construction and planning efforts began October 2010. In the long
term, staff anticipates that, while SRF funding will remain available in the future, the ARRA funding
program was a one-time opportunity resulting from federal stimulus spending, and will not be available
in the future.
The operating fund derives the majority of its revenue from wastewater user charges that are collected
by Eugene and Springfield from their respective customers. Transfers from the operating fund are
budgeted annually consistent with the MWMC Financial Plan to meet the financial needs of the capital
projects. The RWP uses these transfers to reduce the amount of borrowing necessary to finance the
capital program.
For each fiscal planning cycle, only one year of budget authority is appropriated. The remaining four
years of the CIP are important and useful for fiscal and work planning purposes, but the funds in the
outer years of the CIP are only planned for, not appropriated. The full amount of obligated multi-year
project costs is typically appropriated in the first year of the project, unless a smaller subset of the
project, such as project design, can be identified and funded without budgeting the full projected project
cost. For these multi-year contracts, unspent funds from one fiscal year will be carried over to
subsequent fiscal years until the project is completed.
The RWP CIP reflects projected price changes over time that affect the cost of materials and services.
Until about 2003, the 20-year average Engineering News Record (ENR) inflationary factor for
construction served as a good predictor for future inflation and was used for projecting the MWMC
costs. Initial cost projections for projects included in the Facilities Plan were included in the Plan based
on January 2004 construction costs. In the period 2004 through 2008, construction inflation accelerated
Page 38 DRAFT FY 11-12 BUDGET AND CIP
Metropolitan Wastewater Management Commission Capital Improvement Program
nationally and local construction cost inflation has even accelerated faster than the national average.
Therefore, the MWMC modified its inflationary projections accordingly.
In early 2006, the MWMC hired the consulting firm CH2M Hill to perform a comprehensive update of
project cost estimates. Following that update, the RWP CIP assumes general prices change at five
percent per year over the planning period. This does not reflect a projection of any single inflation index
but was developed by CH2M Hill to reflect a reasonable aggregate rate of increases for the next five
years, based on the historical activity of both construction and non-construction price indices. Indices
tracked include the Engineering News Record Construction Cost Index, the Turner Building Cost Index,
and the Consumer Price Index.
Recently, construction cost inflation has decreased substantially, contributing to a favorable bidding
climate. In several cases, this has resulted in construction bids lower than estimated costs. RWP staff
will continue to monitor inflationary trends to inform our forecasting of capital improvement costs.
Regional Wastewater Program Capital Projects Budget
The following is a summary of the status of capital projects that are currently budgeted in the FY 10-11
Regional Wastewater Program Capital Budget (“Capital Budget”) and those included in the proposed
FY 11-12 Capital Budget.
The proposed Regional Wastewater Program Capital Budget consists of the projects in the first year of
the FY 11-16 five-year CIP, totaling $25,932,282
Budget and cash flow information pertaining to each ongoing or new capital project initiated in FY 11-
12 is provided in the CIP project summary sheets, included in this document. Each summary sheet
provides a description of the project, the project’s purpose and what drives the timing of the project, the
funding schedule, and the expected final cost and cash flow for the project. For those projects that are in
progress, a short status report is included on the summary sheet.
Completed Capital Projects (Scheduled Completion by June 30, 2011)
In FY 10-11, several capital projects are projected to be completed and closed out. No CIP summary
sheets are included in this document for these projects because there is no expected carryover of project
funds to FY 11-12, and therefore no FY 11-12 budget for these projects will be requested. All projects
completed in FY 10-11 have been completed within the Commission-approved capital budgets for each
project. The completed capital projects are:
Aeration Basin Improvements – Phase 1
Clarifier Improvements
Line Biosolids Lagoon - Phase 2
Odorous Air Treatment—Phase 1
Master Landscape Design & Implementation for the WPCF. (The Landscape Design &
Implementation for the WPCF project established the integrated conceptual design for the
Page 39 DRAFT FY 11-12 BUDGET AND CIP
Metropolitan Wastewater Management Commission Capital Improvement Program
WPCF. It was funded by existing budgeted MWMC Capital Projects. Hereafter,
implementation of the landscape detailed design and construction will likewise be funded
through existing and approved project budgets.)
Carryover Capital Projects (Projects Initiated in FY 10-11 or Earlier)
Most or all (depending on the specific project) of the remaining funding for capital projects that were
started or are on-going in FY 10-11 is carried over in this FY 11-12 budget. CIP project summary
sheets for these carryover projects are included in this document. Overall, the funding for these projects
continues to be consistent with the CH2M Hill 2006 re-costing of capital projects. The on-going
carryover projects are:
WWFMP Update
Facilities Plan Engineering Services
Influent Pumping and Headworks Expansion (Landscape funding only)
Sodium Hypochlorite Conversion
Peak Flow Management Improvements (Landscape funding only)
Odorous Air Treatment - Phase 2
Primary Sludge Thickening
Tertiary Filtration - Phase 1
Effluent Reuse - Phase 1
Effluent Reuse - Phase 2
Line Biosolids Lagoon – Phase 3
Increase Digestion Capacity
Waste Activated Sludge Thickening
Repair and/or Partial Replacement of Biosolids Force Main
2010 Partial Facility Plan Update
New Projects for the FY 11-12 Capital Budget
Consistent with the Facilities Plan project list and the FY 10-11 CIP, several additional projects are
rolling from the second year of the adopted FY 10-15 CIP, into the first year of the FY 11-16 CIP, and
therefore into the FY 11-12 Capital Budget. CIP project summary sheets for these projects are included
in this document.
The following new project was added in the FY 11-12 Capital budget:
Line Biosolids Lagoon—Phase 4
Summary of FY 10-11 Capital Budget
The following summary table Exhibit 12 on page 41– Summary of FY 11-12 MWMC Construction
Program Capital Budget shows the adjusted budget and end-of-year estimates for expenditures for the
FY 10-11 Capital Budget and the amount of funding that is expected to be carried over to FY 11-12 for
those projects that are ongoing to FY 11-12. Also shown is additional funding and new projects in the
FY 11-12 Capital Budget. The projects are organized in the table by where they are in the funding
Page 40 DRAFT FY 11-12 BUDGET AND CIP
Metropolitan Wastewater Management Commission Capital Improvement Program
cycle, i.e. projects completed in FY 10-11, projects to be carried over from the FY 10-11 budget to the
FY 11-12 budget, and projects that are newly budgeted. These projects and funding are consistent with
the planning and funding as presented in the approved FY 10-15 CIP.
Regional Wastewater Program FY 11-16 Five-Year CIP
The projects in the out years of the Regional Wastewater Program FY 11-16 Five-Year CIP are based
almost exactly on the programming of regional capital projects in the current adopted FY 10-15 CIP.
Significant changes from the current CIP include:
Continuation of funding for the Facility Plan Engineering Services in FY 15-16, which includes
an adjustment for inflation.
$69,700 was moved from FY 12-13 to FY 11-12 for the Increase Digestion Capacity project to
support the master landscaping plan implementation (see Exhibit 12, note 1).
Page 41 DRAFT FY 11-12 BUDGET AND CIP
Metropolitan Wastewater Management Commission Capital Improvement Program
Staff has continued, as in past CIPs, to organize the projects in the CIP based on categories that illustrate
the major functions they serve in the wastewater system. The classification system groups capital
projects in four main project categories as follows:
a. Biosolids Management,
b. Non-Process Facilities and Facilities Planning,
c. Conveyance Systems, and
d. Plant Facilities Improvements.
The above classifications of projects are used to organize projects in the summary table for the FY 11-16
CIP in Exhibit 13 on page 43, Regional Wastewater 5-Year Capital Program, and to organize the CIP
summary sheets that describe each project.
EXHIBIT 13
Regional Wastewater 5-Year Capital Programs
FY 11-12FY 12-13FY 13-14FY 14-15FY 15-16TOTAL
CAPITAL PROJECTS
Biosolids Management
Line Biosolids Lagoon - Phase III1,999,0001,999,000
Line Biosolids Lagoon - Phase IV100,0003,200,0003,300,000
Repair/Replace.of Biosolids Force Main1,430,0001,430,000
Non-Process Facilities and Facilities Planning
WWFMP Update278,400278,400
Facility Plan Engineering Services67,00570,35573,87377,56781,445370,245
2010 Facility Plan Update70,13570,135
2015 Facility Plan Update1,349,0001,349,000
Conveyance Systems
Influent Pumping & Headworks92,50492,504
Plant Performance Improvements
Sodium Hypochlorite Conversion2,977,0002,977,000
Peak Flow Management Improvements1,276,0001,276,000
Odorous Air Treatment II1,495,0001,495,000
Primary Sludge Thickening2,052,0002,052,000
Tertiary Filtration I5,517,0005,517,000
Tertiary Filtration II9,680,0009,680,000
Effluent Reuse I3,089,4683,089,468
Effluent Reuse II4,996,1704,996,170
Effluent Reuse III6,542,0006,542,000
Effluent Reuse IV18,835,00018,835,000
Waste Activated Sludge Thickening192,6003,601,6003,794,200
Increase Digestion Capacity300,0008,030,3008,330,300
TOTAL CAPITAL PROJECTS 25,932,28221,444,25511,102,87377,56718,916,44577,473,422
ASSET MANAGEMENT
Equipment Replacement720,355734,701953,041917,8141,828,7625,154,673
Major Rehab507,400775,400592,500383,100403,4002,661,800
Major Capital Outlay275,0001,225,0001,500,000
TOTAL ASSET MANAGEMENT 1,502,7552,735,1011,545,5411,300,9142,232,1629,316,473
TOTAL CAPITAL IMPROVEMENTS$27,435,037$24,179,356$12,648,414$1,378,481$21,148,607$86,789,895
Page 42 DRAFT FY 11-12 BUDGET AND CIP
Metropolitan Wastewater Management Commission Capital Improvement Program
As shown in Exhibit 13 on page 42, the FY 11-16 five-year CIP for Regional Capital Projects amounts
to $77,473,422. When Asset Management Capital Program planned expenditures (administered by the
City of Eugene) are added in, the total five-year CIP comes to $86,789,895. Information regarding each
capital project in the FY 11-16 CIP is included in the CIP summary sheets included in this document.
Regional Wastewater Asset Management Capital Program
Another category of projects in the MWMC Capital Budget are those capital projects and capital
purchases that are administered by the City of Eugene for the MWMC, and which provide for major
reconstruction, replacement, repairs, and purchases necessary to maintain functionality, lifespan, and
effectiveness of existing facility assets. This is called the Asset Management Capital Program. Three
sub-categories are included in the Asset Management category:
a.Equipment Replacement
b.Major Rehabilitation
c.Major Capital Outlay
FY 11-12 Asset Management Capital Program Budget
Equipment Replacement Program - Budget
The FY 11-12 Capital Programs budget includes $720,355 in Equipment Replacement purchases which
are identified on the table below.
Shop Lathe – The regional treatment plant’s maintenance shop lathe has been in service for 27 years and
has reached the end of its useful life. Replacement with current technology will also enable machining
of more kinds of equipment parts with less setup time. Machining equipment parts allows for faster
Page 43 DRAFT FY 11-12 BUDGET AND CIP
Metropolitan Wastewater Management Commission Capital Improvement Program
repair, keeping equipment downtime to a minimum, and is less expensive than purchase of
manufactured parts.
Odor Scrubber Fans – The regional treatment plant’s odor scrubber fans convey odorous air from the
pretreatment solids/grit dewatering building to the odorous air scrubber. The fans have been in service
for 27 years and have reached the end of their useful life. Replacement will maintain the operational
reliability of the scrubber system, which is a legal requirement for worker safety and control of odors
from the treatment facility.
Primary Treatment Sludge and Scum Pumps – The regional treatment plant’s primary sludge and scum
pumps convey sludge and scum removed in primary clarification to the anaerobic digestion process.
The pumps are air-operated diaphragm type and have been in service for 27 years. Replacement with
rotary lobe-type pumps will provide for continued reliability and are more energy efficient.
Return Activated Sludge Pumps – The regional treatment plant’s return activated sludge pumps are
essential equipment to the secondary treatment process. The pumps have been in service for 27 years
and have reached the end of their useful life. These pumps convey settled sludge from the secondary
clarifiers to the aeration basins and the solids handling complex, a key function for removal of
suspended solids and biochemical oxygen demand. Two of the four pumps are currently being replaced
in FY10-11 and this replacement project will complete the full set.
Oil & Grease Extraction System – The oil and grease extraction system is laboratory equipment that
removes oil and grease from wastewater samples for measurement analysis.
Computer replacement includes scheduled replacement of personal and laptop computers, monitors, and
a network file server.
Fleet replacement consists of replacement of a farm tractor, boom mower, and two turf mowers. This
equipment is utilized in grounds maintenance.
Major Rehabilitation Program - Budget
The FY 11-12 Capital Programs budget includes $507,400 for Major Rehabilitation projects which are
identified on the table below.
Page 44 DRAFT FY 11-12 BUDGET AND CIP
Metropolitan Wastewater Management Commission Capital Improvement Program
Air Drying Bed Resurfacing – The biosolids drying process takes place on 13 asphalt drying beds over a
25 acre area. Many of the beds will require resurfacing to extend their useful life. Beginning in FY11-
12 two beds will be resurfaced each year until all beds in need of resurfacing can be completed.
Jenbacher Cogeneration Upper Engine Rebuild – The regional treatment plant’s cogeneration system
provides power equivalent to approximately 55% of the plant’s power needs. Continuous power
generation engine will require a regular scheduled 20,000 hour engine rebuild in FY11-12.
Willakenzie Pump Station Discharge Piping – This project will consist of rehabilitation or replacement
of 4 pump discharge pipe elbows. The existing pipe elbows are the original piping and are severely
worn and could lead to failure.
Exterior Doors Replacement – The original metal exterior doors of the Operations Building at the
Beneficial Reuse Site (prior Seasonal Industrial Waste Site) have corroded to the point which calls for
their replacement.
Block Masonry Wall Coating – The exterior block wall of the Operations Building at the Beneficial
Reuse Site (prior Seasonal Industrial Waste Site) will be coated to address signs of moisture leakage
through the wall.
Operations/Maintenance Building Improvements – This expenditure will go towards miscellaneous
repairs and renovation to maintain and improve the functionality of the Operations and/or Maintenance
Building for staff. Business functions and staff size have changed substantially for office and technical
staff since original construction of the Operations and Maintenance buildings. Rehabilitation and
functionality improvements help to delay the need for additional floor space.
Major Capital Outlay - Budget
The FY 11-12 Capital Programs budget includes $275,000 for one Major Capital Outlay item identified
on the table below.
Page 45 DRAFT FY 11-12 BUDGET AND CIP
Metropolitan Wastewater Management Commission Capital Improvement Program
Major Capital Outlay
Description FY11-12Proposed
Budget
Aeration Blower Design and Engineering 275,000
Total$275,000
Aeration Blower Design and Engineering – This expenditure will go towards the design consulting
phase for replacement of a secondary treatment aeration basin blower. The existing blowers are the
original fixed speed 1,000 horsepower blowers and are far less energy efficient than current available
technology. The equipment and construction related cost, not included in FY11-12, to be requested in
FY12-13 will be an additional $1,225,000.
Summary of FY 11-12 Asset Management Capital Budget
FY 11-12 Proposed
Category of Capital Expense
Budget
Equipment Replacement 720,355
Major Rehabilitation 507,400
Major Capital Outlay 275,000
TOTAL$1,502,755
Page 46 DRAFT FY 11-12 BUDGET AND CIP
Metropolitan Wastewater Management Commission Capital Improvement Program
LINE BIOSOLIDS LAGOONS – PHASE 3
Description:
Reline existing lagoons, Phase 3 at the Biosolids Management Facility (BMF).
Status:
Design phase. Construction is anticipated to start in the summer of 2011.
Justification:
Existing clay lagoon liners are reaching the end of the material’s useful life. A new synthetic
liner will be installed in the lagoons. In Phases 1 and 2, the liner material of choice was high
density polyethylene. In the Phase 1 project implementation, the contractor installed the main
components for a new dredge lateral movement system for all four lagoons, for improved
operational safety and efficiency.
Project Driver:
The MWMC proactively desires to improve the safety of BMF staff, improve operational
reliability of the facultative lagoons, and ensure DEQ compliance related to groundwater
protection.
Project Trigger:
Implement the phased work based on the 2005 work plan schedule provided from the MWMC
to the DEQ. Continue to monitor the effectiveness of the first and second phase of the lagoon
lining projects. The MWMC anticipates rehabilitating all four existing lagoons and monitor the
new liner improvements.
Project Type:
100% Rehabilitation
Estimated Project Cost:
$3,200,000
Expected Cash Flow:
FY 09-10 = $192; FY 10-11 = $1,200,808; FY 11-12 = $1,999,000
Prior2010-11
Expenditure/Category:YearsEst. Act.2011-122012-132013-142014-152015-16Total
Design/Construction $192 $1,200,808 $1,999,000 000$3,200,000
Other 00000000
Total Cost $192 $1,200,808 $1,999,000 $0$0$0$0$3,200,000
Page 47 DRAFT FY 11-12 BUDGET AND CIP
Metropolitan Wastewater Management Commission Capital Improvement Program
LINE BIOSOLIDS LAGOONS – PHASE 4
Description:
Reline existing lagoons, Phase 4 at the Biosolids Management Facility (BMF).
Justification:
Existing clay lagoon liners are reaching the end of the material’s useful life. A new synthetic
liner will be installed in the lagoons. In Phase 1 and 2, the liner material of choice was high
density polyethylene. In the Phase 1 project implementation, the contractor installed the main
components for a new dredge lateral movement system for all four lagoons, for improved
operational safety and efficiency.
Project Driver:
MWMC proactively desires to improve the safety of BMF staff, improve operational reliability of
the facultative lagoons, and ensure DEQ compliance related to groundwater protection.
Project Trigger:
Implement the phased work based on the 2005 work plan schedule provided from MWMC to
DEQ. Continue to monitor the effectiveness of the first and second phase of the lagoon lining
projects. MWMC anticipates rehabilitating all four existing lagoons and monitor the new liner
improvements.
Project Type:
100% Rehabilitation
Estimated Project Cost:
$3,300,000
Expected Cash Flow:
FY 11-12 = $100,000; FY 12-13 = $1,540,000; FY 13-14 $1,660,000
2009-10
PriorEst.
Expenditure/Category:YearsAct.2010-112011-122012-132013-142014-15Total
Design/Construction 000100,000 $3,200,000 00$3,300,000
Other 00000000
Total Cost $0$0$0$100,000 $3,200,000 $0$0$3,300,000
Page 48 DRAFT FY 11-12 BUDGET AND CIP
Metropolitan Wastewater Management Commission Capital Improvement Program
REPAIR AND/OR PARTIAL REPLACEMENT OF BIOSOLIDS FORCE MAIN
Description:
Investigate, repair, and/or replace sections of the biosolids force main (piping system)
where struvite deposits reduce the pipe diameter and cannot be removed by an acid
washing method. The piping system connects the Water Pollution Control Facility
(WPCF) to the Biosolids Management Facility (BMF). A project estimate is $1.5 million
that may require additional funding due to a lack of any existing helpful investigation
technology.
Status:
As of December 22, 2010, staff is researching information about the existing MWMC
biosolids force main (piping system) and confirming the project scope details related to
consultant and construction services.
Justification:
Project will rehabilitate portions of the existing MWMC biosolids conveyance system.
Project Driver:
Maintain system functionality of the biosolids conveyance system.
Project Trigger:
Functionality and capacity issues within the existing pipeline.
Project Type:
100% Rehabilitation
Estimated Project Cost:
$1,500,000
Expected Cash Flow:
FY 10-11 = $70,000; FY 11-12 = $1,430,000
Prior2010-11
Expenditure/Category:YearsEst. Act.2011-122012-132013-142014-152015-16Total
Design/Construction 0$70,000 $1,430,000 $0$0$00$1,500,000
Other 00000000
Total Cost $0$70,000 $1,430,000 $0$0$0$0$1,500,000
Page 49 DRAFT FY 11-12 BUDGET AND CIP
Metropolitan Wastewater Management Commission Capital Improvement Program
WET WEATHER FLOW MANAGEMENT PLAN (year 2010 and beyond)
Description:
Evaluate collection system flow monitoring data collected since the original WWFMP
(Wet Weather Flow Management Plan) which was finalized in 2000. Update and run
collection system model and confirm (revise) the 2004 MWMC Facility Plan
recommendations. Continue evaluating the wastewater private lateral systems, and
investigate ways to encourage or require private lateral repairs. This project is a
combination of two MWMC Facility Plan projects – one for the update of the 2001
WWFMP report, and one for further support and development of a private lateral
program.
Status:
The collection system model update portion of the work has been completed. An
ongoing planning effort is underway to assess opportunities to reduce I&I and provide
reduction targets to cost-effectively ensure compliance with Federal and State
regulations.
Project Driver:
Continue to monitor the wastewater collection system and refine work programs to
reduce infiltration and inflow (I/I) that is caused by wet weather storm events.
Wastewater private lateral infiltration remains an important issue to monitor and address.
Project Trigger:
Scheduled update (WWFMP work programs) and address regulation requirements.
Improvement
SDC Eligibility:
11%
Estimated Project Cost
: $532,000
Expected Cash Flow:
FY 05-06 = $6,028; FY 06-07 = $86,895; FY 07-08 = $42,589; FY 08-09 = $9,562
FY 09-10 = $14,724; FY 10-11 = $93,802; FY 11-12 = 193,000; FY 12-13 = $85,400
Prior2010-11
Expenditure/Category:YearsEst. Act.2011-122012-132013-142014-152015-16Total
Design/Construction 00000000
Other $159,798 $93,802 $278,400 0000$532,000
Total Cost $159,798 $93,802 $278,400 $0$0$0$0$532,000
Page 50 DRAFT FY 11-12 BUDGET AND CIP
Metropolitan Wastewater Management Commission Capital Improvement Program
FACILITY PLAN ENGINEERING SERVICES
Description:
Engineering services for analysis, project definition, cost estimating, and general
consultation regarding the 20-Year Facilities Plan.
Status:
This year, work included continued assistance with overall coordination of utility needs
for the various projects in the capital program at the plant, assistance with plant wide
corrosion control and cathodic protection of piping systems, and a load study and
modeling of WPCF electrical systems.
Justification:
Projects were developed to varying levels of specificity in the 20-Year Facilities Plan and
there is an on-going need to have a consistent technical and engineering resource to
help in further refining projects and generally assisting with implementation of the plan.
Another need addressed by this resource is assurance that the new improvements
maintain the overall integrity of the plant in terms of treatment processes and hydraulics.
Project Driver:
Ongoing goal to efficiently follow and update the 20-Year Facilities Plan.
Project Trigger:
On-going need.
Estimated Project Cost:
$617,585 (Note: Staff anticipates continuation of the need for facility plan engineering
services in 2015-2016 and beyond. Therefore, $81,446 was added for FY 15-16, which
assumes 5% inflation annually)
Expected Cash Flow:
FY 06-07 = $50,000; FY 07-08 = $50,044; FY 08-09 = $25,467;
FY 09-10 = $31,829; FY 10-11 = $90,000; FY 11-12 = $67,005;
FY 12-13 = $70,355; FY 13-14 = $73,873; FY 14-15 = $77,567;
FY 15-16 = $81,445
PriorEst .Act.
Expenditure/Category:Years2010-112011-122012-132013-142014-152015-16Total
Design/Construction 00000000
Other $157,340 $90,000 $67,005 $70,355 $73,873 $77,567 $81,445 $617,585
Total Cost $157,340 $90,000$67,005$70,335$73,873$77,567 $81,445$617,585
Page 51 DRAFT FY 11-12 BUDGET AND CIP
Metropolitan Wastewater Management Commission Capital Improvement Program
SODIUM HYPOCHLORITE CONVERSION
Description:
Convert the existing chlorine gas system to sodium hypochlorite for the base and wet weather flows.
Retain the existing chlorine contact basins for the disinfection process. Install new system with capability
for high rate disinfection of primary effluent diversion using dosages of sodium hypochlorite into a new
contact basin structure. The new contact basin has been split off of this project and is now part of a
different MWMC project (Peak Flow Management Improvements), so the budget for that portion of the
project has also been moved. Staff included upgrades of the existing recreational vehicle (RV)
wastewater dump station to accommodate boat wastewater dumping in the construction bid documents
for the sodium hypochlorite conversion project. The boat wastewater dump modification was designed
and grant funded by the Oregon State Marine Board that the MWMC approved for implementation at the
September 21, 2006 public meeting. The recommended project budget below includes $80,000 allocated
to the project for the boat wastewater dump that was reimbursed by the State agency after construction
was completed. Some of the project funding will support the treatment plant landscape upgrades.
Status:
The upgraded disinfection system has been continuously used since March of 2010. As of December 22,
2010, Emery and Sons Construction and a vendor are following up on improving the sodium hypochlorite
injection/mixing system related to the specified performance requirements. Completion of this system is
anticipated in early 2011.
Justification:
Liquid sodium hypochlorite and sodium bisulfite system will replace the existing chlorine and sulfur
dioxide gas systems and increase the disinfection capacity from 175 mgd to 277 mgd. The high rate
disinfection of the primary effluent is a key component of the primary/secondary split treatment process,
which is needed for meeting the peak flow capacity needs of the wastewater treatment plant.
Project Driver:
Operator and community safety issues and meeting flow capacity requirements for peak flows.
Project Trigger:
Phasing with other related MWMC projects and the need to meet peak flow treatment requirements.
Project Type:
50% Capacity;50% Performance
Improvement SDC Eligibility:
25%
Estimated Project Cost:
$7.8 million (part of the project money will support the treatment plant landscape upgrades)
Expected Cash Flow:
FY 06-07 = $1,353; FY 07-08 = $594,520; FY 08-09 = $3,319,347; FY 09-10 = $(102,501); FY
10-11 = $1,010,281; FY 11-12 = $250,000; FY 12-13 = $50,000; FY 13-14 = $2,677,000 (construction, landscape,
administration, consultant services)
2010-11
Expenditure/Category:Prior Years2011-122012-132013-142014-152015-16Total
Est. Act.
Design/Construction $3,812,719 $1,010,281 $2,977,000 0000$7,800,000
Other 00000000
Total Cost $3,812,719 $1,010,281 $2,977,000 $0$0$0$0$7,800,000
Page 52 DRAFT FY 11-12 BUDGET AND CIP
Metropolitan Wastewater Management Commission Capital Improvement Program
PEAK FLOW MANAGEMENT IMPROVEMENTS
Description:
The Peak Flow Management project combines several project elements described in the
2004 Facilities Plan into one project. These are 1) the Parallel Primary/Secondary Treatment
project, 2) the Bankside Outfall project, 3) the Outfall Mixing Zone Study, and 4) the design
and construction of the high rate disinfection basins, which was pulled out of the Sodium
Hypochlorite Conversion project and added to the Peak Flow Management project. These
project elements combine to provide the hydraulic infrastructure necessary to convey the
peak flow through the plant, split the flow into the parallel primary and secondary treatment
trains, provide additional disinfection capacity, and discharge the treated flow in accordance
with the 2004 MWMC Facilities Plan.
Status:
Construction completed. The remaining budgeted money will help fund the Water Pollution
Control Facility (WPCF) landscape project related to the MWMC Conditional Use Permit
(CUP) requirements.
Justification:
This project expands the peak wet weather treatment capacity to 277 mgd through flow
management techniques.
Project Driver:
DEQ and Oregon Administrative Rules (OAR) related to winter peak wet weather flow (5-
year, 24-hour rain event).
Project Trigger:
Elimination of sanitary sewer overflows by January 1, 2010 related to OAR.
Project Type:
100% Capacity
Improvement SDC Eligibility:
30.2%
Estimated Project Cost
: $19,054,000 (part of the project money will support the treatment plant landscape
upgrades).
Expected Cash Flow:
FY 06-07 = $28,913; FY 07-08 = $1,499,833; FY 08-09 = $9,525,527;
FY 09-10 = $5,934,957; FY 10-11 = $788,770; FY 11-12 = $570,000; FY 12-13 =
$706,000
2010-11
Expenditure/Category:Prior YearsEst. Act.2011-122012-132013-142014-152015-16Total
Design/Construction $16,989,230 $788,770 $1,276,000 $0$0$0$0$19,054,000
Other $0$0$0$0$0$0$0$0
Total Cost $16,989,230$788,770 $1,276,000 $0$0$0$0$19,054,000
Page 53 DRAFT FY 11-12 BUDGET AND CIP
Metropolitan Wastewater Management Commission Capital Improvement Program
ODOROUS AIR TREATMENT – PHASE 2
Description:
Provide odorous air conveyance duct work and tank covers associated with the new
Primary Sludge Thickener.
Status:
Odorous Air Treatment Phase 2 upgrades are being implemented through the Primary
Sludge Thickening and Odorous Air Phase 1 projects. The Odorous Air Phase 1 work
was completed in FY 10-11. The Primary Sludge Thickening project is in the design
phase as of December of 2010.
Justification:
Compliance with Conditional Use Permit requirements and “good neighbor” policy to
reduce odor impacts on the surrounding community.
Project Driver:
Maintain MWMC’s status as environmental stewards. Address neighborhood odor
complaints and community concerns regarding odors.
Project Trigger:
New construction of certain facilities requires odor control upgrades.Odorous Air
Treatment Phase 2 work is being coordinated with the design and construction of the
new Gravity Sludge Thickener (primary sludge thickener technology).
Project Type:
100% Performance
Improvement SDC Eligibility:
26%
Estimated Project Cost
: $1,704,000
Expected Cash Flow:
FY 10-11 = $209,000; FY 11-12 = $1,495,000
Prior2010-11
Expenditure/Category:YearsEst. Act.2011-122012-132013-142014-152015-16Total
Design/Construction 0$209,000 $1,495,000 0000$1,704,000
Other 00000000
Total Cost 0$209,000 $1,495,000 0000$1,704,000
Page 54 DRAFT FY 11-12 BUDGET AND CIP
Metropolitan Wastewater Management Commission Capital Improvement Program
PRIMARY SLUDGE THICKENING
Description:
Install gravity thickener system (covered for odor control), upgrade thin primary sludge
pumping and piping systems, install supernatant overflow pumping and piping, and
thickened sludge piping/pumping to digesters. See Odorous Air Treatment – Phase 2 for
treatment of odors.
Status:
As of December 2010, the project is in the design development phase. The construction
bidding phase is anticipated to start in spring of 2011.
Justification:
Thicken sludge before the digester system and help keep the sludge blanket lower in
primary clarifiers to avoid washout of the sludge blanket during peak flow events.
Project Driver:
Meet class B biosolids requirements during peak two-week solids loading event with all
three existing digesters in service.
Project Trigger:
Availability of sludge thickening capacity is needed prior to next scheduled digester
cleaning (i.e., before 2013).
Project Type:
100% Capacity
Improvement SDC Eligibility:
65%
Estimated Project Cost
: $4,498,000 (Note: Part of the project money will support the treatment plant
landscape upgrades. Also, MWMC received a state revolving fund (SRF) loan
for the primary sludge thickening project)
Expected Cash Flow:
FY 07-08 = $9,730; FY 08-09 = $40,606 FY 09-10 = $501,876;
FY 10-11 = $1,893,788; FY 11-12 = $2,027,000; FY 12-13 = $25,000 (administration,
construction, landscape, consultant services, etc.)
Prior2010-11
Expenditure/Category:YearsEst. Act.2011-122012-132013-142014-15201-165Total
Design/Construction $552,212$1,893,788 $2,052,0000000$4,498,000
Other 00000000
Total Cost $552,212 $1,893,788 $2,052,000 $0$0$0$0$4,498,000
Page 55 DRAFT FY 11-12 BUDGET AND CIP
Metropolitan Wastewater Management Commission Capital Improvement Program
TERTIARY FILTRATION - PHASE 1
Description:
The phased work program will install infrastructure/support facilities for 30 mgd of filters for
tertiary filtration of secondary treated effluent. The first phase/project will only install filter
system technology sufficient for 10 mgd of treatment. Future projects will install the remaining
filter technology. Some of the project funding will support the treatment plant landscape
upgrades.
Status:
The Tertiary Filtration (Phase 1) project is in the construction phase and Pacific Excavation, Inc.
is the MWMC general contractor.
Justification:
Up to 10 mgd of filtration is required in the first phase to meet dry season mass limits, with the
need for filtration increasing up to 30 mgd by the end of the planning period (2025). The 2004
MWMC Facilities Plan proposes phasing filters on an as-needed basis. Filtration provides high
quality secondary effluent and potential level 4 reuse water. Also, filtration is needed to assist
with meeting wet season mass load requirements during peak flow events.
Project Driver:
Performance reliability to meet the dry weather NPDES total suspended solids limits of less
than 10 mg/L, reuse development, and compliance with effluent limits during peak flow
conditions.
Project Trigger:
NPDES permit compliance for TSS: Dry weather maximum month flow in excess of 49 mgd.
Also, initially to provide higher quality effluent so that reuse can be developed.
Improvement SDC Eligibility:
42%
Estimated Project Cost
: Reduced to $11,500,000 (Note: Part of the project money will support the treatment
plant
landscape upgrades. Also, MWMC received a DEQ state revolving fund (SRF) loan for
the tertiary filtration project).
Expected Cash Flow:
FY 07-08 = $236,186; FY 08-09 = $554,241; FY 09-10 = $647,844; FY 10-11 =
$4,544,729; FY 11-12 = $2,750,000; FY 12-13 = $60,000; FY 13-14 = $2,707,000
(design, construction, landscape, administration, etc.)
2010-11
Expenditure/Category:Prior YearsEst. Act.2011-122012-132013-142014-152015-16Total
Design/Construction $1,438,271 $4,544,729 $5,517,000 0000$11,500,000
Other 00000000
Total Cost $1,438,271 $4,544,729 $5,517,000 0000$11,500,000
Page 56 DRAFT FY 11-12 BUDGET AND CIP
Metropolitan Wastewater Management Commission Capital Improvement Program
EFFLUENT REUSE - PHASE 1
Description:
This project is the first package of funding for effluent reuse to address thermal load
issues and for multiple environmental benefits. This project combines two projects
identified in the 2004 MWMC Facilities Plan; Level II Reuse at Seasonal Industrial Waste
and Level 4 Effluent Reuse Demonstration Projects. Project components may include
additional treatment, disinfection, pumping, pipeline, and distribution/irrigation systems.
The projects will be better defined as the planning for reuse continues and as markets
for reuse are identified.
Status:
Ongoing planning phase. The MWMC reached a settlement agreement on October 28,
2009 with the Department of Environmental Quality (DEQ) related to Willamette River
total maximum daily loads (TMDL) for temperature.
Justification:
Implements reuse so that thermal load is removed from the Willamette River and for
multiple environmental benefits.
Project Driver:
Expansion of effluent reuse programs. Address NPDES permit thermal load compliance
related to Willamette River total maximum daily loads (TMDL) temperature requirements.
Project Trigger:
Potential exceedance of NPDES thermal load limit.Identification of water needs for
potential clients.
Project Type:
100% Performance
Improvement SDC Eligibility:
26%
Estimated Project Cost:
$ $3,325,000
Expected Cash Flow:
FY 06-07 = $7,000; FY 07-08 = $0; FY 08-09 = $2,904; FY 09-10 = $12,757;
FY 10-11 = $213,271; FY 11-12 = $2,064,000; FY 12-13 = $1,025,068
PriorEst. Act.
Expenditure/Category:Years2010-112011-122012-132013-142014-152015-16Total
Design/Construction $22,661 $213,271 $3,089,068 $0000$3,325,000
Other 00000000
Total Cost $22,661 $213,271 $3,089,068 $0$0$0$0$3,325,000
Page 57 DRAFT FY 11-12 BUDGET AND CIP
Metropolitan Wastewater Management Commission Capital Improvement Program
EFFLUENT REUSE - PHASE 2
Description:
This project is identified as Level C Effluent Reuse at the Biocycle Farm in the 2004
MWMC Facilities Plan. It encompasses planning, design, and construction necessary
for 1.5 mgd of Class B reuse water at the Biocycle Farm and installation of dedicated
reuse irrigation pipeline and microspray system. The project may change to adapt to
take advantage of emergent opportunities and new information as planning progresses.
Status:
Ongoing planning phase. The MWMC reached a settlement agreement on October 28,
2009 with the Department of Environmental Quality (DEQ) related to Willamette River
total maximum daily loads (TMDL) for temperature.
Justification:
Implements Level C reuse program to reduce the MWMC thermal load discharge into the
Willamette River.
Project Driver:
Expansion of effluent reuse programs. Address NPDES permit thermal load compliance
related to Willamette River total maximum daily loads (TMDL) temperature requirements.
Project Trigger:
Potential exceedance of NPDES thermal load limit. Identification of water needs for
potential clients.
Project Type:
100% Performance
Improvement SDC Eligibility:
26%
Estimated Project Cost:
$5,152,000
Expected Cash Flow:
FY 10-11 = $155,830; FY 11-12 = $1,826,000; FY 12-13 = $3,170,170
PriorEst. Act.
Expenditure/Category:Years2010-112011-122012-132013-14 2014-15 2015-16Total
Design/Construction 0$155,830 $4,996,170 $0000$5,152,000
Other 00000000
Total Cost $0$155,830 $4,996,170 $0$0$0$0$5,152,000
Page 58 DRAFT FY 11-12 BUDGET AND CIP
Metropolitan Wastewater Management Commission Capital Improvement Program
EFFLUENT REUSE - PHASE 3
Description:
This project is in the 2004 MWMC Facilities Plan known as Permanent Level A Reuse. It
is to provide 2.5 mgd of permanent Level A reuse water to local greenspaces and
community areas. Project components may include additional treatment, disinfection
with UV system, pumping, pipeline, and distribution/irrigation systems. The project will
be better defined as the planning for effluent reuse continues and as markets for reuse
are identified.
Status:
Planning phase.
Justification:
Continue implementation of an effluent reuse program to reduce the MWMC thermal
load discharge into the Willamette River and for other environmental benefits.
Project Driver:
Expansion of effluent reuse programs. Address NPDES permit thermal load compliance
related to Willamette River total maximum daily loads (TMDL) temperature requirements.
Project Trigger:
Potential exceedance of NPDES thermal load limit.Identification of water needs for
potential clients.
Project Type:
100% Performance
Improvement SDC Eligibility:
26%
Estimated Project Cost:
$6,542,000
Expected Cash Flow:
FY 12-13 = $500,000; FY 13-14 = $3,942,000; FY 14-15 = $2,100,000
PriorEst. Act.
Expenditure/Category:Years2010-112011-122012-132013-142014-152015-16Total
Design/Construction 000$6,542,000 0$00$6,542,000
Other 00000000
Total Cost $ 0 $ 0 $0$6,542,000 0$0$0$6,542,000
Page 59 DRAFT FY 11-12 BUDGET AND CIP
Metropolitan Wastewater Management Commission Capital Improvement Program
EFFLUENT REUSE - PHASE 4
Description:
This project is in the 2004 MWMC Facilities Plan known as Permanent Level A Reuse. It
is to provide 2.5 mgd of permanent Level A reuse water to local greenspaces and
community areas. Project components may include additional treatment, additional
disinfection, pumping, pipeline, and distribution/irrigation systems. The project will be
better defined as the planning for effluent reuse continues and as markets for reuse are
identified.
Status:
Planning phase.
Justification:
Continue implementation of an effluent reuse program to reduce the MWMC thermal
load discharge into the Willamette River and for other environmental benefits.
Project Driver:
Expansion of effluent reuse programs. Address NPDES permit thermal load compliance
related to Willamette River total maximum daily loads (TMDL) temperature requirements.
Project Trigger:
Potential exceedance of NPDES thermal load limit.Identification of water needs for
potential clients.
Project Type:
100% Performance
Improvement SDC Eligibility:
26%
Estimated Project Cost:
$18,835,000 (estimated based on CH2M Hill’s 2006 project description and cost
estimate, which assumes inflation at 5% annually)
Expected Cash Flow:
FY 15-16 = $4,140,000; FY 16-17 = $11,868,000; FY 17-18 = $2,827,000
PriorEst. Act.
Expenditure/Category:Years2010-112011-122012-132013-142014-152015-16Total
Design/Construction 00000018,835,000 $18,835,000
Other 00000000
Total Cost $ 0 $ 0 $0$0$0$0$18,835,000 $18,835,000
Page 60 DRAFT FY 11-12 BUDGET AND CIP
Metropolitan Wastewater Management Commission Capital Improvement Program
WASTE ACTIVATED SLUDGE THICKENING
Description:
This project provides a third gravity belt thickener (GBT) and associated at-grade
building improvements. The project also includes landscaping.
Status:
Planning stage with the exception of landscaping (in keeping with the 2004 Facilities
Plan landscaping budget allocations, funding from this project is being made available in
FY 11-12 to accommodate staging of the plant-wide integrated landscape plan).
Justification:
Provides additional capacity for Waste Activated Sludge (WAS) thickening and, along
with addition of primary sludge thickening, will help to eliminate the need for additional
digester capacity.
Project Driver:
Additional capacity to provide WAS thickening with one unit offline at upper limit flow
projections. Nitrification required by the NPDES permit and increasing wastewater flows
and loads generates more WAS solids. Provide ability to conduct recuperative
thickening so that the need for additional digestion volume can potentially be deferred.
Project Trigger:
Exceeding solids and hydraulic loading rate design criteria.The latest evaluations of
need for Waste Activated Sludge thickening indicates a need by about 2012 or later.
After the secondary treatment modifications are completed and operational for a time,
the timing of need for this project should be reevaluated.
Estimated Project Cost
: $3,901,000
Improvement
SDC Eligibility:
100%
Expected Cash Flow:
FY 06-07 = $7, 000; FY 07-08 = $0; FY 08-09 = $0; FY 09-10 = $0;
FY 10-11 = $107,400; FY 11-12 = $17,724; FY 12-13 = $202,965;
FY 13-14 = $1,100,500; FY 14-15 = $2,465,411
Expenditure/Category:Prior Years2010-11 Est. Act.2011-122012-132013-142014-152015-16Total
$7,000$107,400$192,600$3,601,600$0$0$0$3,901,000
Design/Construction
Other$0$0$0$3,601,600$0$0$0$0
$7,000$107,400$192,600$3,601,600$0$0$0$3,901,000
Total Cost
Page 61 DRAFT FY 11-12 BUDGET AND CIP
Metropolitan Wastewater Management Commission Capital Improvement Program
INCREASE DIGESTION CAPACITY
Description:
Installation of a fourth conventional high rate digester for continued production and expanded
production of Class B biosolids.
Status:
Planning stage with the exception of landscaping (in keeping with the 2004 Facilities Plan
landscaping budget allocations, funding from this project is being made available in FY 11-12 to
accommodate staging of the plant-wide integrated landscape plan).
Justification:
Continue to meet the requirements for Class B digestion with the ability to take one digester out
of service for cleaning.
Project Driver:
This project addresses the need for more anaerobic digestion capacity. In the 2004 MWMC
Facilities Plan, an option was identified to also change the existing digestion method in order to
produce Class A biosolids. This option was to be considered as a strategy to secure a wider
range of beneficial end-use options in the case that that flexibility was needed for beneficial
reuse. Since that time, MWMC has taken effective steps to expand the ability to handle Class B
biosolids through the construction and expansion of the Biocycle Poplar Plantation, and through
working with other end users. Also, studies have shown that the current solids handling system
will actually produce a Class A product because of the extended storage time available for
biosolids in the lagoons at the biosolids handling facility. The digestion capacity issue will be
influenced by several operational factors including the effectiveness of new primary sludge
thickening and expanded WAS thickening processes, as well as digester cleaning protocols and
schedules. Observation over the next several years is required prior to making a decision on
when the expanded digestion facilities will be needed. A restudy of the anaerobic digestion
system function and capacity should be undertaken prior to moving forward with this digestion
expansion project. This study can be conducted as part of the Facilities Plan Engineering
Services contract with CH2M HILL.
Project Trigger:
The trigger for design and construction of new digestion facilities will depend on the findings of
the digestion system capacity and process alternatives study under the 2010 Facilities Plan
Update.
Improvement SDC Eligibility:
54%
Estimated Project Cost
: $8,600,000
Expected Cash Flow:
FY 10-11 = $269,700; FY 11-12 = $286,200; FY 12-13 = $3,806,000; FY 13-14 = 4,238,100
Prior2010-11
Expenditure/Category:YearsEst. Act.2011-122012-132013-142014-152015-16Total
Design/Construction $0$269,700 $300,000 $8,030,300 $0$0$0$8,600,000
Other $0$0$0$8,030,300 $0$0$0$0
Total Cost $0$269,700 $300,000 $8,030,300 $0$0$0$8,600,000
Page 62 DRAFT FY 11-12 BUDGET AND CIP
Metropolitan Wastewater Management Commission Capital Improvement Program
Page 63 DRAFT FY 11-12 BUDGET AND CIP