3/28/2017 <br />Pre-ConstructionConstruction & Monitoring <br />• <br />Right-of-way acquisition delays <br />Construction <br />• <br />Administrative Order for driveway closures <br />• <br />6 months (2/16-8/16) <br />• <br />Utility Relocation <br />• <br />$1.3M (~$750K Brown Const. + <br />• <br />Rebid project <br />Materials/Equipment + Inspection) <br />• <br />Initial bid response too high <br />• <br />Monitoring additional $150K <br />• <br />Re-scoped project, materials purchase, <br />timing of bid, and schedule <br />Eugene City Council Work Session1/23/2017Eugene City Council Work Session1/23/2017 <br />2122 <br />Business AccessPavement Condition <br />Maintained access to businesses <br />• <br />Traffic control <br />• <br />Business open signs <br />Communication <br />• <br />Letters <br />• <br />In-person <br />Time of day <br />• <br />Signals & striping at night <br />• <br />Concrete hardscape in daytime <br />Eugene City Council Work Session1/23/2017Eugene City Council Work Session1/23/2017 <br />2324 <br />6 <br /> <br />