HomeMy WebLinkAboutItem A: Update on City Hall
ECC
UGENE ITY OUNCIL
AIS
GENDA TEM UMMARY
Work Session: Update on City Hall
Meeting Date: July 9, 2012 Agenda Item Number: A
Department: Central Services Staff Contact: Mike Penwell
www.eugene-or.gov Contact Telephone Number: 541-682-5547
ISSUE STATEMENT
The purpose of this work session is to provide an update on planning efforts related to City
Hall.
BACKGROUND
At the March 16, 2011, work session, the council directed the City Manager to develop and
implement a transition plan for moving all remaining City services out of City Hall by June
30, 2012, and to develop a phased approach to building a new city hall at the current site
utilizing available resources. The council also directed the City Manager to return with a
funding plan for the project. This is both an update on those efforts and an opportunity for the
council to provide input.
At the June 22, 2011, work session, a brief update was provided to the council on efforts to
relocate existing City Hall functions to a combination of temporary, longer-term, and
permanent space while the plan for a new city hall is finalized and approved by the council.
An update on the culmination of those efforts will be provided at the work session.
At the same June 22, 2011, work session, the council expressed general approval to proceed
with the staff-presented plan for reaching a final decision on the two primary options being
considered for City Hall: the new building option and the major renovation option. The plan
included soliciting input from the local chapter of the American Institute of Architects (AIA)
that included review and comment on previous City Hall studies, and analysis of the urban
context around the City Hall site. The final report can be found at http://www.eugene-
or.gov/Archive.aspx?ADID=176.
The plan also included retaining two architects for the purpose of developing and evaluating
strategies for achieving both the new building and major renovation options within a proposed
budget for review and input by a citizen advisory committee. The architects selected were
Poticha Architects for the major renovation option and Rowell Brokaw Architects for the new
building option. Conceptual cost models were developed and refined by Turner Construction.
The City Hall Advisory Committee (CHAC) members provided a broad variety of viewpoints
by people with knowledge of accessibility, design, construction, finance, development issues,
downtown issues, and/or historical preservation. The CHAC members are listed in
Attachment A.
S:\CMO\2012 Council Agendas\M120709\S120709A.doc
The objective of both studies - aided by feedback from the CHAC - was to develop strategies
and discussion points that could assist staff and decision-makers when considering City Hall
options. The committee met on four occasions with the consultants and staff in the fall of
2011, and these meetings provided the primary structure for the completed studies. The final
report on new building strategies produced by Rowell Brokaw Architects can be accessed at
http://www.eugene-or.gov/Archive.aspx?ADID=170 and the final report on major renovation
strategies by Poticha Architects at http://www.eugene-or.gov/Archive.aspx?ADID=169. Each
report contains a cost model developed by Turner Construction detailing the elements and
assumptions that make up the cost-model for each option.
The feedback from the CHAC on the consultant work suggested two overarching conclusions:
1) either the new building or major remodel option could probably be successful, depending
on what the City wanted to accomplish; and 2) a great deal more analysis was needed—
especially for the new building option - to flesh out the opportunities, challenges, benefits,
and risks of the options. In the months since completion of the final reports, a number of City
staff have been engaged in additional analysis relating to funding strategies, occupancy
options, and developer interest in potential public/private opportunities on the full-block site.
Meetings with various members of the development community have indicated strong interest
and a variety of ideas for redeveloping the City Hall site including phase 1 of a new city hall.
Recently, as this additional staff work was nearing completion on the two options, a third
option emerged as a potentially more cost-effective possibility: use of the Eugene Water &
Electric Board’s (EWEB) administration building and conference room building. EWEB’s
rd
recent purchase of a building on West 3Avenue, as well as the work EWEB has completed
on the administration building (such as the roof and HVAC system), prompted a conversation
between City and EWEB staff to see whether it made sense to provide the council with a
third option. That conversation has not progressed yet to know whether this is a viable
option; if it becomes viable, staff will present this option to the council at a work session after
the council’s summer break.
RELATED CITY POLICIES
The City Hall planning process relates to the council goals of an effective, accountable
municipal government, a safe community, and sustainable community growth and change.
COUNCIL OPTIONS
The council is asked to provide feedback on the information presented at this work session.
The council will be asked to take action at a future work session to select a city hall
development option.
CITY MANAGER’S RECOMMENDATION
There are no specific recommendations for this agenda item.
S:\CMO\2012 Council Agendas\M120709\S120709A.doc
SUGGESTED MOTIONS
There are no suggested motions related to this agenda item.
ATTACHMENTS
A.City Hall Advisory Committee
FOR MORE INFORMATION
Staff Contact: Mike Penwell
Telephone: 541-682-5547
Staff E-Mail: michael.j.penwell@ci.eugene.or.us
S:\CMO\2012 Council Agendas\M120709\S120709A.doc
Attachment A
City Hall Advisory Committee
NameTitle/RoleCompany/Organization
Liz CawoodPresidentCAWOOD
David DoughertyPrincipalDougherty Landscape Architects
Andrew FisherBoard MemberHistoric Review Board
Eric GundersonPrincipalPIVOT Architecture
David MandelblattChairDowntown Neighborhood Assoc.
Mary OttenAccessiblity Committee MemberHuman Rights Commission
Hugh PrichardPartnerPrichard Partners, Inc.
Stephanie SeubertPartnerEvans, Elder & Brown
Brian SmithAssistant V. P. for AdministrationUO Dept. of Finance & Admin.
David SuchartManagement Services DirectorLane County