My WebLink
|
Help
|
About
|
Sign Out
Home
Browse
Search
Admin Order 58-20-26
COE
>
City of Eugene
>
Administrative Orders
>
2020
>
Admin Order 58-20-26
Metadata
Thumbnails
Annotations
Entry Properties
Last modified
8/25/2020 11:00:30 AM
Creation date
8/25/2020 10:55:01 AM
Metadata
Fields
Template:
City Recorder
CMO_Document_Type
Admin Orders
There are no annotations on this page.
Document management portal powered by Laserfiche WebLink 9 © 1998-2015
Laserfiche.
All rights reserved.
/
109
PDF
Print
Pages to print
Enter page numbers and/or page ranges separated by commas. For example, 1,3,5-12.
After downloading, print the document using a PDF reader (e.g. Adobe Reader).
View images
View plain text
2020 Eugene Wastewater Master Plan Chapter 6: Basis of Cost Estimates 50 <br />WASTEWATER PRESSURE LINES <br />Estimated construction costs for wastewater pressure lines are shown in Table 6-5. These costs were <br />developed by updating the ENR index from the 1992 Master Plan to the 2019 index of 11281 and <br />reviewing and comparing the values with recently bid projects. Costs are shown for two construction <br />conditions: 1) in paved street areas, which require imported granular backfill material and pavement <br />removal and restoration; and 2) in open areas, where surface restoration and utility conflicts are a <br />minimum. <br />Both conditions assume minimum trench depth with three feet of cover above the top of pipe. The <br />types of pipe material assumed for the various sizes are: <br />Pipe Size/Range Type of Pipe Material <br />6-inch to 27-inch PVC <br />30-inch and larger Concrete-encased steel <br /> <br />Table 6-5: Estimated Construction Cost for Wastewater Pressure Lines (Force Mains) <br />Pipe diameter (inches) <br />Estimated construction cost (per foot) <br />In paved areas2 In open areas1 <br />6 $66 $43 <br />8 $76 $53 <br />10 $93 $65 <br />12 $108 $75 <br />14 $156 $114 <br />16 $169 $125 <br />28 $255 $194 <br />30 $271 $210 <br />36 $417 $341 <br />42 $507 $425 <br />72 $899 $786 <br />Notes: ENR =11281 <br />1 Costs assume 3-foot depth of pipe cover, with imported granular backfill above the <br />pipe zone area and minimal surface restoration or utility conflicts. <br />2 Costs assume 3-foot depth of pipe cover, with imported granular backfill above the <br />pipe zone area and removal and restoration of pavement in trench area. <br /> <br />ADDITIONAL INFORMATION <br />The estimated construction costs included here are for high-level planning purposes. All construction <br />costs are influenced by the economy, time of bidding, difficulties of the specific project, and time <br />allowed for construction. Consideration of all factors should be included when preparing project-specific <br />estimates.
The URL can be used to link to this page
Your browser does not support the video tag.