Laserfiche WebLink
IMPLEMENTATION AND FINANCING PLAN <br />Project Title: <br />Employee Parking Lot Construction and Reconfiguration <br />Project Description: <br />Construct and reconfigure tenant and airport administration parking lot using single access control system. <br />Project Trigger: <br />Design of the new terminal and concourse expansion begins. <br />Project Justification: <br />The employee parking lot reconfiguration is an enabling project for the terminal ticketing and concourse expansion projects. <br />Project Schedule: <br />Procurement StartDesign StartConstruction StartConstruction End <br />2021 - Q12021 - Q22021 - Q42022 - Q2 <br />Budgeted Costs: <br />Planning/EnvironmentalA&E DesignConstructionProject Management <br />$0$119,000$1,190,000$119,000 <br />Equipment/Miscellaneous Budgeted Project Cost (2017 $)Budgeted Project Cost (Escalated) <br />$0$1,428,000$1,607,000 <br />Project Location: <br /> <br /> <br />EUGENE AIRPORT MASTER PLAN 5-54 <br /> <br />