HomeMy WebLinkAboutItem B - EWEB Carmen-Smith Relicensing Project
ECC
UGENE ITY OUNCIL
AIS
GENDA TEM UMMARY
Work Session: Carmen-Smith Relicensing Project
Meeting Date: May 29, 2012 Agenda Item Number: B
Department: Central Services Staff Contact: Sue Cutsogeorge
www.eugene-or.gov Contact Telephone Number: 541-682-5589
ISSUE STATEMENT
This is a work session to provide the council information about Eugene Water & Electric Board’s
(EWEB) project for relicensing the Carmen-Smith Hydroelectric Project. The work session will give
some background for the item on the May 29 consent calendar for bonds to finance the project.
BACKGROUND
The Eugene Water & Electric Board owns and operates five hydroelectric generating facilities, three of
which are located on the McKenzie River. All of EWEB’s hydroelectric facilities operate under federal
operating licenses issued by the Federal Energy Regulatory Commission, or FERC. The Carmen-Smith
Hydroelectric Project, which is located 71 miles east of Eugene on the upper McKenzie River, is
EWEB’s largest hydroelectric facility and represents almost half of EWEB’s total utility-owned
generation capacity. EWEB received an initial federal license for the Carmen-Smith Project in 1958,
and the project went online in 1963. The original 50-year license expired in November 2008, and
EWEB has been operating under an annual license from the FERC since that time. EWEB expects to
receive a new 50-year operating license from the FERC for the Carmen-Smith Project in late 2012 or
early 2013.
Relicensing Process
EWEB has been engaged in a process to relicense the Carmen-Smith Project since 2002. This
relicensing process, which is dictated by federal regulation, resulted in the development of draft and
final license applications that were submitted to the FERC in 2006. Beginning in early 2007, EWEB
entered into settlement negotiations with a stakeholder group that included federal and state agencies,
three Native American tribes, and a number of non-governmental organizations. The negotiations
concluded in October 2008, with an agreement signed by EWEB and 16 other groups (EWEB Board
Resolution #0833, October 21, 2008). The Settlement Agreement was filed with the FERC on October
23, 2008, in support of and as a supplement to EWEB’s 2006 license application.
In May 2011, EWEB verified that the FERC has in its possession all of the requisite pieces to process
the new license for the Carmen-Smith Project. In March 2012, EWEB received a notice that FERC staff
had identified an issue regarding the license application that requires resolution before the license can be
issued. Measures to address the issue, which involves the intersection of EWEB’s Carmen-Smith
Project boundary, as licensed by the FERC, and the McKenzie Wild and Scenic River (WSR), as
designated by Congress and managed by the USDA Forest Service, are underway and expected to be
S:\CMO\2012 Council Agendas\M120529\S120529B.doc
complete by October, 2012. Because it will take the FERC several months to revise and review the draft
license, EWEB does not expect the new license for the Carmen-Smith project to be issued before the end
of 2012. There is also a chance that the resolution of this issue by the FERC may be challenged by
outside groups, which could add to the relicensing timeline.
License Application and Settlement Agreement
In EWEB’s application for a new operating license, as amended by the 2008 Settlement Agreement,
EWEB committed to adding upstream and downstream fish passage (fish ladder and fish screening
facilities) to the lowest of the three project reservoirs, Trail Bridge Reservoir. EWEB will also enhance
fish habitat in all three reservoirs and three stream reaches, as well as modifying an existing salmon
spawning channel and providing facilities for enhanced stream flow releases. These actions will directly
benefit native trout and anadromous Chinook salmon. EWEB has also committed to rebuilding three
campgrounds and day use areas associated with the project, and improving native vegetation and
wildlife habitat in the project area. In addition, EWEB plans to rehabilitate the power generation and
transmission facilities associated with the project so that Carmen-Smith can continue to serve the
citizens of Eugene for the next 50 years.
License Implementation Preparation
EWEB staff has used the time between the Settlement Agreement signing and the issuance of the new
FERC license to prepare for the implementation of the agreement and new license. This preparation
includes the development of fish passage design elements and power plant rehabilitation plans, along
with the completion of discrete engineering projects needed for license implementation. EWEB
contracted with CH2M Hill, as design engineer, in 2009, and with Wildish Building Company, as
Construction Manager/General Contractor (CM/GC), in 2011, to assist with the design and construction
of the project. CH2M Hill, recently completed the 60 percent design development for the fish passage
construction elements contained in the settlement agreement. EWEB will continue to work through the
design and consultation process for the fish passage elements in 2012, with an expectation that the
designs will be substantially complete by late 2012.
For the powerhouse improvements, the EWEB and CH2M Hill team completed, in 2011, an in-depth
assessment of all power generation components in both powerhouses and at all three dams. This work
culminated in a comprehensive document that currently serves as EWEB’s guide for future
rehabilitation work at these facilities. Ancillary to the primary work being completed by EWEB staff
and CH2M Hill, the project team continues to work on implementation elements that can either be
completed now or soon after license issuance. In 2011, the project team completed several construction
projects that are part of the overall license implementation program. These include a new bridge at
Carmen Diversion Reservoir, installation of a restroom at Trail Bridge Powerhouse, contract
construction of two SNOTEL weather stations near Carmen-Smith and replacing the remaining wooden
transmission pole structures along the Carmen transmission line. Staff also completed the design of a
number of projects that will be implemented shortly after license issuance in 2013. These include a new
emergency access road to the top of Smith Dam, a re-routed portion of the McKenzie River Trail near
Trail Bridge Dam, and a master plan for new homes and buildings to be built at the project office
compound.
Project Costs and Financing
As part of the Settlement Agreement process, EWEB completed a comprehensive evaluation of license
implementation costs. In June 2011, EWEB updated the implementation cost estimate for the
S:\CMO\2012 Council Agendas\M120529\S120529B.doc
Settlement Agreement and new license based upon the preliminary design (30 percent design) for fish
passage work and conceptual design (15 percent design) for power generation facilities. The cost to
complete the project at that time was estimated to be $156 million plus or minus 30 percent, in
accordance with standard engineering practice. Since then, EWEB has expended approximately $15
million in design, procurement and construction as part of the project. EWEB continues to monitor and
update anticipated project costs as the design work progresses. The next project cost estimate, based on
the 60 percent design for fish passage work, will be available shortly.
The project is being financed with a phased bonding approach. EWEB previously issued $13.4 million
in bonds relating to the Carmen-Smith Project. The remainder of the project will be funded through two
additional bond authorizations: $45 million requested at this time, and the balance to be requested after
the license has been issued and accepted. Authorization for $45 million is being requested to 1) provide
reimbursement of $20 million of project costs paid from reserves over the last several years and 2)
provide funds to cover design and implementation work planned for the remainder of 2012 and through
2013. Once the FERC license is issued and after completion of design work, EWEB will return for
additional authorization for bonding of the construction phase of the project. The reimbursement of
prior year project costs will be placed in reserve to pay for project costs in 2014 and beyond. The
authorization for the first $45 million of bonding authority is on the May 29 council consent calendar.
The impact on rates from issuance of the requested bonds is approximately two percent.
TRIPLE BOTTOM LINE – SOCIAL, ENVIRONMENTAL, ECONOMIC IMPACTS
EWEB and the Settlement Parties included triple bottom line (TBL) concepts as they balanced the
environmental and social impacts of the Carmen-Smith Project with project economics in the Settlement
Agreement. EWEB also recently completed a specific TBL analysis of the project as part of an updated
economic evaluation. The TBL analysis identified the following impacts of completing the project.
Social
Improved safety of recreational facilities through design and construction and financial support
for State Police personnel stationed in the area.
Improved accessibility and maintenance of recreation opportunities close to the
Eugene/Springfield area.
Bull trout and Chinook salmon habitat improvements that result in increased fishing and tourism
opportunities.
Enhanced Native American tribal value as a result of increased number and variety of culturally
significant plant sources of traditional foods and vegetative craft material.
Increased educational opportunities related to aquatics and wildlife management.
Environmental
Decreased risk of oil contamination into the reservoir with the relocation of the substation.
Maintains a low carbon hydro peak power generation facility for the region.
Improvements to trout, Chinook, elk, bird and many other species habitat through installation of
habitat or removal of invasive vegetation.
S:\CMO\2012 Council Agendas\M120529\S120529B.doc
Economic Prosperity
Creates local economic opportunities and activity especially during construction of the
improvements, but also increased tourism as a result of recreation facilities and improved
wildlife habitat.
Compares favorably to the alternative of decommission and replacement capacity development.
FERC staff also completed an environmental assessment under the National Environmental Policy Act
(NEPA) and found that the project as envisioned has no significant environmental impacts, and the State
of Oregon has issued a certification for the project under Section 401 of the Clean Water Act, specifying
that the Project, as certified, will comply with state water quality criteria.
RELATED CITY POLICIES
This project will contribute to the council goal of sustainable development.
COUNCIL OPTIONS
No action is required, therefore, there are no options listed.
CITY MANAGER’S RECOMMENDATION
No action is required; therefore, there is no recommendation.
SUGGESTED MOTION
No action is required; therefore, there is no suggested motion.
ATTACHMENTS
None
FOR MORE INFORMATION
Staff Contact: Sue Cutsogeorge
Telephone: 541-682-5589
Staff E-Mail: Sue.L.Cutsogeorge@ci.eugene.or.us
EWEB Contact: Michael J. McCann, P.E.
Telephone: 541-685-7379
Staff E-Mail: Mike.McCann@eweb.org
S:\CMO\2012 Council Agendas\M120529\S120529B.doc