Laserfiche WebLink
IMPLEMENTATION AND FINANCING PLAN <br />Project Title: <br />Environmental Assessment - Terminal Area and Landside Facilities <br />Project Description: <br />Environmental study conducted to analyze potential environmental consequences related to short-term (PAL 1) terminal area and <br />landside/roadway projects. <br />Project Trigger: <br />Begin EA study approximately two years prior to planned construction start date. <br />Project Justification: <br />Determine potential environmental impacts of short-term projects and meet NEPA requirements. <br />Project Schedule: <br />Procurement StartDesign StartConstruction StartConstruction End <br />2019 - Q4--2020 - Q4 <br />Budgeted Costs: <br />Planning/EnvironmentalA&E DesignConstructionProject Management <br />$300,000$0$0$0 <br />Equipment/Miscellaneous Budgeted Project Cost (2017 $)Budgeted Project Cost (Escalated) <br />$0$300,000$323,000 <br />Project Location: <br /> <br /> <br />EUGENE AIRPORT MASTER PLAN 5-45 <br /> <br />