Laserfiche WebLink
<br />b. Two requests totaling $363,000 move resources from Balance Available to Capital appropriation. The first item appropriates <br />$260,000 for increased costs on the 3rd/4th Connector project due to additional street excavation, purchase of additional right of wa} <br />to address safety concems, additional storm drainage required due to underground springs, and higher than anticipated utility <br />relocation costs. Another action requests $103,000 for the city match for the North Bank Bike Path Rehabilitation project. The <br />federal STP-U funds for the project were programmed by the Metropolitan Policy Committee on July 15, 2005. <br />