HomeMy WebLinkAboutItem C: Review of Implementation of Street Bond MeasureEUGENE CITY COUNCIL AGENDA ITEM SUMMARY Eugene Work Session: Review of 2012 Implementation of Bond Measure to Fix Streets and 2013 Pavement Management Report Meeting Date: February 20, 2013 Agenda Item Number: C Department: Public Works Staff Contact: Kurt Corey www.eugene - or.gov Contact Telephone Number: 541 - 682 -8421 ISSUE STATEMENT This work session is an opportunity for the Eugene City Council to review the fourth year of the implementation of Measure 20 -145, the 2008 bond measure to fix streets. To facilitate this review, two documents were prepared: the Citizen Street Repair Review Panel 2012 Report and the independent accountant's report prepared by Isler CPA. These reports are provided as informational items in compliance with the City Council resolution placing the bond measure on the ballot. This work session will also review the 2013 Pavement Management Report. BACKGROUND Council Action History Following considerable study and discussion, including forming a Council Committee on Transportation Funding and convening an ad hoc citizen Street Maintenance Task Force, the council on July 28, 2008, approved Resolution 4953, calling a city election on a measure authorizing the issuance of $35.9 million of general obligation bonds to fund street preservation projects. Eugene voters on November 4, 2008, approved the measure. In the City Council resolution and the information provided to voters, there were specific requirements related to accountability: In order to promote accountability in the use of bond proceeds, the City Manager will contract with an outside auditor to prepare a written report on the use of the bond proceeds on a regular basis. The auditor will ascertain and report on whether the bond proceeds were used for the authorized purposes and in compliance with the restrictions set forth above. The City Manager will provide the report to the council and make the report publicly available. (Resolution 4953, Section H) To further promote accountability and citizen involvement in street preservation projects, the City Manager has advised that he intends to create a street repair review panel. The street repair review panel will prepare a report, separate and distinct from the report prepared by the outside auditor, documenting the City's use of the bond proceeds and noting whether the bond proceeds were used in compliance with the terms of this S:ACMO \2013 Council Agendas \Ml30220 \Sl3O220C.doc Resolution. The City Manager will provide the street repair review panel's report to the council and make the report publicly available. (Resolution 4953, Section I) On April 14, 2010, the City Council held a work session to receive the first annual report from the Street Repair Review Panel (SRRP) and the independent accountant's report. On January 19, 2011, the City Council received the year -two report from the SRRP regarding the implementation of the 2008 bond measure to fix streets. On May 11, 2011, and October 26, 2011, the City Council approved 22 additional streets to be repaired with the projected remaining bond funds, bringing the total streets to be repaired to 54 streets. On February 29, 2012, the City Council received the year -three report from the Citizen Street Repair Review Panel. Street Repair Review Panel In October 2009, a citizen group was formed to evaluate the City's use of the first year of bond proceeds and report whether the bond funds were used in compliance with the council resolution. The 12 community members serving on the 2012 Street Repair Review Panel (SRRP) were: John Barofsky, Howard Bonnett, Janet Calvert, Mel Damewood, Paul Holbo, Steve Lee, Dave Perez, 011ie Snowden, Clayton Walker, Victoria Whitman, Gary Wildish and Sue Wolling. During the past year, the 12- member panel met three times over a three -month period in preparation of the report, which included a physical inspection of the projects completed in 2012. On January 9, 2013, the Street Repair Review Panel unanimously approved its fourth annual report (Attachment A), which included the following conclusion: Based on this limited review and all materials presented to us, we unanimously conclude that the bond proceeds were used for the authorized purposes and in compliance with the limitations and restrictions outlined in Council Resolution 4953. (SRRP 2012 Report, Page 1). The report from the SRRP highlighted the City of Eugene's effort to continually strive to improve the quality, lessen the environmental footprint, and increase the cost efficiency of its projects. Bond projects use warm mix asphalt pavement, reclaimed asphalt materials and in -place recycling to realize environmental, economic, social, and health benefits to the community. The positive economic impacts include the funding of more than 76 full -time equivalent jobs during the period of construction. The 2012 SRRP report recognized the successful renewal of the street bond measure at the polls. On Nov. 6, 2012, Eugene voters resoundingly approved a new, $43 million bond measure to fix streets and fund bicycle and pedestrian projects. Looking to the future, expectations are that construction costs will return to pre- recession levels, which will reduce the likelihood that the City will see much difference between programmed and actual costs for the final year of the bond measure and into the future. The SRRP recognizes that while street bonds provide a partial funding stopgap, they cannot be relied upon as the primary means of funding Eugene's ongoing street repair needs in the future. Additional ways to fund street repair should be reviewed. A web site tracking the bond measure implementation has been established at www.eugene- or.govtgobonds The panel's 2012 report has been placed on the internet, and links to the online S:ACMO \2013 Council Agendas \Ml30220 \Sl3O220C.doc report will be sent to the Neighborhood Leaders Council and other community and business organizations. In preparation of the 2013 report, the Street Repair Review Panel is scheduled to reconvene in the fall, upon completion of the 2013 construction season. Independent Accountant's Report The accounting firm of Isler CPA, who also performed the annual audit of the City's FY12 financial statements, was contracted to perform sufficient agreed upon procedures in order to determine whether the expenditure of general obligation bonds were made in accordance with the purposes and limitations outlined in the street repair bond resolution - namely, that expenditures were: 1. Used only for costs related to street preservation projects, off - street bicycle and pedestrian path preservation projects and payment of bond issuance costs, and not to expand the capacity of the street system; and also, 2. Limited to projects included in Exhibit A to the resolution, unless upon completion of all of the projects listed in Exhibit A, the council adds other street preservation projects to the list in order to utilize unspent bond proceeds. The accountant's procedures were performed for the period December 1, 2011, through November 30, 2012, and were conducted in accordance with attestation standards established by the American Institute of Certified Public Accountants. The independent accountant expenditure testing concluded: All tested expenditures were recorded in the proper account, fund and period and were spent on street projects included in ExhibitA of City Council Resolution No. 4953 or other street preservation projects approved by City Council, as permitted under Resolution 4953. No exceptions were noted. Further, it was the summary conclusion of the independent accountant that, "Based on our limited testing, we noted that the City followed the purpose and limitation of the City Council Resolution #4953." The Isler CPA report is included as Appendix C to the SRRP 2012 Report. The Isler CPA 2012 report has been placed on the internet along with the report of the citizen panel at www.eugene- or.gov /gobonds Pavement Management Report The annual Pavement Management Report is produced to update information and data regarding the City of Eugene's transportation system including improved streets, unimproved streets and off - street shared -use paths. This report provides surface descriptions and associated mileage, reviews current treatment programs and costs, and projects future treatment needs based on several funding scenarios. Currently, Public Works manages 1,328 lane miles (533 centerline miles) of streets, and approximately 43 miles of off - street, shared -use paths within the City limits. This report includes a breakdown of the street transportation system in terms of pavement type, level of improvement, and functional classification. S:ACMO \2013 Council Agendas \Ml30220 \Sl3O220C.doc The 2013 Pavement Management Report was compiled by the Public Works Maintenance Division's Surface Technical Team to provide updated information on the condition of asphalt paving in Eugene using 2012 rating and inventory data. The 2013 Pavement Management Report shows progress has been made on the condition of Eugene's streets, but more work is needed to further reduce the backlog of needed repairs of City streets. Specifically, based on the 2011 ratings, and reported in the 2012 report, the calculated backlog of repairs on improved asphalt streets was $118 million; as of the end of 2012, the current backlog has been calculated to be $100 million. Despite this short -term downward trend the backlog is projected to continue to grow in the long -term unless there is an increase in funding that is both sufficient and sustainable. The report includes an inventory of streets by improvement status and functional classification, details how a pavement management system is used to inspect and rate pavement surfaces, explains Eugene's pavement preservation program, and includes updated information about treatment types and costs. Electronic copies of the 2013 Pavement Management Report are available at www.eugene- or.gov /pw RELATED CITY POLICIES The Council's Goals include "Transportation Initiative: Develop mechanisms to adequately fund our transportation system for cars, trucks, bikes and pedestrians including maintenance and preservation and capital reconstruction." COUNCIL OPTIONS This work session is informational; no action is requested. CITY MANAGER'S RECOMMENDATION This work session is informational; no action is requested. SUGGESTED MOTION This work session is informational; no motion is requested. ATTACHMENTS A. Citizen Street Repair Review Panel 2012 Report, including Auditor's Report B. 2013 Pavement Management Report FOR MORE INFORMATION Staff Contact: Kurt Corey, Public Works Director Telephone: 541 - 682 -8421 Staff E -Mail: Kurt.A.Core @y ci.eugene.or.us S:ACMO \2013 Council Agendas \Ml30220 \Sl3O220C.doc Citizen Street Repair Review Panel 2012 Report Implementation Update for Measure 20 -145 Bonds to Fix Streets OEM& R XING RICO" 'STRE TS � 4 ft__ Public Works Street Repair Review Panel Memorandum Date: January 18, 2013 To: Jon Ruiz, City Manager From: Street Repair Review Panel Subject: Year Four Report of the Street Repair Review Panel uet? B oflds Fixing Eugene's Streets It is our pleasure to present the fourth annual report of the Street Repair Review Panel (SRRP). This panel was formed, and this report was written, in response to the accountability provisions in Measure 20 -145 (2008 bond measure to fix streets). The 12- member panel met three times over a three -month period in preparation of this report, which included a physical inspection of the projects completed in 2012. We reviewed and accepted the report prepared by the City's external auditor (Appendix C) with respect to the City's use of the bond proceeds through November 30, 2012. Based on this limited review and all materials presented to us, we unanimously conclude that the bond proceeds were used for the authorized purposes and in compliance with the limitations and restrictions outlined in Council Resolution 4953. We are also providing a detailed report, prepared at our request and with our approval, from the Public Works staff on the bond projects constructed in 2012. Highlights from our review of the 2012 street bond projects: • 2012 Bond Measure - We draw your attention to the successful renewal of the bond measure at the polls. On Nov. 6, 2012, Eugene voters resoundingly approved a new, $43 million bond measure to fix streets and fund bicycle and pedestrian projects. Despite the economic stresses many are experiencing in Eugene, the measure passed in every ward but one and, overall, by a larger majority than the first measure. We attribute the success at the polls to increased understanding by the electorate of the importance of maintaining our City's transportation infrastructure and to recognition and appreciation by the electorate of the repairs funded by the current bond measure. We appreciate the diligence and competence of the City's Public Works staff in planning and overseeing the improvements in infrastructure achieved by the current bond measure. While street bonds provide a partial funding stop gap, they cannot be relied upon as the primary means of funding Eugene's ongoing street repair needs in the future. Additional ways to fund street repair should be reviewed. • Triple Bottom Line - The City of Eugene continually strives to improve the quality, lessen the environmental footprint, and increase the cost efficiency of its projects. Bond projects use warm mix asphalt pavement, reclaimed asphalt materials and in -place recycling to realize environmental, economic, social, and health benefits to the community. Warm mix asphalt reduces energy consumption and improves workers' health and safety. In -place recycling reduces land filling, material mining, and truck hauling which benefits the environment. It also reduces excavation of existing roadway materials and importation of virgin construction materials which has direct economic benefits, while the traveling public benefits from reduced construction time. It is estimated that using the in -place recycling process for the street bond projects on 24th Avenue, Augusta Street, City of Eugene . 101 E. Broadway, Ste. 400 . Eugene, OR 97401 . 541 -682 -8421 . 541 - 682 -6826 Fax www.eugene- or.gov 2012 SRRP REPORT Riverview Street, and Royal Avenue, eliminated the need to excavate and haul away 22,000 cubic yards of material and eliminated hauling 39,000 tons of new base rock to the site, saving over 3,500 truck trips. • Jobs Impact - Based on the Oregon Department of Transportation Highway Division jobs multiplier model, the 12 bond measure repair projects completed in 2012 conservatively sustained approximately 76 full -time equivalent jobs during the period of construction. • Overall Condition Index (OCI) - All roads in our transportation system age and gradually decline in OCI until, reaching some range of OCI value, every road needs either an overlay or reconstruction. An important program goal is to keep streets from falling into the more expensive reconstruction category and to expend resources early on to preserve the condition of the street. It costs more to rebuild the streets than to maintain them. In 2012, 11.8 lane miles of streets were rehabilitated to keep them from falling into the reconstruction category. • Forecast - By the expiration of the current measure, more street repair work will have been completed than was programmed in the measure. Although our region is not fully recovered from the recession beginning in 2008, the economic climate, leading to low bids during the early years of the current bond measure, has changed. Expectations are that construction costs will return to pre - recession levels, which will reduce the likelihood that the City will see much difference between programmed and actual costs for the final year of the bond measure and into the future. • Additional Projects - In 2011 the council approved 22 additional streets representing 30.7 lane miles to be repaired with bond funds. At this time, the projected cost of the 22 additional streets is $16.8 million. The City plans to construct 10 of the additional street sections in 2013 with remaining bond funds, with the remaining 12 street sections to be constructed between 2014 and 2016 with local gas tax funds. • Active Transportation - The bond measure has allowed meaningful progress toward enacting elements of the Pedestrian and Bicycle Master Plan. Shared -use paths, reconstructed to greater depth and width, will accommodate increased use well into the future. Meanwhile, street preservation often has provided an opportunity to leverage other funds to add bicycle and pedestrian improvements on streets. Thanks to conscientious staff efforts, programmed bond measure projects have incorporated new or wider bicycle lanes, shared lane markings, and improvements in pedestrian facilities. Even though few funds are available for the Pedestrian and Bicycle Master Plan (PBMP), the bond measure has facilitated the construction of some PBMP projects on bond measure streets. • Progress - To date, the use of bond proceeds has allowed the City to repair 66.8 lane miles of streets at a cost of $24.3 million. In addition, $1.9 million has been spent reconstructing 2.3 miles of off - street shared -use paths. • Bottom Line - Many roads are getting fixed, the rate of deterioration has been slowed on others, and the bonds are meeting the objectives of Ballot Measure 20 -145. We appreciate the support and thoughtful responses to our questions provided by Public Works Director Kurt Corey and his staff. The Committee also expresses our appreciation to the voters and taxpayers of Eugene for their support of the bond measure. We believe the voters are getting a good return for their investment Additional information about the Street Repair Review Panel, including action summaries of our meetings and a variety of reports and studies, can be found at www.eugene- or.gov/gobQnds Please feel free to contact any of us for additional information. SRRP Members City of Eugene Staff John Barofsky Dave Perez Kurt Corey Matt Rodrigues Howard Bonnett 011ie Snowden Eric Johnson Mark Schoening Janet Calvert Clayton Walker Eric Jones Tammy Smith Mel Damewood Victoria Whitman Paul Klope Robert Tintle Paul Holbo Gary Wildish Jeff Lankston Jenifer Willer Steve Lee Sue Wolling 2012 SRRP REPORT 2012 Report to the Citizen Street Repair Review Panel TABLE OF CONTENTS INTRODUCTION.............................................................................. ............................... 4 CRITERIA FOR PROJECT SELECTION AND SCHEDULING ....... ............................... 6 FUNDING STATUS AND FORECAST ............................................. ..............................8 24TH AVENUE FROM JEFFERSON STREET TO CHAMBERS STREET ..................10 AUGUSTA STREET FROM 16TH AVENUE FROM 26 AVENUE AND RIVERVIEW STREET FROM SYLVAN STREET TO 16TH AVENUE AND TO THE NORTHBOUND 1 -5 FRANKLIN BLVD OFF RAMP ................................................... .............................11 BREWER STREET FROM GILHAM ROAD TO NORKENZIE ROAD .......................... 12 CURTIS AVENUE FROM NORKENIZE ROAD TO 550 FEET EAST (CUL -DE -SAC). 13 GILHAM ROAD FROM HONEYWOOD STREET TO CRESCENT AVENUE ..............14 GOODPASTURE ISLAND ROAD FROM KINGSLEY ROAD TO 1,250 FEET NORTH OF VALLEY RIVER DRIVE ............................................................. .............................15 ROYAL AVENUE FROM HIGHWAY 99 TO 100 FEET EAST OF WAITE STREET.... 16 SILVER LANE FROM RIVER ROAD TO GROVE STREET ............ .............................17 TANEY STREET FROM BARGER DRIVE TO MARSHALL AVENUE ........................18 TERRY STREET FROM 100 FEET NORTH OF AVALON STREET TO ROYAL AVENUE.......................................................................................... .............................19 WARREN STREET FROM BAILEY HILL ROAD TO TIMBERLINE DRIVE ................ 20 WEST BANK PATH REPAIRS ...................................................... ............................... 21 APPENDIX A (LISTING OF BOND STREETS) ............................... .............................22 APPENDIX B (MAP OF BOND STREETS) ................................... ............................... 24 APPENDIX C (REPORT OF THE INDEPENDENT AUDITOR) ..... ............................... 25 Photos on cover from 2012 projects: Gilham Road paving (top); West Bank Path (lower left); Terry Street (lower right) 2012 SRRP REPORT INTRODUCTION BACKGROUND This report has been compiled for use by the Street Repair Review Panel (SRRP). It is intended to give background on projects included in the 2008 voter - approved Bond Measure 20 -145, the schedule for construction of these projects, and details of bond projects constructed in 2012. The Street Repair Bond is a five -year bond, with construction of bond - funded projects starting in 2009 and bond - funded projects to be complete in 2013. KEY TERMS Bond - Bond Measure 20 -145, Bonds to Fix Streets, approved by Eugene voters in November 2008. In -Place Recycling - A process in which a large piece of equipment called a reclaimer mixes the existing base rock and a portion of subgrade soils with dry cement and water to create a cement - treated base. This process greatly reduces the use of virgin materials and trucking that are needed using conventional remove - and - replace construction techniques. Inlay — An inlay treatment consists of removing a specified depth of the existing pavement surface and repaving that same depth with a new pavement surface. This treatment works well where the pavement distress is isolated to the removed portion of the pavement. At times, the inlay treatment needs to be supplemented with an "overlay" which is when an additional thickness of pavement is placed over the inlaid pavement. An overlay is used when engineering analysis shows that the existing structure does not have sufficient strength to accommodate the projected traffic loading. The term "overlay" is commonly used to describe both the inlay and overlay practices. One of the benefits of performing an inlay rR `A t Milling pavement for inlay on Goodpasture Island Road treatment is that the new pavement surface will match existing adjacent structures and not increase the street cross grade. Another benefit of an inlay is that in the removal of the existing pavement, contractors grind up the old pavement and stockpile the material to be recycled into new pavement. The use of reclaimed asphalt pavement, or "RAP ", has been used for more than 20 years in Eugene. In 2012, approximately 10,800 tons of RAP material (30% by weight) was incorporated into the pavement on bond - funded projects. 2012 SRRP REPORT PPP - Pavement Preservation Program. This is the current capital project program to preserve Eugene's improved street system. The priority for this program is to preserve streets that have not yet degraded to a point where reconstruction is required. Preserving a street through overlay or similar treatment is four to five times more cost effective than waiting to repair a street after it requires reconstruction. This program was initiated in 2003 and, until passage of the 2008 street re air bond was redominatel funded with p 1 p y Paving on Augusta Street local fuel tax and the reimbursement fee component of transportation system development charges. Warm Mix Asphalt - Warm mix asphalt pavement is identical to conventional hot mix asphalt pavement, except that through a special mixing process it is produced at a temperature approximately 50 to 100 degrees cooler than conventional hot mix asphalt. In Eugene, all asphalt concrete producers have retrofitted their plants to produce warm mix asphalt using a water foaming process. The foaming process allows temperature reductions of approximately 50 degrees. This reduction in temperature has several advantages: 1. Reduces energy consumption to produce asphalt concrete, lowering costs and greenhouse gas emissions. 2. Reduces off - gassing (smoke) of asphalt concrete by keeping temperature under the boiling point of "light oils" in the liquid asphalt, benefiting construction workers and the public. 3. Because the light oils are not boiled off, the liquid asphalt coating the rock particles is slightly thicker, which slows the aging process of the asphalt. 4. Reduces the oxidation caused during high temperature production that causes premature aging of the asphalt, which should provide a longer life product. The use of warm mix asphalt pavement is required on City of Eugene projects. SRRP MISSION Per Resolution No. 4953, the SRRP "will prepare a report, separate and distinct from the report prepared by the outside auditor, documenting the City's use of the bond proceeds and noting whether the bond proceeds were used in compliance with the terms of this Resolution." 2012 SRRP REPORT CRITERIA FOR PROJECT SELECTION AND SCHEDULING STREET PROJECTS Street projects to be included in the bond were specifically listed (see Appendix A). All street projects were identified by the Public Works Maintenance Pavement Management System as priorities for repair. In addition, the following criteria were used to select streets for the bond measure: 1. Citizen input with respect to prioritizing major streets in need of reconstruction. 2. Scientific information about needed street rehabilitation and reconstruction from the pavement management system. 3. Geographic distribution throughout the community to ensure all areas of the City receive a benefit from the bond proceeds. Unlike the trends reported in previous years where actual costs were substantially lower than budgeted costs, in 2012 total projected expenses for the bond projects are within 10 percent of the costs originally budgeted in the bond. This is primarily due to increasing construction costs, which is further explained in the Economic Status and Forecast section below. Based on the favorable bidding climate early in the bond and cost reductions due to rehabilitation and reconstruction techniques realized in the first two years of bond construction, the City constructed the majority of the projects prior to 2013. The original bond allowed that if all of the projects listed in the bond measure were completed and there were bond proceeds remaining, the Council may add other street preservation projects to the list. In 2011, the Eugene City Council approved additional streets to be repaired with remaining bond funds (See Appendix A). A list of the street bond projects, their estimated repair cost from the Pavement Management System in 2008 dollars, and the year scheduled for construction is included in Appendix A. For projects completed in 2009 through 2012, the list includes a comparison of programmed costs to actual costs with any difference noted. Differences in total project costs on individual projects will affect the funding available for future projects. The list also includes projected costs for all projects through the end of the bond in 2013, including the streets added to the list by City Council in 2011. The remaining projects from the original bond measure to be constructed in 2013 are Blair Street, Van Buren Street, and a section of Coburg Road. Including streets added by City Council in 2011 to use the remaining bond funds, thirteen street sections with total programmed budget of over $11 million are scheduled for 2013. The City plans to supplement the bond funds with local gas tax funds as necessary to complete the entire list of additional streets Council approved in 2011. 2012 SRRP REPORT OFF- STREET (SHARED -USE) PATH PROJECTS The 2008 bond measure states that the City will allocate not less than $350,000 each year to fund the overlay and reconstruction of existing off - street bicycle and pedestrian paths. These projects were not named in the bond measure, but a list of prioritized projects has been developed. As with streets, Public Works Maintenance performs routine inspection of off - street paths. Information on path condition was cross - referenced with path pedestrian and bicycle usage counts collected by the Public Works Engineering Transportation Planning team. City staff Paving on West Bank Path presented the data to the citizen Bicycle and Pedestrian Advisory Committee (BPAC) and collaboratively developed a prioritized list of off - street path repair projects. This list is included in Appendix A (also see the accompanying bond project map in Appendix B). USE OF OTHER FUNDS IN CONJUNCTION WITH STREET BOND FUNDS The use of street - repair bond funds is limited to the overlay or reconstruction of the driving surface of streets as well as to preserve existing integral elements of the street such as curbs, gutters, sidewalks, on- street bike lanes, traffic signals, street lights, medians, traffic calming devices, and other integral parts of a street preservation project (Council Resolution 4953, Section D). However, there is often a need or an opportunity to complete additional work as part of the construction contracts for street preservation. The additional work may be funded by wastewater and stormwater utility funds, local gas taxes, transportation system development charges, or state and federal grants Wastewater and stormwater utility funds are used to repair and rehabilitate the existing wastewater and stormwater systems, respectively, that underlie much of the city's street system. Making these repairs in coordination with the street bond projects is a cost - effective way to accomplish the work and precludes emergency repairs in the future that would require cutting new pavement. Local gas taxes were used for preliminary engineering conducted in advance of the street bond measure's passage. This assured a quick start of bond measure projects in 2009. Local gas taxes have also been used to include adjacent streets in the street bond project contracts. Transportation system development charges (SDCs) are often used to upgrade existing signal systems during pavement preservation projects. The work typically includes installing new conduit under the pavement to connect the traffic detection loops to the signal controller. 2012 SRRP REPORT SUSTAINABILITY The City of Eugene continually strives to improve the quality, environmental footprint, and cost efficiency of its projects. In 2012, Eugene continued to use warm mix asphalt pavement and in place recycling to meet these sustainability criteria. Warm mix asphalt continued to be specified for all the paving projects in 2011 in place of conventional hot mix asphalt. As explained in the Key Terms section of this report warm mix asphalt provides environmental and human health benefits as well as a potentially longer lasting product. The National Cooperative Highway Research Program ( NCHRP) estimates that there is a CO savings of 12 pounds per ton of pavement using warm mix as compared to hot mix asphalt. The NCHRP also estimates that the use of warm mix asphalt reduces the energy used in the asphalt batch plant by about 30% compared to hot mix asphalt. In -place recycling (see Key Terms) was used on the street bond projects on 24th Avenue, Augusta Street, Riverview Street, and Royal Avenue. It is estimated that using the in -place recycling process for these streets eliminated the need to excavate and haul away 22,000 cubic yards of material and eliminated hauling 39,000 tons of new base rock to the site, saving over 3,500 truck trips for the four streets. The City of Eugene started using the in -place recycling process to realize the environmental, economic and social benefits to the community that can come from this type of process. The reduction in land filling, material mining, and truck hauling all have direct environmental benefits; the reduction in excavating existing roadway materials and importing virgin construction materials have direct economic benefits; and the reduction in construction time has a direct social benefit. Funding Status and Forecast In 2012, construction costs increased significantly over early bond years. For example, according to global energy advisor Poten & Partners, Inc., the average price for asphalt cement in the Portland area in June 2011 was $541 per ton and in June 2012 was $639 per ton, an increase of about 18% (published on the Oregon Department of Transportation (ODOT) website and used to calculate asphalt escalation factors). According to the Construction Costs Forecast by ODOT (published October 2012) ODOT projects that construction costs will continue to increase at a more steady rate rather than with the volatility of recent years, for a variety of reasons: • Extreme volatility in fossil fuel market is not expected, with prices remaining steady over the next few years (with seasonal fluctuations). • Construction materials cost forecasts a "bump up" for the remainder of 2013 with steady increases through 2016 with producer prices overall steady (forecast average change per FY 3.1 % through FY2020). • Machinery /equipment cost forecasts a bump up for the remainder of 2013 and then normal or average prices overall (forecast average change per FY 2.3% through FY 2020). 2012 SRRP REPORT As noted in previous reports to the SRRP, construction bids, innovative treatment technologies, and other variables substantially reduced project costs through the first three years of the bond. The total budget for bond projects constructed in 2009 through 2012 was $30,507,000 (in 2008 dollars); total expenditures were approximately $25,265,000. As noted above, in 2011 City Council approved 22 additional streets to be repaired with any remaining bond funds. At this time, it is projected that the cost of the 22 additional streets is $16.8 million. The City plans to construct 10 of the additional street sections in 2013 with remaining bond funds, with the remaining 12 street sections to be constructed between 2014 and 2016 with local gas tax funds. 2012 Bond Construction Projects The following pages are reports on individual street projects. The total costs for each project listed are estimated as not all of the 2012 construction - related costs have been finalized as of December 1, 2012. 2012 SRRP REPORT In -place road recycling on Augusta Street 24th Avenue from Jefferson Street to Chambers Street Project Description: This project consisted of reconstruction of 24 Avenue from Jefferson Street to Chambers Street in south Eugene. This work on 24th Avenue was combined with a local gas tax funded project to rehabilitate Jefferson Street from 19th Avenue to 24th Avenue and reconstruct Jefferson Street from 25th Avenue to 28th Avenue. Treatment Methodology: Pavement testing recommended the section from Jefferson Street to Chambers Street needed to be reconstructed due to the poor condition of the street surfacing, which was exhibiting load- related cracking distress in the eastbound lane some cracking distress in the westbound lanes, except extensive cracking distress was observed in both lanes from Polk Street to Chambers Street. Rather than reconstruct this street with conventional methods, it was decided to reconstruct this street using the in -place recycling technique (see Key Terms) with the cement - treated base and then paving with 7 inches of warm mix asphalt pavement. Costs: Total project costs, from all funding sources, are estimated at $942,000. Total Bond Funds Programmed to the Project = $ 622,000 Total Projected /Actual Bond Funds Used = $ 934,000 Difference = $ - 312,000 Prior to budgeting for the bond measure, preliminary testing determined this street could be rehabilitated with a mix of inlay, spot repair reconstruction and partial depth reconstruction. Upon scheduling this project for construction, the street had very quickly deteriorated and full depth reconstruction was recommended based on further testing. While the project costs are higher than originally anticipated when the street repair bond was developed, using the reclamation technique for construction was significantly less expensive than a conventional reconstruction, which was estimated to be approximately $1,222,000. Additional Sources of Funding: Stormwater and wastewater utility funds. Project Photos: 24th Avenue pre- construction 24th Avenue post- construction 2012 SRRP REPORT Augusta Street from 16th Avenue from 26 Avenue and Riverview Street from Sylvan Street to 16th Avenue and to the northbound 1 -5 Franklin Blvd off ramp Project Description: This project consisted of reconstruction of Augusta Street from 16th Avenue to 26th Avenue and Riverview Street from Sylvan Street to 16th Avenue and to the northbound 1 -5 Franklin Blvd off ramp in southeast Eugene. This work on Augusta Street was combined with work to rehabilitate 16th and 26th Avenues between Riverview and Augusta using local gas taxes. Treatment Methodology: Augusta and Riverview Streets were in very poor condition with significant fatigue (load related) and block cracking over approximately 80% of the surface. Pavement testing confirmed the need to reconstruct these streets due to the poor condition of the street surfacing. Because of poor subgrade soils and pavement too thin to support collector -level traffic loading, it was decided to reconstruct the streets using the in -place recycling technique (see Key Terms) which creates a cement - treated base by mixing existing materials with dry cement and water. The cement - treated base was then paved with 7 inches of warm mix asphalt pavement. Costs: Total project costs, from all funding sources, are estimated at $1,261,000. Total Bond Funds Programmed to the Project = $1,516,000 Total Projected /Actual Bond Funds Used = $1,121,000 Difference = $ 395,000 Using the reclamation technique for construction was significantly less expensive than a conventional reconstruction as originally anticipated. Additional Sources of Funding: Road capital (traffic calming), local gas tax (16th and 26th Avenues), stormwater utility and wastewater utility funds. Project Photos: Augusta Street pre- construction Augusta Street post- construction 2012 SRRP REPORT Brewer Street from Gilham Road to Norkenzie Road Project Description: This project included reconstruction of Brewer Street in northeast Eugene from Gilham Road to Norkenize Road. Treatment Methodology: Sections of this street were in poor condition and pavement testing and evaluation showed that the west end of the project needed full depth reconstruction and the east end needed partial depth reconstruction (removal of asphalt pavement and a portion of the underlying base rock). Costs: Total project costs, from all funding sources, are estimated at $346,000. Total Bond Funds Programmed to the Project = $146,000 Total Projected /Actual Bond Funds Used = $346,000 Difference = $ - 200,000 In testing this street, it was determined that the subgrade soils and thin pavement were too weak to support construction traffic and future traffic loading and the street needed a more expensive treatment than originally anticipated when the street repair bond was developed. Additional Sources of Funding: Stormwater utility fund. Project Photos: Brewer Street pre- construction 2012 SRRP REPORT Brewer Street post- construction Curtis Avenue from Norkenize Road to 550 feet East (cul -de -sac) Project Description: This project included reconstruction of Curtis Street in northeast Eugene from Norkenzie Road to 550 feet east to the end of the cul -de -sac. Treatment Methodology: Sections of this street were in poor condition and pavement testing and evaluation showed that the street needed partial depth reconstruction (removal of asphalt pavement and a portion of the underlying base rock). Costs: Total project costs, from all funding sources, are estimated at $91,000. Total Bond Funds Programmed to the Project = $38,000 Total Projected /Actual Bond Funds Used = $91,000 Difference = $ - 53,000 In testing this street, it was determined that the subgrade soils and thin pavement were too weak to support construction traffic and future traffic loading and the street needed a more expensive treatment than originally anticipated when the street repair bond was developed. Additional Sources of Funding: None. Project Photos: Curtis Avenue pre- construction Curtis Avenue post- construction 2012 SRRP REPORT Gilham Road from Honeywood Street to Crescent Avenue Project Description: This project included rehabilitation of Gilham Road in northeast Eugene from Honeywood Street to Crescent Avenue. Treatment Methodology: While this street exhibited nearly continuous low to medium severity cracking, pavement testing determined there was sufficient existing pavement and base aggregate to rehabilitate this street by removing and repaving ( "inlay ") 4 inches of asphalt pavement. Costs: Total project costs, from all funding sources, are estimated at $493,000. Total Bond Funds Programmed to the Project = $305,000 Total Projected /Actual Bond Funds Used = $469,000 Difference = $- 164,000 In order to remove enough depth of pavement to eliminate reflective cracking from occurring in 5 to 7 years, a thicker depth of pavement needed to be removed than originally anticipated when the Street Repair Bond was developed, which increased the project cost. Additional Sources of Funding: Stormwater and wastewater utility funds Project Photos: k Gilham Road post- construction 2012 SRRP REPORT Gilham Road pre- construction Goodpasture Island Road from Kingsley Road to 1,250 feet north of Valley River Drive Project Description: This project included the rehabilitation of Goodpasture Island Road from Kingsley Road to 1,250 feet north of Valley River Drive (near Delta Ponds Bridge) in north Eugene. Treatment Methodology: Pavement testing confirmed that this section could be rehabilitated with an inlay treatment (remove existing and repave same pavement thickness) of 2 inches of asphalt pavement. There were some sections that only required a seal treatment. Costs: Total project costs, from all funding sources, are estimated at $196,000. Total Bond Funds Programmed to the Project = $ 448,000 Total Projected /Actual Bond Funds Used = $ 193,000 Difference = $ 255,000 Because some sections only required a seal treatment, project costs were less than anticipated in 2008. Additional Sources of Funding: Stormwater and wastewater utility funds. Project Photos: 2012 SRRP REPORT Goodpasture Island Road pre- construction Goodpasture Island Road post- construction Royal Avenue from Highway 99 to 100 feet east of Waite Street Project Description: This project consisted of reconstruction of Royal Avenue from Highway 99 to 100 feet east of Waite Street in northwest Eugene. Treatment Methodology: Royal Avenue east of Waite Street was in poor condition and had insufficient structure to support arterial -level traffic loading. Based on the condition and projected traffic loading, pavement testing supported full depth reconstruction of this street. It was decided to reconstruct this street using the in -place recycling technique (see Key Terms) which creates a cement - treated base by mixing existing materials will dry cement and water. The 9- inch -thick cement - treated base was then paved with 6 inches of warm mix asphalt pavement. Costs: Total project costs, from all funding sources, are estimated at $1,030,000. Total Bond Funds Programmed to the Project = $1,565,000 Total Projected /Actual Bond Funds Used = $1,022,000 Difference = $ 543,000 Existing materials and soils were found to support the in -place recycling technique which was significantly less expensive than a full depth reconstruction repair as originally anticipated when the street repair bond was developed Additional Sources of Funding: Stormwater and wastewater utility funds. Project Photos: Royal Avenue pre- construction 2012 SRRP REPORT Royal Avenue post- construction Silver Lane from River Road to Grove Street Project Description: This project consisted of repairing Silver Lane from River Road to Grove Street in north Eugene. Treatment Methodology: Silver Lane was in fair condition and pavement testing supported rehabilitating the street with an inlay treatment (see Key Terms, above) with full depth reconstruction at isolated spots where base failures were evident. Costs: Total project costs, from all funding sources, are estimated at $567,000. Total Bond Funds Programmed to the Project = $ 305,000 Total Projected /Actual Bond Funds Used = $ 450,000 Difference = $ - 145,000 In order to remove enough depth of pavement to eliminate reflective cracking from occurring in 5 to 7 years, a thicker inlay treatment depth of the pavement was needed than originally anticipated when the street repair bond was developed, which increased the project cost. Additional Sources of Funding: Stormwater and wastewater utility funds, and transportation system development charges. Project Photos: Silver Lane pre- construction Silver Lane post- construction 2012 SRRP REPORT Taney Street from Barger Drive to Marshall Avenue Project Description: This project consisted of rehabilitating Taney Street from Barger Drive to Marshall Avenue in north Eugene. Treatment Methodology: Taney Street was in fair condition and pavement testing supported rehabilitating the street with an inlay treatment (see Key Terms, above) with full depth reconstruction at isolated spots where base failures were evident. Costs: Total project costs, from all funding sources, are estimated at $496,000. Total Bond Funds Programmed to the Project = $ 349,000 Total Projected /Actual Bond Funds Used = $ 483,000 Difference = $ - 134,000 In order to remove enough depth of pavement to eliminate reflective cracking from occurring in 5 to 7 years, a thicker inlay treatment depth of the pavement was needed than originally anticipated when the street repair bond was developed, which increased the project cost. Additional Sources of Funding: Stormwater and wastewater utility funds, and transportation system development charges. Project Photos: 2012 SRRP REPORT Taney Street pre- construction Taney Street post - construction Terry Street from 100 feet north of Avalon Street to Royal Avenue Project Description: This project consisted of rehabilitating Terry Street from 100 feet north of Avalon Street to Royal Avenue in west Eugene. Treatment Methodology: Terry Street had a significant amount of medium severity cracking with some areas of high severity cracking. A mix of partial depth reconstruction and inlay treatment were used to rehabilitate this pavement. Costs: Total project costs, from all funding sources, are estimated at $385,000. Total Bond Funds Programmed to the Project = $ 978,000 Total Projected /Actual Bond Funds Used = $ 374,000 Difference = $ 604,000 When the street repair bond was developed, it was anticipated that this section of Terry Street would need full or partial depth reconstruction. Based on pavement testing, it was determined only the northbound side of the street on the south half of the project needed partial depth reconstruction. The rest of the street only required an inlay treatment, significantly reducing the overall project cost. Additional Sources of Funding: Stormwater and wastewater utility funds, and transportation system development charges. Project Photos: 2012 SRRP REPORT Terry Street pre- construction Terry Street post- construction Warren Street from Bailey Hill Road to Timberline Drive Project Description: This project consisted of rehabilitating Warren Street from Bailey Hill Road to Timberline Drive in southwest Eugene. Treatment Methodology: Warren Street had a significant amount of cracking on the southern end of the project. There were areas with cracking elsewhere along the project, although primarily in the northbound lane. Poor quality gravel base was encountered beneath the asphalt pavement during pavement testing. Based on the pavement testing it was determined that a 5 inch deep inlay treatment was needed, with full depth spot repairs where the pavement and base had failed. Costs: Total project costs, from all funding sources, are estimated at $460,000. Total Bond Funds Programmed to the Project = $ 217,000 Total Projected /Actual Bond Funds Used = $ 452,000 Difference = $ - 235,000 The depth of distressed pavement to be removed with the inlay treatment was deeper than was anticipated and more full depth spot repairs were needed than originally anticipated when the street repair bond was developed increasing the project costs. Additional Sources of Funding: Stormwater utility funds and transportation system development charges. Project Photos: Warren Street pre- construction 2012 SRRP REPORT Warren Street post- construction West Bank Path Repairs Project Description: This project replaced the existing asphalt surface with a concrete surface on the West Bank Path from the Greenway Bike Bridge to Stephens Drive. Treatment Methodology: The existing asphalt path was cracking due to expansion and contraction of the underlying soils. Sections of the path that were deemed to be stable were overlaid with 6 inches of concrete reinforced with structural fibers. Where the existing path was experiencing severe cracking and movement the existing path surface was removed and the path was stabilized with additional base rock and /or reinforcement. Structural fibers were incorporated into the new concrete path to help prevent cracking due to soil expansion and contraction. The pavement structure thickness is based on the soil conditions and use of the path by emergency and maintenance vehicles. Costs: Total project costs, from all funding sources, are estimated at $361,000. Total Bond Funds Programmed to the Project = $350,000 Total Projected /Actual Bond Funds Used = $361,000 Difference = $ - 11,000 Project Photos: 2012 SRRP REPORT West Bank Path post- construction West Bank Path pre- construction APPENDIX A 2012 Report from Engineering to the Citizens Street Repair Review Panel 5 -Year Street Bond Proiect List - Costs and Forecast Project Bailey Hill Rd 18th Ave East Side Of 8 proposed Programmed Revised Projected/ Over / (Under) Map # Street name From To Ward(s) Treatment Cost (2008) programmed Actual Cost programmed 15 Goodpasture Is Rd Norkenzie Rd Delta Hwy Bride 5 Overlay $ 367,000 Cost $ 435,000 Cost U. - tinn Year 9nnq 6 Bailey Hill Rd 18th Ave East Side Of 8 Reconstruct/Overlay $ 1,866,000 $ 1,866,000 $ 883,000 $ (983,000) 14 Goodpasture Is Rd Bridge Over Slough Bertelsen 5 Reconstruct/Overlay $ 1,319,000 $ 1,319,000 $ 689,000 $ (630,000) 15 Goodpasture Is Rd Norkenzie Rd Delta Hwy Bride 5 Overlay $ 367,000 $ 367,000 $ 435,000 $ 68,000 20 Railroad Blvd Van Buren Chambers 7 Overla $ 421,000 $ 421 $ 398,000 $ 23,000 construction rear ZUUy iocais= Z,bb4,000 - P Z,b04,000 S 7,17b,000 S (twa,000) r n�rr „mri n veer gnin 1 18th Ave 510' East Of Chambers City View 1 Reconstruct/Overlay $ 1,733,000 $ 1,733,000 $ 1,333,000 $ (400,000) 14 Goodpasture Is Rd Bridge Over Slough Kingsley Rd 5 Reconstruct/Overlay $ 1,319,000 $ 1,319,000 $ 689,000 $ (630,000) 1750 -feet North of Valley River Dr 1250 -feet North of Valley River Dr 16 Harlow Rd 1 -5 Coburg 4 Reconstruct/Overlay $ 1,202,000 $ 1,202,000 $ 889,000 $ 313,000 18 Patterson E 13th Ave 23rd Ave 3 Reconstruct $ 2,134,000 $ 2,134,000 $ 1,285,000 $ (849,000) 2 18th Ave Hil and Patterson 1 3 23rd Ave Hil and Patterson 1 3 29 Willamett e St 306' North Of 29th Ave 140' South Of 29th Ave 2 1 Reconstruct $ 405,000 $ 405,000 $ 550,000 $ 145,000 29 Willamette St 46th Ave 152nd Ave 2 10verlay 1 $ 500 1 $ 500 1 $ 412 $ 88 000 construction 7earzu iocais= zo t,Zeui,uuu zo r,zas,uuu 4. b,7bu,uuu 4. tz,7sb,uuul r n�rr „mri n veer gnii 2 18th Ave Patterson Washington 1,3 Reconstruct/Overlay $ 2,052,000 $ 2,052,000 $ 1,773,000 $ (279,000) 5 Alder Broadway 18th Ave 3 Reconstruct/Overlay $ 964,000 $ 964,000 $ 1,190,000 $ 226,000 9 Coburg Rd 850' North Of Cal Young 450' North Of 1 -105 Off Ram 4 Overlay $ 1,479,000 $ 1,479,000 $ 1,457,000 $ (22,000) 11 Conger St 7th Ave 11th Ave 7 Overlay $ 147,000 $ 147,000 $ 190,000 $ 43,000 17 Hil and St E 24th Ave 34th Ave 2,3 Reconstruct $ 2,900,000 $ 2,900,000 $ 1,360,000 $ 1,540,000 19 Pearl 4th Ave 200' North Of Broadwa 7 Reconstruct/Overlay $ 470,000 $ 470,000 $ 667,000 $ 197,000 21 River Rd Horn Ln Railroad 7 !Overlay $ 2,000,000 $ 2,000,000 $ 1,118,000 $ 882,000 29 Willamette St 140' South Of 29th Ave 46th 2 ReconstrucUOverla $ 2,254,000 $ 2,254,000 $ 1,755,000 $ 499,000 30 Wilson St W 5th Ave W 7th Ave 1 7 10verlay $ 100 1 $ 100 1 $ 81 $ 19 000 construction Yearzu99 iocais= 4. iz,3bb,uuu J 74sbb,000 J Y,OY7,000 ri (.,110,000) r n�rr „mri n veer gniq 4 24th Ave Jefferson Chambers 1 Reconstruct/Overlay $ 622,000 $ 622,000 $ 934,000 $ 312,000 31 Augusta St 16th Ave 26th Ave 3 Reconstruct $ 1,516,000 $ 1,516,000 $ 1,121,000 $ (395,000) 23 Riverview St Sylvan 16th Ave 22 Franklin Off Ramp 247' South Of Franklin Off Ramp 8 Brewer St Gilham Rd Norkenzie Rd 5 Reconstruct/Overlay $ 146,000 $ 146,000 $ 346,000 $ 200,000 12 Curtis Ave 550' East Of Norkenzie Norkenzie 5 Overlay $ 38 $ 38 $ 91,000 $ 53,000 13 Gilham Rd Honeywood St Crescent 5 Overlay $ 305,000 $ 305,000 $ 469,000 $ 164,000 14 Goodpasture Is Rd Kingsley Rd 1250 -Feet N of Valley River Drive 5 Overlay $ 448,000 $ 448,000 $ 193,000 $ (255,000) 24 Royal Ave Hwy 99 100' East Of Waite St 8 Reconstruct $ 1,565,000 $ 1,565,000 $ 1,022,000 $ (543,000) 25 Silver Ln River Rd Grove 7 Overlay $ 305,000 $ 305,000 $ 450,000 $ 145,000 32 Taney St Barger IMarshall 6 Reconstruct $ 349,000 $ 349,000 $ 483,000 $ 134,000 26 Terry St 1100' North Of Avalon St Royal 6 Reconstruct/Overlay $ 978,000 $ 978,000 $ 374,000 $ (604,000) 28 Warren St Bailey Hill ITimberline Dr 8 1 ReconstrucVOverla $ 217 $ 217 $ 452,000 $ 235,000 VOns RUG[IOn rear &U 1,4 locals = y 0,40V,000 ,D 0,40&,000 0 0 0 (0- r-tn-tinn Year gnin *Th- ctr-tc -ra arirtart by (.it,, rm -i1 anrt -ra nmt Hart of tha mrimi -I Rmnrt KA-ci ira 7 Blair Blvd 2nd Ave Monroe 7 Reconstruct/Overlay $ 1,228,000 $ 1,300,000 $ $ 27 Van Buren RR Crossing Blair Blvd 7 Reconstruct $ 305,000 $ 388,000 $ $ 9 Coburg Rd Crescent South Onramp Beltline 4 Overlay $ 515,000 $ 515,000 $ $ 33 5th Avenue* High Street Blair Street 7 ReconstructlOverlay $ 2,000,000 $ $ 34 5th Avenue* SS HWY 99 ES Bailey Hill Rd 7,8 Reconstruct $ 1,900,000 $ $ 36 40 49 10th Avenue* Broadway* Olive Street* WS Olive St WS Lincoln St NS 10th Ave WS Jefferson St ES Monroe St NS 13th Ave 7 Reconstruct $ 922,000 $ $ 37 18th Avenue* Washington Street 510' East of Chambers 1 Reconstruct $ 2,800,000 $ $ 39 Alder Street* SS 18th Ave NS 24th Ave 3 Reconstruct $ 1,043,000 $ $ 41 Coburg Road* City Limits Crescent Ave 4,5 Overlay $ 334,000 $ $ 47 Hil and Street* SS E Broadway i S E 11th Ave 3 Overla $ 329,000 $ $ 54 Willamette Street* INS 19th Ave ISS DRWY 2415 1 1 10verlay $ 419 $ $ I nese sneers were aooeU oy i,ny i,owtcu anti "onstruction rear w t.s totals = a /,o4b,ouu a 7 a - a were not part of the original Bond Measure 2012 SRRP REPORT APPENDIX A 2012 Report from Engineering to the Citizens Street Repair Review Panel 5 -Year Street Bond Project List - Costs and Forecast Project 8th Avenue* WS Lincoln St WS Monroe St 7 Proposed Programmed Revised Projected/ Over / (Under) Map # Street name From To Ward(s) Treatment Cost (2008) Programmed Actual Cost Programmed 42 Donald Street* SS E 46th Ave NS Fox Hollow Rd 2 Overlay Cost $ Cost Construction Year 2014 - 2016 (paid for with Local Gas Tax Funds) * These streets were added by City Council and were not part of the original Bond Measure 35 8th Avenue* WS Lincoln St WS Monroe St 7 Reconstruct Programmed $ 643,000 $ $ 38 46th Avenue* WS Donald St ES Willamette St 2 Reconstruct Cost (2008) $ 257,000 $ $ 42 Donald Street* SS E 46th Ave NS Fox Hollow Rd 2 Overlay $ 763,000 $ $ 43 Donald Street* Willamette St 40th Ave 2 Reconstruct/Overlay $ 500,000 $ $ 44 Friendly Street* NS W 24th Ave NS W 28th Ave 1 Overlay $ 346,000 $ $ 45 Garden Way* SS Harlow Rd S 110 Sisters View A 4 Overlay $ 609,000 $ $ 46 Harris Street* 18th Ave 28th Ave 3 Reconstruct/Overlay $ 1,738,000 $ $ 48 Marshall Avenue* Hughes Echo Hollow Rd 6 Overlay $ 556,000 $ $ 50 Roosevelt Blvd.* Danebo Rd Terry St 8 Overlay $ 371,000 $ $ 51 Terry Street* Olympic Circle Barger 6 Overlay $ 264,000 $ $ 52 River Way* SS Valley River Dr SS Cul -de -Sac 5 Reconstruct/Overlay $ 383,000 $ $ _Valley 53 Willakenzie Rd* ES Bogart Ln ES Coburg Rd 4 Overlay $ 593,000 $ $ * These streets were added by City Council and Construction Year 2014 -2016 Totals = $ $ 7,023,000 were not part of the original Bond Measure Off - Street (Shared Use) Path Project List Project Off - Street Path JVan Buren St. lChambers St. 1 1 Proposed Programmed Revised Projected/ Over / (Under) Map ID Project From To Ward(s) Treatment Cost (2008) Programmed Actual Cost Programmed 350,000 1 $ 350,0001 $ 361,000 1 11,000 Construction Year 2013 Cost Cost Construction Year 2009 A JAmazon Path 11 9th Ave 131 st Ave 1 3 lReconstruct 1 $ 648,000 1 $ 648,000 1 $ 730,000 1 $ 82,000 Construction Year 2010 B IFern Ridge Path JVan Buren St. lChambers St. 1 1 1 Reconstruct $ 410,000 $ 410,000 $ 405,000 $ (5,000) C Westmoreland Connector Path Polk Street 500' West of Polk St. 1 1 1 Reconstruct Construction Year 2011 D I South Bank Path Maurie Jacobs Park IRiver Play Park 1 7 lReconstruct 1 $ 367,000 1 $ 367,000 1 $ 466,000 1 $ 99,000 Construction Year 2012 E JWest Bank Path I Greenway Bridge Istephens Dr. 1 7 lReconstruct 1 $ 350,000 1 $ 350,0001 $ 361,000 1 11,000 Construction Year 2013 F ISouth Bank Path IRiver Play Park JDeFazio Bridge 1 7 lReconstruct I $ 350,000 1 $ 350,000 $ - I $ Total Off - Street Path Project Costs = $ 2,125,000 $ 2,125,000 $ 1,962,000 $ 187,000 Summary of Bond Funds Total Street Projects in 2008 Dollars $ 30,850,000 Total Off - Street Path Projects $ 2,125,000 Bond Issuance Costs $ 130,000 Inflation $ 2,795,000 Total Bond Funds $ 35,900,000 Summary of Bond Revenue and Expenditures Bond Funds Available for Construction Costs (amount above less issuance costs) $ 35,770,000 Projected Street and Shared Use Path Expenditures thru FY13 $ 36,662,000 Projected Bond Planning /Pre - Design Expenditures $ 903,000 Sub -Total Bond Costs thru FY13 $ 37.565.000 Projected Local Gas Tax Funding Needed to Supplement Bond Funds thru FY13 $ 1,795,000 Projected Local Gas Tas Funding Needed in FY14 - FY16 $ 7,023,000 Projected Total Local Gas Tax Funding to Complete Projects $ 8,818,000 2012 SRRP REPORT 23 APPENDIX B Citizens Street Repair Review Panel 2012 Report Eugene Street Bond Project List p I December 2012 b,aako, ok o. \N•• Cl— LakeRe stirs J e. �, ee�����eRa I._._ S?� f_• _"'+'' 1 � I �! 51 Ward 6 26 50 is zs a � J 324 NPa,k 4 no,�s� 48 r "I J 24 21 D 20 Ward 7 a 4 w„ a 27 D w, 30 � w „na�m 11 .e a� Ward 8 3 Wfetnave 9 1 ` e wvm 40 a36 - ea `� o C'� D a A 2 Ward I 54\ «� g 3 _ Ward 3 1 17 w roe .. �_ _.. � • iL„. �..� • ;_.! f'—••1.._� _ �� _ �s ���o. � ss,aa� � 9 sQ ; ✓'�� —s i y W:1 °._ ! �j w3s-- 43 Legend Council Ward Construction Year 1 2009 2 2010 3 2011 4 —2012 5 —2013 6 City Streets 7 �•_� Eugene UGB 8 R,d by Cfty of Eugene M Eng I nfa Teem, December 2012 (Ref# 1112 1667) 29 1 �e r ♦.� ��a °a ��1'i _.._.._. 42 f 1 608o 1 FIXING E( "Wi fTREM 1.._..I N 1�1 � 25 05 Miks ����.a•�A e 41 ►r 7 � 9 tl 12 ' °4 15 Ward 5 10 if w Ward 4 + 45 z i -� r [gut INDEPENDENT ACCOUNTANT'S REPORT McQ!L REYALL - ;, E �McGladrey ON APPLYING AGREED -UPON PROCEDURES To Jon Ruiz, City Manager City of Eugene Eugene, Oregon We have performed the procedures enumerated below, which were agreed to by the City of Eugene ( "City "), solely to assist you in connection with the determination of whether the expenditure of general obligation bond funds approved for issuance through voter's approval of Ballot Measure 20 -145 were expended in accordance with the purposes and limitations outlined in City Council Resolution No. 4953; namely that such expenditures were: a) used only for costs related to street preservation projects, off- street bicycle and pedestrian path preservation projects and payment of bond issuance costs and not to expand the capacity of the street system; and b) limited to projects included in Exhibit A to the Resolution unless upon completion of all of the projects listed in Exhibit A the Council adds other street preservation projects to the list in order to utilize unspent bond proceeds. This agreed -upon procedures engagement was conducted in accordance with attestation standards established by the American Institute of Certified Public Accountants. The sufficiency of these procedures is solely the responsibility of those parties specified in this report. Consequently, we make no representation regarding the sufficiency of the procedures described below either for the purpose for which this report has been requested or for any other purpose. All procedures were performed for expenditures incurred between December 1, 2011 and November 30, 2012. All procedures we performed were limited to documentation and information supplied to us by the City, as follows: • An Excel spreadsheet detailing all payments made, charges allocated and /or invoices received by the City for expenditures related to the use of the bond proceeds • Copies of Resolution No. 4953 and Ballot Measure 20 -145 • Copies of bids and contracts issued by the City for any projects to be completed using the bond proceeds • Copies of supporting documentation including, but not limited to, invoices, cancelled checks, payroll records, certifications of payments and bank statements; and • Copies of the City's general ledger detail for the bond fund accounts, as needed The procedures we performed and the associated findings are as follows: (1) Expenditure testing. From December 1, 2011 through November 30, 2012, total expenditures for the projects funded by the bond proceeds were $7,492,730 per the City's general ledger detail of the bond fund. We tested $3,712,383, or 50 %, of those expenditures. All tested expenditures were supported by appropriate documentation such as invoices from vendors, certifications of payment, payroll records, signed contracts, and photographs of the work in progress. All tested expenditures were recorded in the proper account, fund and period and were spent on street projects included in Exhibit A of City Council Resolution No. 4953 or other street preservation projects approved by City Council, as permitted under Resolution 4953. No exceptions were noted. 2012 SRRP REPORT City of Eugene Street Bonds - agreed -upon procedures Page 2 (2) Bond proceeds and project expenditures. The following is a summary of bond proceeds and project expenditures from inception of the Street Bond project to November 30, 2012: From Issuance to 12/1/2009 12/1/2010 12/1/2011 11/30/2009 11/30/2010 11/30/2011 11/30/2012 Total Bond proceeds $ 2,795,000 $ 5,555,000 $ 9,690,000 $ 7,460,000 $ 25,500,000 Project expenditures 2,682,749 5,737,236 9,631,111 7,492,730 25,543,826 (3) As of November 30, 2012 the City had $4,000,000 outstanding on the line of credit facility ($7,460,000 in proceeds plus interest of $4,565 less $3,464,565 repaid) with $10,400,000 in authorized borrowing remaining on the bond ($35,900,000 authorized less $25,500,000 in proceeds). Based on our limited testing, we noted that the City followed the purpose and limitation of the City Council Resolution 4953. We were not engaged to and did not conduct an audit, the objective of which would be the expression of an opinion on the financial records. Accordingly, we do not express such an opinion. Had we performed additional procedures, other matters might have come to our attention that would have been reported to you. This report is intended solely for the information and use of the City Manager of the City of Eugene, and is not intended to be and should not be used by anyone other than this specified party. Isler CPA JkLt CPA Eugene, Oregon December 20, 2012 2012 SRRP REPORT 2013 PAVEMENT MANAGEMENT REPORT An Update on Asphalt Pavement Conditions and Programs (2012 Rating & Inventory Data) 88118nds FAX /NC EUCFW� STRFM f "s I Approximately 423 Lane N e } L_ Prepared by: Public Works Maintenance Surface Technical Team 1820 Roosevelt Blvd. Eugene, OR 97402 RA, Mgt For comy or 11 Hlfinriral and Vrojesied Fonding impe[IS to Totai Syrtem Vr— an 1 �w .......... - .. ��na ivmn amW �. •.u.m.mn E�narx nanar wogs m Smas Eagsrn UW 196.E Rabaf Cover Photos (top left clockwise): GO BONDS, Asphalt distress photos, System condition index graph, Completed pavement preservation projects map 2002 to2012. EXECUTIVE SUMMARY The annual Pavement Management Report is produced to update information and data regarding the City of Eugene's transportation system including improved streets, unimproved streets and off - street shared -use paths. This report provides surface descriptions and associated mileage, reviews current treatment programs and costs, and projects future treatment needs based on several funding scenarios. The transportation system is conservatively estimated to represent a $500 million public asset. This asset is typically described in lane miles and /or centerline miles. Currently, Public Works manages 1328 lane miles (533 centerline miles) of streets, and approximately 43 miles of off - street shared -use paths within the City limits. This report includes a breakdown of the street transportation system in terms of pavement type, level of improvement, and functional classification. Comparative statistical data includes both lane miles and centerline miles. Street (and off - street shared -use path) condition data are collected by Public Works Maintenance staff through on -site inspections. An Overall Condition Index (OCI) score is then generated using CenterLine, the current Pavement Management System (PMS) used by the City. The CenterLine analysis helps establish efficient treatment requirements and identify financial implications of various response strategies. The PMS also provides street inventory and condition trends using 25 years of street condition information. The current estimated street repair backlog on improved asphalt streets at the end of 2012 is $100 million Because street repair funding levels have not kept pace with rehabilitation needs, the City established a local gas tax in 2003 for a pavement preservation program (PPP). In 2008 a $35.9 million, five -year bond measure was approved by voters and another five -year bond for $43 million was approved by voters in 2012. Between these funding sources more thanl26 streets in Eugene are identified to be repaired by 2018. The revenues from the local gas tax and the first bond measure have helped reduce the backlog of street repair projects. Specifically, based on the 2011 ratings and reported in the 2012 Pavement Management Report the calculated backlog of repairs on improved asphalt streets was $118 million; as of the end of 2012 the current backlog has been calculated to be $100 million. In addition to the infusion of local gas tax and bond funding, other factors have contributed to the current status of the backlog: Several projects previously defined as needing to be reconstructed have been redesignated for overlay treatment after detailed testing was performed. An overlay treatment is much less expensive than a reconstruct treatment and can provide a comparable service life if the base is properly designed and undamaged. In recent years, the cost of projects has been lower than anticipated. However, according to the Construction Costs Forecast (ODOT, October 2012) costs will continue to increase at a more steady rate rather than with the volatility of recent years. Changes in costs for construction materials and labor will affect long -term backlog estimates. • In 2009 the City was awarded approximately $3 million of federal American Recovery and Reinvestment Act (ARRA) funds that were earmarked for projects constructed in 2010. This "bought down" the backlog in the short term, but because the ARRA funds were one -time funding, they will not result in a significant ongoing or cumulative effect. EXECUTIVE SUMMARY — ( continued) New construction techniques such as in -place recycling (also known as in -place cement treated base) which strengthens existing roadbed materials for reuse have been successfully used in place of conventional reconstruction techniques resulting in substantial cost savings. • There has been an increase in inventory of improved streets through capital improvement projects (CIP), privately engineered public improvements (PEPI) and jurisdictional transfers. Overall, even though the backlog figure declined in 2012, the current level of funding -- including the two bond measures -- is insufficient to stabilize the backlog long term. Annually, a number of streets needing a less expensive treatment are falling into a more costly treatment category due to lack of funding to repair them. It is also important to note that the backlog estimate is limited to improved asphalt streets. It does not take into account the repair needs for concrete streets, unimproved streets, sidewalks, off - street shared -used paths, or other elements of the transportation system. The 2012 report uses three funding scenarios to project treatment needs and costs over a 10 -year period. The analyses for all three scenarios use costs updated by Engineering in 2011 and are adjusted to include a 2% inflation factor. Following is a summary of the analyses: • Maintaining the current level of funding, including the 2008 and 2012 bond measures, results in a total projected backlog of $238 million in 10 years. Last year, prior to approval of the 2012 bond, the projected 10 -year backlog was $264 million. Increasing the funding level to $12 million annually would prevent arterials and collectors currently from falling into the reconstruct range and eliminate the reconstruct backlog for arterial and collector streets in 10 years. Prior to this year's report, these results required a funding level of $15 million annually. Increasing the funding level to $19 million annually would prevent any street from falling into the reconstruct range and eliminate the total reconstruct backlog in 10 years. Prior to this year's report, these results required a funding level of $18 million annually. Due to the substantial and increasing backlog in Residential treatment needs (residential streets account for approximately 64% (lane miles) of the system) additional funding is required to achieve the same results as in previous years. 2 SCOPE OF THIS REPORT This report is made up of four primary sections: Street Inventory: The street inventory is discussed including improvement status and functional classification definitions. Pavement Management System (PMS): A brief history and description of the Pavement Management System used by the City is discussed, including rating methodology, pavement inspection frequency, pavement conditions described by the Overall Condition Index (OCI), specific distress definitions and the resulting reports. Pavement Preservation Program (PPP): The Pavement Preservation Program is highlighted in this report, including Maintenance and Engineering Division roles, treatment types and estimated unit costs, sustainable construction, current, historical and projected funding, unimproved streets, projected funding, project prioritization, and off - street shared -use paths. Projects: This section includes completed and future project lists and maps, including a list and map of the projects identified in the 2012 bond measure. EUGENE'S STREET INVENTORY The City of Eugene has jurisdictional responsibility for many different types and classifications of transportation facilities. Many factors such as age, development type, traffic loads, use, and future transportation needs affect the maintenance and rehabilitation planning for the system. The segment inventory component of the PMS system allows a reporting of both centerline miles (intersection to intersection) and lane miles of each segment of the system. While commonly used in reporting distance, centerline miles do not relate equally across streets of different widths or different number of lanes. For this report, comparisons typically are shown both in centerline and 12- foot -wide lane miles unless otherwise noted. Improvement Status For purposes of establishing budget allocations and rehabilitation priorities, and performing maintenance activities based on established maintenance policies, the City of Eugene divides the street inventory into two distinct categories: Improved streets are those which have been fully designed for structural adequacy, have storm drainage facilities provided which include curbs and gutters, and have either an asphalt concrete (AC) or a Portland cement concrete (PCC) surface. Typically, these streets were either fully improved when the area was developed and paid for by the developer, or were improved through a local improvement district (LID) and paid for in part by the abutting property owners. In some cases a street may have been fully improved while under state or county jurisdiction and then surrendered to the City. Improved streets receive the highest level of ongoing maintenance and are eligible for rehabilitation funding through Eugene's Capital Improvement Program (CIP) and Pavement Preservation Program (PPP). Unimproved streets are those with soil, gravel, or asphalt mat surfaces that have typically evolved to their existing state, have not been structurally designed, and have few if any, drainage facilities and no curbs or gutters. Typically, an unimproved street must be fully improved through a local improvement district, funded in part by the abutting property owners before a higher level of service will be provided (see "City of Eugene Street Maintenance Policy and Procedure Manual" for levels of maintenance service). Unimproved streets receive a low level of ongoing maintenance limited primarily to emergency pothole patching (three inches or greater in depth) and minimal roadside ditch maintenance. To address the growing number of potholes on City streets, the City Council augmented the street repair budget with General Fund allocations for a total of $2.3 5 million from FY 2009 through FY 2011. Subsequently, Public Works has allocated $200,000 per year from Road Fund for enhanced pavement repairs. The Maintenance Division has addressed potholes by either filling individual potholes or by performing maintenance overlays over entire street segments. During the past five years more than 75 unimproved streets, representing more than 23 lane miles, have been resurfaced as a temporary treatment. In addition, several unimproved streets have been brought up to full urban street standards through assessment projects, attributable in part to more flexible design standards. The following tables categorize Eugene's Improved and Unimproved Street System in Centerline Miles and 12 -foot Lane Miles by Pavement Type and by Functional Class. IMPROVED SYSTEM As halt ACP Asphalt over Concrete (APC ) Concrete (PCC) Gravel Undeveloped Total Miles 12' Lane Miles Miles 12' Lane Miles Miles 12' Lane Miles Miles 12' Lane Miles Miles 12' Lane Miles Miles 12' Lane Miles Major Arterial 13.12 59.11 0.03 0.16 1.38 2.84 0 0 0 0 14.53 62.11 Minor Arterial 60.61 203.74 2.23 7.38 3.73 11.81 0 0 0 0 66.57 222.92 Major Collector 30.18 92.72 1.16 3.17 2.88 7.91 0 0 0 0 34.22 103.8 Neighborhood Collector 23.48 60.91 0.60 1.62 1.58 4.35 0 0 0 0 25.66 66.88 Residential 303.89 705.97 2.42 6.19 21.57 54.86 0 0 0 0 327.88 767.02 Total 431.28 1122.45 6.44 18.52 31.14 81.77 0 0 0 0 468.86 1222.73 UNIMPROVED SYSTEM As halt ACP Bituminous Surface BST Concrete (PCC) Gravel Undeveloped Total Miles 12' Lane Miles Miles 12' Lane Miles Miles 12' Lane Miles Miles 12' Lane Miles Miles 12' Lane Miles Miles 12' Lane Miles Major Arterial 0 0 0 0 0 0 0 0 0 0 0 0 Minor Arterial 1.01 1.96 0 0 0 0 0 0 0 0 1.01 1.96 Major Collector 2.74 6.29 0 0 0 0 0 0 0 0 2.74 6.29 Neighborhood Collector 4.36 8.66 0 0 0 0 0 0 0 0 4.36 8.66 Residential 38.88 64.27 3.95 5.91 0.03 0.03 8.73 12.87 4.46 4.96 56.05 88.04 Total 46.99 81.18 1 3.95 1 5.91 1 0.03 1 0.03 1 8.73 1 12.87 1 4.46 4.96 64.16 1 104.95 4 Functional Classifications The quantity and associated vehicle weight of traffic using streets is a critical factor affecting the rate at which pavement and roadbeds deteriorate. Eugene divides streets into five categories called functional classifications (FC), each representing a different volume and type of vehicular usage. Major Arterial (FC -1): Major Arterials are usually four or more lanes and generally connect various parts of the region with one another within the city and with the "outside world ". They serve as major access routes to regional destinations such as downtowns, universities, airports, and similar major focal points within the urban area. Major Arterials typically carry an average of more than 20,000 vehicles per day. Major Arterials receive high priority maintenance. Minor Arterial (FC 2): Minor Arterials are typically two or three lanes. These streets provide the next level of urban connectivity below major arterials. In most cases their main role tends to be serving intra -city mobility. Minor Arterials carry between 7,500 and 20,000 vehicles per day. Minor Arterials receive priority maintenance. Major Collector (FC -3): Major Collectors can be found in residential, commercial, and industrial areas. They typically carry between 2,500 and 7,500 vehicles per day. Major Collectors have a higher priority for maintenance than local streets. Neighborhood Collector (FC -4): Neighborhood Collectors are found only in residential neighborhoods and provide a high degree of access to individual properties in a neighborhood. They typically carry between 1,500 and 2,500 vehicles per day. Local (FC -5): Local streets provide access to individual properties along the roadway. They are narrow, slow- speed, and low - volume service facilities. They typically carry fewer than 1,500 vehicles per day, and receive low priority maintenance. Local streets are also referred to as Residential streets. The following graph illustrates both centerline miles and lane miles by improvement type and functional classes. Mileage by Functional Class - Improved and Unimproved 1300 1200 1100 1000 900 800 700 600 500 400 300 200 100 Major Minor Collector Neigh. Local Total Arterial Arterial Collector *Improved 12' lane miles 62 223 104 67 767 1223 ■Unimproved 12'lane miles 0 2 6 9 89 106 *Improved centerline miles 15 67 34 26 327 469 OUnimproved centerline miles 0 1 3 4 57 65 PAVEMENT MANAGEMENT SYSTEM A Pavement Management System (PMS) performs analysis of collected rating data and reports on the current and projected conditions of the street system. In addition, it is used to evaluate the effectiveness of planning and funding priorities, and provides guidance in the decision making process. The goal of the decision making process is to prevent pavement failures through judicious maintenance. The PMS used by the City of Eugene since 1987 is CenterLine. CenterLine was developed by Washington's League of Cities and Washington County Roads Administration Board in conjunction with the Washington Department of Transportation (WDOT). The PMS combines visual field inspection ratings, compiled under strict criteria, with computer tracking and condition analysis. The rating methodology for field inspections used prior to 2010 was the WDOT Standard method. Beginning in 2010 the rating methodology was revised to the WDOT's Extended (WSEXT) method, keeping the program consistent with industry standards. Eugene's FMS contains 25 years of historical data and has the ability to estimate financial needs and road conditions 20 years into the future. Starting with the next rating season the City will be converting from CenterLine to a new pavement management system yet to be determined. CenterLine no longer provides customer support, making it necessary to migrate all of our historical data to a new system. Rating data will still be collected using WSEXT method. A more complete description of this conversion will be reported in the future. Pavement Inspection Frequency Two predominant work efforts required to maintain the PMS are updating the street inventory and performing the annual inspection of surface conditions. City streets are divided into segments based on their Functional Classification (FC), pavement type, and geometric design. Segments are the basic unit for evaluating streets and surface conditions. A segment is defined as a portion of a street with a beginning and ending description. Changes in geometric features are used as a guide for determining segments. Examples of geometric differences are surface type, segment width, surface age, and extent of past rehabilitations. Field inspections are conducted by pavement raters who walk each individual street segment evaluating the pavement surface for signs of distress. City arterial and collector streets are inspected annually; residential streets inspections are completed in a three -year cycle; and off - street shared -use path inspections are completed in a two -year cycle. In 2010 and 2011 all streets were inspected to establish an accurate baseline using the WSEXT rating method. In 2012, the program resumed with standard annual inspection intervals as described above. ra Overall Condition Index (OCI), Deduct Values, and Distresses Pavement distresses are dependent on pavement type and are rated by severity and extent. A street with an OCI of 100 represents a new or recently rehabilitated street. This OCI value is the basis used to analyze the surface treatment needs. Distress data are collected using handheld computers (IPAQ's) and then uploaded to the pavement management software. The extended method (WSEXT) rates severities and all their extents; this information is then used to determine a deduct value. A segment's OCI is calculated by subtracting the deduct values from 100. As the condition of a street's surface begins to deteriorate the OCI decreases. Asphalt distresses typically observed are alligatoring, longitudinal and transverse cracks, rutting, and raveling. Distresses in concrete streets typically observed and rated include cracks per panel, raveling, joint spalling, faulting, and crack sealing. Descriptions of some common distresses are shown below: Alligator Cracking: When the asphalt begins to crack in all direction it is called alligator cracking. Longitudinal Cracking /Transverse Cracking: These are cracks that are vertical (longitudinal) and horizontal (transverse) in length. These distresses usually divide the piece into different sections and which are caused by repeated traffic loading. The low- severity cracks are not considered serious to the overall function and safety of the road. Medium to high- severity cracks are usually caused by heavy traffic loads and environmental factors and can become very serious distresses. The picture below shows longitudinal cracking. IN Rutting: When the traffic of the street becomes heavy for long periods of times the asphalt begins to sink into the wheel path of the vehicles causing a rut. When there is a rut it is usually a long length of the road and is 1 to 2 feet wide and there are almost always two ruts, one for each side of the vehicle. Joint Spalling: Spalling is the deterioration of the edges of a concrete slab within 2 feet (0.6m) of the joint. The edges get chipped off concrete slabs causing spalling. Spalling is caused by heavy traffic loads and environmental factors. Raveling: The roads, mainly asphalt, over time become worn out and rough not smooth as when they were first put in, often due to age and the effects of UV rays. Raveling measures the severity of the roughness and coarseness of the top layer of the street. Faulting: Faulting is the difference in elevation across the slab. One side may be leaning up more over the other side. Causes are soft foundations, heavy traffic, poor construction, and environmental damage. How PMS Information is Used The primary purpose of maintaining a PMS is to collect and analyze information relating to street system condition and trends. With this vital information Public Works managers ensure the most cost - effective maintenance or rehabilitation strategies are identified and performed at the optimum time. Each year the PMS is used to generate several reports requested by other agencies as well as statistical data requested within our own agency. The following is a sample of reports produced with PMS data: • Pavement Preservation Project List • Crack Seal Program • Five -Year Surface List — five -year moratorium for street cutting • ODOT Oregon Mileage Report • City of Eugene Public Infrastructure Table • Annual Insurance Marketing Report • Transportation Service Profile 3] PAVEMENT PRESERVATION PROGRAM Street preservation and rehabilitation, capital improvements, off - street shared -use path projects, and maintenance efforts make up Eugene's Pavement Preservation Program (PPP). Additionally, the City has budgeted funding for Maintenance Operations to repair portions of the unimproved street system through the Enhanced Street Repair Program. Both PW Maintenance and PW Engineering have important roles within the PPP. PW Maintenance Roles Maintenance Division Surface Technical team completes the pavement rating, budget and street life analysis, resulting in a proposed list of projects which is forwarded to Engineering for field testing and final grouping. Surface Technical staff are responsible for producing this report. Operations staff is responsible for the preventative maintenance of all City streets (including concrete streets) and off - street shared -use paths. Preventative maintenance designed to extend the life of the transportation asset is of highest priority. Fully improved asphalt streets receive the highest level of maintenance. Maintenance activities are performed to mitigate hazardous conditions and to extend the useful life of the street. The goal of preventative maintenance is to prevent a street's OCI from slipping into a reconstruction category. PW Engineering Roles The Engineering Division typically receives projects proposed for preservation from the Maintenance Division three years in advance of the planned construction. Engineering then performs field investigations to confirm the need for treatment, and reviews historic data on construction and maintenance of the streets. Streets are then prioritized for detailed pavement testing and design recommendations based on the available funding and the assessed condition of the streets. The pavement testing and design reports identify whether a street needs to be reconstructed or rehabilitated (overlaid) and the range of treatment options available. If a street is determined to be a full reconstruct, it is typically deferred until funding is identified and available, such as street repair bond measures. The Engineering Division is responsible for capital project management including design, stakeholder coordination and communication, contract administration, and construction management. For analysis and reporting of projected backlogs, the Engineering Division has provided construction costs based on historic and current road projects. 10 Treatment Types and Estimated Costs For the purpose of reporting projected backlogs the Engineering Division provides construction costs based on historic and present road projects. Treatments reflected in the backlog analysis are limited to three types; slurry seal, overlay, and reconstruction and reporting is based on a system wide approach, not at the project level performed by Engineering. Each functional class has an estimated unit cost for overlay and reconstruction treatments. For local streets (FC -5) an additional maintenance option, slurry seal, is considered. Slurry Seal: The slurry seal option allows for a cost - effective treatment to seal the surface and restore the skid resistance of local street segments, which do not carry high traffic loads. This treatment is not used on streets which require strengthening or reconstruction. Typical slurry seal costs include street cleaning, removal of vegetation, minor base repairs (dig- outs), sealing of cracks, and application of an emulsified asphalt aggregate mixture to the entire paved surface. Associated costs include replacement of striping and pavement markings, and other work needed to return the street to normal operation. Overlay: Typical overlay rehabilitation costs include milling of existing pavement to a moderate depth to remove existing cracking and increase strength of the structural section. Isolated areas of severely distressed pavement are removed and replaced including a new aggregate base. Associated costs include replacement of striping and pavement markings, adjustment of manholes, and other work needed to return the street to normal operation. Reconstruct: Typical street reconstruction costs include removal of the existing pavement and base structural section and replacement with a new structural section which will meet a 20 -year design life. Isolated areas of curb and gutter are replaced where they would not be suitable to contain new paving or have severe drainage problems. The following table identifies the estimated costs for the various treatment types including costs to upgrade curb ramps to comply with The American with Disabilities Act (ADA). The slurry seal treatment is exempt from ADA requirements. Treatment — Functional Class Improved System Overlay - FC 1 & 2 12' Updated II. cost $215,000 Lane Mile Cost pd2013 2012 $243,000 cost with % inflation $248,000 Overlay - FC 3 & 4 $184,000 $214,000 $218,000 Overlay - FC 5 $169,000 $195,000 $198,000 Re -Contt - FC I & 2 $765,000 $724,000 $738,000 Re -Contt - FC 3 & 4 $677,000 $679,000 $693,000 Re -Contt - FC 5 $505,000 $505,000 $515,000 Slurry Seal - FC 5 1 $19,000 1 $25,000 1 $26,000 11 The following graph identifies the trigger points (OCI) for each treatment based on Functional Class. Sustainable Construction Since 2008, Eugene has been in the forefront of sustainable construction and paving practices, some of which include paving with warm mix asphalt (WMA), using reclaimed asphalt pavement (RAP), and full depth reclamation (FDR). Production of warm mix asphalt is a "green" solution for the environment with noticeable reduced energy consumption and greenhouse gas emissions. Exposure to fuel emissions, fumes, and odors are reduced for asphalt producers, construction workers and the public. Benefits of paving with WMA are the ability to extend the paving season in colder weather, longer haul distances, and better road performance. Warm mix asphalt is identical to conventional hot mix asphalt, except that through a special mixing process it is produced at a temperature approximately 50 to 100 degrees cooler than conventional hot mix asphalt. This mixing process for asphalt aids in compaction during paving, assists in preventing premature aging and slowing the aging process of asphalt. In Eugene, all asphalt producers have retrofitted their plants to produce warm mix asphalt. 12 Council set goals in 2011 for waste reduction by requiring that the quantity of materials placed in landfills be reduced. In addition to using WMA, Public Works conducted two pilot projects specifying that reclaimed asphalt shingles (RAS) be used as a binder in the asphalt mix, thereby keeping this material from entering the waste stream. The City continues to use warm mix asphalt and in -place recycling techniques to improve the quality, environmental footprint, and cost efficiency of the street bond projects. Key terms in sustainable construction practices: In -Place Recycling: A process in which a large piece of equipment called a reclaimer pulverizes and mixes the existing base rock and a portion of subgrade soils with dry cement and water to create a cement - treated base. This process greatly reduces the use of virgin materials and trucking that are needed using conventional remove and replace construction techniques. Full Depth Reclamation: When applicable, partial or full -depth reclamation (FDR) is used as a cost- and time - saving alternative to traditional reconstruction. Associated costs include replacement of striping and pavement markings, adjustment of manholes, and other work needed to return the street to normal operation. Crack Seal: Placing specialized materials into cracks in unique configurations to keep water and other matter out of the crack and the underlying pavement layers. Crack sealing can be used for two different reasons in pavement maintenance. One is a treatment to seal the cracks in order to prevent moisture intrusion into the pavement. The other is preparatory work to other treatments, such as overlays, and slurry seals. Reclaimed Asphalt Pavement (RAP): The term given to removed and /or reprocessed pavement materials containing asphalt and aggregates. These materials are generated when asphalt pavements are removed for reconstruction, resurfacing, or to obtain access to buried utilities. When properly crushed and screened, RAP consists of high - quality, well - graded aggregates coated by asphalt cement that can be reused as a substitute for a portion of virgin materials in asphalt and aggregate base. Recycled Asphalt Shingles (RAS): A primary reason for the high potential value of recycled shingles is that they contain ingredients that hot mix asphalt (HMA) producers purchase to enhance their paving mixtures including asphalt cement (or AC "binder ") and mineral aggregate. Asphalt shingles also contain a fibrous mat made from organic felt (cellulose) or fiberglass that can also be valuable as fiber in some asphalt paving mixes. 13 Current Treatment Costs This chart provides detail of the current cost for treatment of the entire improved system excluding concrete streets at the end of the 2012 rating period. The total estimated treatment cost backlog at the end of 2012 is $100 million down from $118 million reported in 2011. $120,000,000 $10C $8C $6C $4C $2C Treatment Costs By Functional Class 2012 Year End ,000,000 1 000,000 ,000,000 1 000,000 1 000,000 $0 Major Art Minor Art Coll Neigh. Coll Local Total ■Slurry $0 $0 $0 $0 $9,173,000 $9,173,000 ■Overlay $1,698,000 $5,859,000 $3,978,000 $3,598,000 $36,672,000 $51,805,000 ❑Reconst $4,645,000 $10,353,000 $10,568,000 $2,952,000 $10,622,000 $39,140,000 ■Total $6,343,000 $16,212,000 $14,546,000 $6,550,000 $56,467,000 $100,118,000 Historical and Projected Funding Outcomes Using the PMS software, an analysis for a 10 -year period (2013 through 2022) has been completed based on the current funding, including the 2012 bond measure. The PMS software evaluates the deterioration of each segment based on individual OCI ratings. The software then projects when to apply the necessary treatment at the proper time. When possible, the system applies a less expensive treatment earlier in the degradation curve to prevent the street from falling into an overlay or reconstruct range. In the following four graphs this projected evaluation includes historical data to present a more comprehensive view of the street system. The graphs show the impact of past and current funding over a 20 -year period (2002 to 2022). Each graph indicates the percentage of streets that fall within a specific treatment range (reconstruct, overlay and no treatment). Plotting the percentages of streets within a treatment range over time visually demonstrates the overall condition of streets within that class. This is useful when deciding how to allocate funds in future years. 14 Arterial streets have been a major focus of the Pavement Preservation Program since 2002; as a result the percentage of arterial streets within the reconstruct treatment range steadily declined from 2008 to present and is projected to stabilize after 2014. This stabilization provides an opportunity for funding to be allocated towards preservation (preventative maintenance) of the streets, a primary goal of the pavement management system. Preventative treatments (including overlays) are far less expensive and can extend the life of a street considerably. Additionally, further analysis of the arterial classification shows a period of time where there is an opportunity to direct a large portion of available funds to other street classifications for treatment. 15 Historical and Projected Funding Impacts to Arterial Streets lac% 9a% 80% _O 70% 60% f 50% s dip 40% 30% • o wes • • 20% ■ • • • • • • • ••••.•..•■ •� 10% • • ••w 2002 2003 2004 2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 — —No Treatment Overlay • • • • Reconstruct Arterial streets have been a major focus of the Pavement Preservation Program since 2002; as a result the percentage of arterial streets within the reconstruct treatment range steadily declined from 2008 to present and is projected to stabilize after 2014. This stabilization provides an opportunity for funding to be allocated towards preservation (preventative maintenance) of the streets, a primary goal of the pavement management system. Preventative treatments (including overlays) are far less expensive and can extend the life of a street considerably. Additionally, further analysis of the arterial classification shows a period of time where there is an opportunity to direct a large portion of available funds to other street classifications for treatment. 15 Similar to arterial streets, reconstruction and overlay treatment needs have decreased since 2008 as a result of completed and upcoming projects. As with arterial streets, further analysis has shown that a majority of streets in the overlay treatment category are in the upper end of the OCI scale. Streets in the upper range of the OCI scale have a number of years remaining before they are at risk of falling into the reconstruct category. Once again, with more arterial and collector streets in the upper range of the OCI scale, a portion of available funding can potentially be directed to the residential classification where street repair needs continue to rise. Beginning in 2017, it is projected that streets which have previously been treated will begin to show expected deterioration. 16 Historical and Projected Funding Impacts to Collector Streets 100% 90 %is s 80% ... ♦. 70% - 60% 50% 4 / 40% •••••!•�• ! 30% ! • •!, • 20% _ _ • _. ! • ! 10% • 0% 2002 2003 2004 2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 2419 2020 2021 2022 i No Treatment Overlay ....Reconstruct Similar to arterial streets, reconstruction and overlay treatment needs have decreased since 2008 as a result of completed and upcoming projects. As with arterial streets, further analysis has shown that a majority of streets in the overlay treatment category are in the upper end of the OCI scale. Streets in the upper range of the OCI scale have a number of years remaining before they are at risk of falling into the reconstruct category. Once again, with more arterial and collector streets in the upper range of the OCI scale, a portion of available funding can potentially be directed to the residential classification where street repair needs continue to rise. Beginning in 2017, it is projected that streets which have previously been treated will begin to show expected deterioration. 16 Residential (Local) streets make up 56% of the total street system backlog. To date residential streets have not been adequately funded to keep them from deteriorating, therefore we see very little change from the projections reported in 2012. The 2012 bond measure identifies approximately 15 centerline miles for repair, less than 5% of the functional class. Although the percentage of streets within the reconstruct range has increased gradually to date, it is projected to climb at a much faster rate in the future, which reflects a street's lifecycle, aggravated by the lack of preventative treatment. The percentage of streets within the overlay treatment range continues to increase as well. Reflectively, the percentage of residential streets within the no- treatment range has been dropping and is projected to continue so that by 2022 less than 40% of residential streets will require no treatment. In that same time period, residential streets requiring reconstruction increases to more than 25% of the system. 17 Historical and projected Funding Impacts to Residential Streets 100% 90% 80% • 60% 50% 40% 20% 10% ! !!i!!��!lii 2002 2009 2004 Zoos 2006 2047 2003 2009 2410 2021 2012 2013 2014 2015 2016 Zan 2918 2019 2020 2021 2022 � � No Treatment Overlay • • • Reconstruct Residential (Local) streets make up 56% of the total street system backlog. To date residential streets have not been adequately funded to keep them from deteriorating, therefore we see very little change from the projections reported in 2012. The 2012 bond measure identifies approximately 15 centerline miles for repair, less than 5% of the functional class. Although the percentage of streets within the reconstruct range has increased gradually to date, it is projected to climb at a much faster rate in the future, which reflects a street's lifecycle, aggravated by the lack of preventative treatment. The percentage of streets within the overlay treatment range continues to increase as well. Reflectively, the percentage of residential streets within the no- treatment range has been dropping and is projected to continue so that by 2022 less than 40% of residential streets will require no treatment. In that same time period, residential streets requiring reconstruction increases to more than 25% of the system. 17 This graph of the combined arterial, collector and residential streets reflects the impacts to the overall street system due to insufficient funding for residential street treatments as well as a treatment strategy that includes reconstruction as well as overlay treatment. The percentage of streets needing "no treatment" declines, while streets requiring a "reconstruct" treatment increases. 18 Historical and Projected Funding Impacts to Total System Streets 100% F 90% 80% 4 ft dop an 70% _ do 60% - 50% — 40% 30% 20% — — .. 10% • rrrrr r• r• .. •� R _�,• r 0% 2002 2003 2004 2665 2006 2007 2008 2609 2010 2611 2912 2013 2014 leis 2016 2617 2018 2619 2620 2621 2022 � i No Treatment Overlay • • • • Reconstruct This graph of the combined arterial, collector and residential streets reflects the impacts to the overall street system due to insufficient funding for residential street treatments as well as a treatment strategy that includes reconstruction as well as overlay treatment. The percentage of streets needing "no treatment" declines, while streets requiring a "reconstruct" treatment increases. 18 Unimproved Street System The City's transportation system consists of 533 centerline miles of improved and unimproved streets. The unimproved portion of this total includes 51 centerline miles (87 lane miles) of asphalt and bituminous surface streets. This section of the report is intended to describe the overall condition of unimproved asphalt streets, potential treatment needs, associated rehabilitation costs, along with a projected backlog repair cost for addressing this classification of street. It is important to note that any treatment short of being brought up to full urban street standards should be considered temporary. The estimated cost to improve this classification to meet the urban street standards is approximately $60 million. In addition, the following backlog figure is separate from the improved street backlog figure. Based on 2012 rating data of the unimproved streets system there is a backlog of temporary repair projects, typically maintenance overlays, totaling an estimated $9.8 million, down from $11.3 million reported in 2011. The following charts and graphs indicate that 45 percent of the system falls into a no treatment category, up from 36 percent reported in 2011, due in large part to recent maintenance overlay and FDR treatments completed over the past five years. More than 75 unimproved streets have benefited from full or partial treatment since 2008. Thirty three percent of the system falls into the "poor" category. Currently, Public Works Maintenance plans on spending $200,000 annually over the next four years to address a portion of these streets. 2012 Unimproved Asphalt Street Condition and Rehabilitation Report (2012 Rating Data) OCI Lane Miles % of System Condition Rehabilitation Cost Unit Cost /SQFT 0 -10 6.77 7.61% Poor $2,573,683 $6.00 1120 11.72 13.18% Poor $2,970,317 $4.00 21 -30 10.68 12.01% Poor $1,522,541 $2.25 31 -40 6.01 6.76% Fair $856,786 $2.25 41 -50 4.18 4.70% Fair $595,901 $2.25 51 -60 7.56 8.50% Fair $1,077,754 $2.25 61 -65 1.72 1.93% Fair $245,203 $2.25 66 -70 1.63 1.83% Good $0 $0.00 71 -80 2.63 2.95% Good $0 $0.00 81 -85 3.89 4.37% Good $0 $0.00 86 -90 4.75 5.33% Excellent $0 $0.00 91 -100 27.42 30.83% Excellent $0 $0.00 Total Rehabilitation $9,842,185 88.96 100.00% * Unit cost based on 2010 estimated costs 19 The following graphs are a visual representation of the information provided on the preceding page. of Unimproved Streets by Condition 45 ° 40 36% 35 33% 30 26% 27% — ■ 2010 25 22% ■ 2011 20 2012 15 10% ° 10 6% 5 0 . Poor Fair Good Excellent Lane Miles of Unimproved by Condition 40.0 38 35 _ 35.0 32 30.0 -- - ■ 2010 25.0 22 21 23 —. ■ 2011 20.0 2012 15.0 10.0 8 5.0 0.0 Poor Fair Good Excellent 20 Projected Funding for Pavement Preservation Program FY12 through FY18 From the inception of the Pavement Preservation Program (PPP), Eugene has been faced with the challenge of securing adequate, sustainable funding for this program. Currently there are several sources that contribute funding for pavement rehabilitation and reconstruction projects. The primary source of ongoing revenue is the City's local motor vehicle fuel tax ( "gas tax "), which is currently levied at 5 cents per gallon. The reimbursement component of Transportation System Development Charges (SDCs) have historically generated close to $800,000 per year for PPP projects. In the current economic environment, building permit activity continues to be low, reducing the level of this funding stream. The cumulative effect of these factors is that PPP annual revenues, which were once projected at $4.2 million per year, are now projected to level out at approximately $3 million per year In 2008, voters approved a $35.9 million dollar bond measure dedicated to 32 street preservation projects and shared -use path rehabilitation work. Based on numerous economic factors construction bids were significantly less than anticipated allowing 22 streets to be added to the original 32 streets approved by voters. In 2012, voters approved a second $43 million bond measure dedicated to 76 street preservation projects plus $516,000 annually to support bicycle and pedestrian projects. The measure will generate approximately $8 million annually for FY14 through FY18. With the funding identified approximately 112 lane miles of City streets and will be repaired. To date approximately 3 miles of off - street shared -use paths have been repaired. Projected Funding Sources Pavement Preservation Projects FY12 - FY18 Fiscal Year Local Gas Tax SDC Bond FY12 (actual) $3,045,192 $390,645 $7,140,000 FY13 (est.) $3,060,000 $136,600 $7,480,000 FY14 (est.) $3,060,000 $186,746 $7,840,000 FY15 (est.) $3,060,000 $186,746 $8,000,000 FY16 (est.) $3,060,000 $186,746 $8,290,000 FY17 (est) $3,060,000 $186,746 $8,590,000 FY18 (est) $3,060,000 $186,746 $8,900,000 Total Other* Funding $41,748 $10,617,585 $20,580 $10,697,180 $37,088 $11,123,834 $35,644 $11,282,390 $36,710 $11,573,456 $37,463 $11,874,209 $36,845 $12,183,591 * "Other" revenue includes investment interest, permit fees and other miscellaneous resources. 21 Project Prioritization Selecting streets or street segments for treatment is done through a process involving analysis, testing, and staff experience. Using the data produced by CenterLine, and combining this information with estimated revenues allows staff to approximate backlogs and group potential street segments for consideration for treatment under the Pavement Preservation Program. Streets are not prioritized on a "worst first" basis. Public Works' main objective is to keep street segments from slipping into the reconstruction category, which typically costs four to five times more per lane mile than rehabilitation. By rehabilitating (overlaying) a street before it significantly deteriorates, 15 to 20 years of useful life can be added to a street at a substantial cost savings over reconstruction. Once a street has deteriorated to the point that it must be reconstructed, the opportunity for preventive street maintenance (overlay) is lost. For these reasons, streets that are categorized as overlay projects receive the highest priority for corrective treatment. If at some point in the future there are additional funds available, or if the majority of overlay projects have been addressed, reconstruction projects will be scheduled. A prioritized list of 32 street repair projects to be funded by a local bond measure was approved by Eugene voters in 2008. The list, approved by City Council, was developed by staff based on citizen input, information about needed street rehabilitation and reconstruction from the pavement management system, and equitable geographic distribution of projects throughout the community. Subsequently, a 12- member citizen review panel was formed to document the use of the bond proceeds. In 2011, City Council approved the addition of 22 streets selected in the same manner and recommended by the citizen review panel to be repaired. In 2012, a second five -year bond measure was approved by Eugene voters with a prioritized list of 76 street repair projects (Exhibit A) and additional funding to support bicycle and pedestrian improvement projects. The list was developed using the same criteria as above and approved by City Council. Off - Street Shared -Use Paths Shared -use paths are used by a variety of non - motorized users, including pedestrians, cyclists, skaters, and runners. Shared -use paths are typically wider than an average sidewalk and paved (asphalt or concrete). There are approximately 41 miles of shared -use paths identified in the Pavement Management System. The complete system of shared -use paths was surveyed and rated in 201 fusing the new rating methodology. With this updated information a future analysis will be performed to project the condition and funding needs of this infrastructure. The City standards for shared -use paths require a concrete structure no less than six inches deep and 12 feet wide. Paths designed, constructed or reconstructed to current standards are expected to have a 50 -year life. ON The following graphs show the division of current surface types and widths within the system. Off - Street Shared -Use Path Surface Type: Off - Street Shared -Use Path Existing Widths: Asphalt, '. 36% Concrete, 64% Miles of Off - Street Shared -Use Paths by Condition 35.00 - 28.85 30.00 - 25.00 ■ Poor 0 -50 OCI 20.00 ❑ Fair 51 -69 OCI ■ Good 70 -89 OCI 15.00 ■ Excellent 90 -100 OCI 10.00 8.25 5.00 4.23 1.48 11 1 0.00 23 Shared -use path projects have been historically funded by state and federal grants and more recently by voter - approved bond measures. There is currently no long -term funding identified specifically for shared -use paths. The following is a list of completed and current projects, including shared -use paths funded by the bond measures. Name Fiscal Year Funding Fern Ridge Chambers - City View 2004 STP -U Garden Way Bike Path 2005 STP -U Monroe Bikeway 2006 STP -U N Bank Path Club Rd 3000'W 2006 STP -U West Bank Trail 2007 Transportation Enhancement (TE) Funds Delta Ponds Bridge 2007 Various Federal Funds Amazon: SEHS - 31st Bike Path 2009 PBM Fern Ridge Path Rehab /Westmoreland Connector 2010 PBM South Bank Path Rehab 2011 PBM West Bank Trail Extension 2011 STP -U /TE Fern Ridge: Chambers - Arthur 2012 ODOT Rapid Readiness Funds W Bank: Greenway - Copping 2012 PBM Amazon /Willamette River Path Connectors 2012 State Urban Trail Funds North Bank Path: DeFazio Bridge to Leisure Ln. 2012 STP -U Fern Ridge: Terry - Greenhill 2013 STP -U /TE South Bank Path: Riverplay to DeFazio Bridge 2013 PBM Project Funding Abbreviations PBM — Paving Bond Measure LGT — Local Gas Tax /SDC /Other STP -U —Surface Transportation Funds -Urban (Federal) TE — Transportation Enhancement (Federal) 24 Scheduled Street Projects for 2013 Project Name Limits Lane Miles Funding 5TH AVE High to Blair 3.35 PBM 5TH AVE Hwy 99 to Bailey Hill 2.88 PBM 10TH AVE Olive to Jefferson 1.04 PBM 18TH AVE Washington to 330' East Of Chambers 2.67 PBM ALDER ST 18th to 24th 0.93 PBM BLAIR BLVD 2nd Ave to Monroe 1.74 PBM BROADWAY W Lincoln to Monroe 1.02 PBM COBURG RD County Farm Rd to Chad 1.99 PBM COBURG RD Beltline to Willakenzie Rd 2.54 LGT /FHWA HILYARD ST Broadway to E 13th Ave 1.00 LGT /PBM LORANE HWY Washington to Paige 1.78 LGT OLIVE ST W 10th Ave to W 13th Ave 0.61 PBM VAN BUREN ST Railroad Crossing to Blair Blvd 0.43 PBM WILLAMETTE ST W 19th Ave to South Of 24th Ave 1.18 PBM 25 The following map illustrates the Pavement Projects scheduled for 2013. A. X I a� fill _I R � t I 2113 Pavement Preservation Program (Bond Measure, Local Gas Tax, Other) Approximately 23 Lane Miles I11 C '►�," ' I � 1 IV it y i �RI•R� till Aim 1 y 11 Hii �2. Legend —2013 Repairs Streets Eugene UGE Water Bodies JW J 26 The following map illustrates Pavement Preservation Projects since inception of the program. Pavement P reservat ion Prog (Bored Measure, Local Gas Tax, Other 2002-2012 Approximately 400 Lane Mies s � a n - _ r i w 1 i f Legend CV- Slurry Seals — Street Repairs Streets Eugene UGB Water Bodies – ,# ki - rd f+r 'f J rag f �p J� 27 The following map illustrates the Enhanced Street Repair Program 2008 -2012. 2 008 - Enhanced Street Repair Program Appro ximately " r+ f . �y. � +�a �ae '��x _�yy +�s.:.^�F r� Legend Enhanced Pothole Program Streets Q; Eugene UGB Water Bodies NINE n r 7 a 28 Attachment B Eugen Street Preservation Projects ... �. ��._ti_...�..�.._...j � a�wu ��. >r��'� t•� �� � crcr iww .._ / f 49 '7} gy 4; p X47 W 52 i Win.. •� • V� vy, 5,� s0 .. or f � a A t i «.. s a)' ...w.b.,. 4) 47 L o. 4 � 7 - a m..._ a......�. a 74 ,• 76 a rn Legend a w Go band Projects City Streets City Limits t Eugene VG6 a ON os P.uCwC @tl by 6�ry.# @l+gShE PUY @ng LiFd 74aM,JUM MttIRad+150614M1 See accompanying index for specific project information 1 % s PQ 1. 1..�..�..¢'•a. * ..nw �.� .x..... ..p.a ...rw w. � ^•,a n r.l ���i ... �. ��._ti_...�..�.._...j � a�wu ��. >r��'� t•� �� � crcr iww .._ / f 49 '7} gy 4; p X47 W 52 i Win.. •� • V� vy, 5,� s0 .. or f � a A t i «.. s a)' ...w.b.,. 4) 47 L o. 4 � 7 - a m..._ a......�. a 74 ,• 76 a rn Legend a w Go band Projects City Streets City Limits t Eugene VG6 a ON os P.uCwC @tl by 6�ry.# @l+gShE PUY @ng LiFd 74aM,JUM MttIRad+150614M1 See accompanying index for specific project information 1 % s PQ Exhibit A Project List for 2012 Bond Measure to Fix Streets Map # Street Name Limits 1 01ST AVE WASHINGTON ST- VAN BUREN ST 2 01ST AVE BLAIR BLVD - WEST END 3 02ND AVE BLAIR BLVD- GARFIELD ST 4 CSTH AVE BERTELSEN RD - WEST END 5 06TH AVE BERTELSEN RD- COMMERCIAL ST Fi 07TH AVE BERTELSEN RD - OSCAR ST 7 017TH PL 7TH AVE /HWY 99 - BAILEY HILL RD 8 13TH AVE WASHINGTON ST- GARFIELD ST 9 13TH AVE BERTELSEN RD- COMMERCE ST 10 15TH AVE FAIRMOUNT BLVD - AGATE ST 11 17TH AVE FAIRMOUINT BLVD - AGATE ST 12 19TH AVE FILLMORE ST - CHAMBERS ST 13 22ND AVE FRIENDLY ST - POLK ST 14 25TH AVE HAWK INS LN - BRITTANY SF 13 27TH AVE COLUMBIAST - SPRING BLVD 16 30TH AVE SPRING OVERPASS - AGATE ST 17 30TH AVE MI LLST(W EST) - FERRYST(EAST) 18 BOTH AVE MILL ST - WILLAMETTE ST 19 39TH AVE WILLAMETTE ST -100' EAST OF DENS MORE RD 20 40TH AVE HILYARD ST - DONALD ST 21 43RD AVE N SHASTA - DILLARD RD 22 AVALONST ECHO HOLLOW RD - JUHL ST 23 BEST LN WILLAKENZIE RD- KENTWOOD!DR 24 BRAE BURN DR 39TH AVE - WILLAMETTE ST 25 BROADWAY MILL ST - PEARL ST 2£ BUFF WAY WOODSIDE DR - FORRESTER WAY 27 CALVIN ST WESTERN DR - HARLOW RD 2.8 CAPITAL DR SPRING BLVD - 50' N OF CRESTA DE RUTA ST 29 CARMELAVE MINDA DR - 40k0]' SQLJTH 0 F MINDA DR 30 CASCADE DR AVALON ST- JUHL ST 31 CENTENNIAL LP MILK, JR BLVD (EAST) - MLK, JR BLVD /CLUB RD 32 CITY VIEW ST 28TH AVE - 29TH AVE 33 COBURG RD SS FERRY ST BRIDGE -50'S OF EWEB ON /OFF RAMP 34 COMMERCIAL ST 5TH AVE - SOUTH END 35 CORYDON ST FO]RRESTER WAY - TANDY TURN 35 EAST AMAZON DR HILYARD ST - DILLARD RD 37 ELIZABETH ST KNOD P AVE - ROYAL AVE 38 FAIRFI ELD AVE WS HWY 99 - ROYAL AVE 39 FILLMORE ST 19TH AVE - 24TH AVE 407 FIRLAND BLVD SPRING BLVD - AGATE ST 41 FORRESTER WAY CC BURG RD - WS DRWY 10733 42 GARFIELD ST ROOSEVELT - 6TH AVE 43 GOODPA5TURE LOOP GOODPASTURE IS RD (EAST INTERSECTION) - GOODPASTU RE IS RD (WEST INTERSECTION) 44 INTERIOR ST NORTH END OF CUL DE SAC - SOUTH END OF IMPROVED SECTION 30 Exhibit A Map 4 Street Name Limits 45 ION AVE BEST LN - ADK INS ST 4G JACOBS DR HWY 99N - FAIRFIELID AVE 47 JEFFERSON 5T 8TH AVE- 18TH AVE 48 1UHLST NSADDR 1424 -SOUTH END 49 K'NOOPAVE ECHO HOLLOW RD- ELIZABETH ST 50 LARKSPUR AVE NORKENZIE RD- 640 FEET WEST OF NORKENZIE RD 51 LARKSPUR LOOP NORKENZIE RD (N) - NORKENZIE RD (S) 52 LEIGH ST NORTH END - WESTERN DR 53 UNCOLN ST 5TH AVE -13TH AVE 54 LYDICK WAY TOMAHAWK LN - HARLOW RD 55 MADISON ST 1ST AVE - 8TH AVE 56 MAHLON AVE GARDEN WAY - HONEYSUCKLE LN 57 MILL ST 30TH AVE (NORTH) - 30TH AVE (SOUTH) 58 MONROE ST 1ST AVE - BLAIR BLVD 59 NORTH SHASTA LOOP FIRLAND -43RD AVE 60 PIONEER CT PIONEER PIKE - NORTH END 51 PIPER LN CHASA ST - FIR ACRES DR (INCL CUL -DE -SAC) 62 POTTER ST 24TH AVE - 29TH AVE 63 ROLAND WAY OAKWAY RD - CAL YOUNG RD 64 SATRE 5T BAILEY LN - WESTERN DR 65 SHARON WAY CO BURG RD - ES DRWY 1023 66 SPRING BLVD FAIRMOUNT BLVD - CAPITAL DR 67 TIMBERLINE DR WARREN ST- WINTERCREEK DR 68 TOMAHAWK LN HARLOW RD -580° NORTH OF HARLOW RD 69 TULIP ST CRESCENT AVE - HOLLY AVE 70 VAN NESS ST 23RD AVE - 27TH AVE 71 WASHINGTON ST 8TH AVE- 13TH AVE 72 WEST AMAZON ❑R ES HILYARD - SS FOX HOLLOW 73 WESTERN DR CALVIN ST- WEST END/MONROE MIDDLE SCHOOL 74 WILLAMETTE ST 24TH AVE - 29TH AVE 75 WILLAMETTE ST 10TH AVE - 13TH AVE 76 WOODSIDE DR CAL YOUNG RD- SHARON WAY 31